| December 31 |
In CHE
Consulting, the Court of Appeals for the Federal Circuit
wound up a relatively quiet year in its bid protest
jurisdiction by affirming the Court of Federal Claims'
decision that a procuring agency acted rationally in bundling
hardware and software requirements into a a
single-provider solicitation. The protester had objected to
the lower court's allowing the agency to supplement the
record. The CAFC, however, reached its decision without
relying on the supplements. The CAFC did rely on the GAO's
1993 decision in National
Customer Engineering (B-251135) to support its
conclusions.
|
| December 30 |
The Prompt
Payment Act interest rate for the period January 1, 2009
through June 30, 2009 will be 5 5/8%.
The National
Science Foundation is proposing regulations to implement
the Program Fraud Civil Remedies Act of 1986. Comments are due
by January 29, 2009.
In States
Roofing, the ASBCA held that the "Permits and
Responsibilities" clause did not impose strict liability
on the prime for all actions of its subcontractors.
|
| December 29 |
Three
new SBA OHA size decisions
have been published. |
| December 25 |
Merry
Christmas! |
| December 23 |
In Spectrum
Sciences and Software, the Court of Federal Claims
delivered a stinging rebuke to the Government and held that
the Air Force repeatedly had improperly used proprietary
information concerning a company's munitions conveyor
equipment (which the company had provided under the supposed
restrictions of a Cooperative Research and Development
Agreement) to issue a solicitation for such equipment, reveal
proprietary details of the equipment to third parties,
and award a contract to one of the contractor's competitors
for equipment based on the improper disclosure of that
proprietary information. However, the aspect of the decision
that interests me the most is the color, digital photograph it
contains of the contractor's conveyor system. The internet and
digital technology continue to amaze and delight at least one
old man.
|
| December 20 |
In L-3
Communications Integrated Systems, the Court of Federal
Claims denied the Government's motion to dismiss a post-award
bid protest seeking bid and proposal costs. L-3 Communications
is the successor-in-interest by operation of law to the entire
business of the original offeror on the procurement (Raytheon
Systems Corporation). Therefore, the court rejected the
Government's contentions (i) that L-3 Communications
lacked standing because it was not the original offeror and
(ii) that the suit was barred by the Anti-Assignment Act (31
U.S.C. 3727). Concerning the latter contention, the court
wrote in part as follows: "By virtue of this acquisition
[of Raytheon], only L-3 possesses the right to pursue this
claim, and the evil the [Anti-Assignment] Act was designed to
prevent--subjecting the Government to multiple lawsuits for
the same claim--is not present here." The court also held
that the Administrative Dispute Resolution Act of 1966 did not
deprive the court of jurisdiction under 28 U.S.C. 1491(a)(1)
over L-3's theory of recovery based on an alleged breach of an
implied-in-fact contract.
Wackenhut
Services won big in its protest before the same court,
which ordered NASA to set aside a contract award, appoint new
members to the Source Evaluation Board (SEB), and also to
appoint a new Source Selection Authority (SSA) to re-evaluate
proposals and correct multiple errors in the original
evaluation, including possible undue influence by the SSA on
the SEB, a complete lack of a documented tradeoff analysis in
the final award decision by the SSA, and other unexplained
adjustments by the SEB and SSA related to various of the
evaluation factors. The court's disgust with the problems in
the original evaluation is palpable. One interesting aspect of
the case is that Wackenhut originally protested at the GAO,
lost there, and then filed this suit seven days later.
Persistence sometimes pays.
In Todd
Construction Co. the Court of Federal Claims held that an allegation that a contractor's
performance evaluation was issued without observing the proper
procedures and is substantively erroneous constitutes a
"claim" within the meaning of the CDA. See also
the BLR Group decision at the December 3 entry below.
|
| December 19 |
Effective
January 18, 2009, the DOL has amended the regulations at 29
C.F.R. Parts 3 and 5 to provide additional protections to worker
privacy under construction contracts covered by the
Davis-Bacon and Copeland Anti-Kickback Acts. Contractors
submitting weekly worker payroll information will need only to
identify individual workers by a unique code (e.g., the last
four digits of their social security numbers) rather than by
their full social security numbers and home addresses.
|
| December 18 |
The DoD
(DFARS Case 2008-D024) has issued an interim rule which authorizes the DoD to acquire
articles containing para-aramid
fibers and yarns manufactured in foreign countries that
have entered into a defense memorandum of understanding with
the United States.
In Devi
Plaza, the CBCA held that the Contracting Officer's
willingness to discuss settlement with the contractor after
issuing the Contracting officer's decision tolled the
90-day appeal period even though the Contracting Officer had
twice written the contractor to remind him that the original
decision had included a statement of his appeal rights.
Not sure I agree with this one.
|
| December 17 |
In Alliance
General Contractors, the ASBCA rejected a defective
specification claim primarily because there was no basis to
interpret the drawings as the contractor wished, i.e., by
giving one of them precedence over the others. As a side note,
the Board found the contractor had not established a causal
link between the allegedly defective drawing and the alleged
harm: "the testimonial evidence proffered to show that
following the drawings led directly to excess 'great big piles
of dirt' is vague, puzzling, and entirely unpersuasive."
In Freedom
NY, the Board provided guidance to the parties concerning
(i) the concept of substantial justification and (ii) the
calculation and apportionment of Equal Access to Justice Costs
on various claims for Contract Disputes Act interest and
Prompt Payment Act interest when the contractor had originally
prevailed on only some of its claims and had rejected
substantial settlement offers from the Government.
|
| December 15 |
The SBA's
Office of Hearings and Appeals (OHA) has published a batch of
new decisions, including two that are instructive concerning
how it analyzes the "ostensible subcontractor" rule:
TCE
Inc. and Public
Communications Services. In addition to the newly
published size decisions, the OHA also has published several
new NAICS code decisions, including one in which it found Genome-Communications
lacked standing to challenge the NAICS code on an unrestricted
procurement, reasoning in part as follows: "This Office has consistently held that
a small business lacks standing to appeal the NAICS code
classification of an unrestricted solicitation unless the firm
can demonstrate that it has been adversely affected. NAICS
Appeal of Integrated Laboratory Systems, Inc., SBA No.
NAICS-4733, at 2 (2005). The size standard here does not
affect Appellant's eligibility to participate in the contract
process, nor does it appear to affect award." Finally,
the OHA has issued several new "VET" decisions
concerning whether firms are owned and controlled by
service-disabled veterans. All the new decisions, plus other
SBA OHA decisions from 2007-2008 are listed elsewhere on my SBA OHA webpage. You may also
find discussions of some of the more important decisions in
the SBA OHA portion of the 2008
Procurement Review.
|
| December 13 |
In The
Boeing Co, Successor-in-Interest to Rockwell International
Corp., the CBCA held that the contractor could recover its
defense costs associated with those counts on which it had
prevailed in a suit filed against it under the False Claims
Act, even though though the contractor was found liable on
other counts in the same suit.
|
| December 9 |
Effective
January 8, 2009, the GSA is amending (rewriting) GSAR
Part 533 (Protests, Disputes, and Appeals)--GSAR Case
2007-G501.
The latest Corners
and Edges decision at the ASBCA is a reminder that
contractors should only accept directions that change the
contract from the Contracting Officer.
While we're on
the subject of reminders, Parsons
Transportation Group serves as a good reminder of the
importance of paying attention to the release language when
drafting contract changes or settlements.
|
| December 7 |
In Lublin
Corp., the Court of Federal Claims held that 31 U.S.C.
1501(a) is not a statute of frauds that precludes the
existence of an oral contract involving the federal
government.
|
| December 5 |
Effective
December 22, the SBA is waiving
the Nonmanufacturer Rule for Control Cable and Conductors,
Trailers and Heavy Duty Truck Tractors, and Line Hardware
(Insulator Strings) Manufacturing.
|
| December 4 |
After
three rounds of preliminary skirmishes, the ASBCA finally has
issued its decision on the merits in SUFI
Network Services, and the decision is a smorgasbord of
claim issues, theories, and defenses, including, inter alia,
breach of duty to cooperate and duty of good faith dealing,
misrepresentation, contract interpretation, contemporaneous
interpretation, course of dealing, ratification, burden of
proof, lost revenues, lost profits, claim preparation
expenses, and consulting fees.
|
| December 3 |
In BLR
Group of America, the Court of Federal Claims held that it
had jurisdiction under the Contract Disputes Act (CDA) over a
complaint filed by a contractor based on the Contracting
Officer's failure to decide the contractor's nonmonetary claim
that a Contractor Performance Assessment Report (CPAR) was
inaccurate and should be corrected. The decision is
interesting and important on several levels. First, it
declines to follow a line of ASBCA decisions that indicate
quarrels over CPARs are not CDA claims. Secondly, it finds the
requirements for a claim met when the contractor simply
requested the Government to change the CPAR, without labeling
the request a claim. Third, it reasons that a claim may be
based on an assertion of any legal right, not necessarily a
right that is explicitly expressed in the contract at issue.
Finally, the court notes that recognizing such challenges to
CPARs as claims (rather than requiring the contractor to wait
and file a protest when the challenged CPAR actually has
adverse consequences on a subsequent procurement) serves the
interests of contract administration because a bid protest
significantly interferes with, even disrupts, the procurement
process, whereas a contract dispute under the CDA does
not.
|
| December 2 |
Effective
for one year beginning December 17, the DoD is waiving
the limitation of 10 U.S.C. 2534 (which limits DoD procurement
of certain items to sources in the national technology and
industrial base) for certain defense
items produced in the United Kingdom.
The GSA
(GSAR Case 2008-G509) is proposing to rewrite GSAR
Part 536 concerning Construction and Architect-Engineer
Contracts. Comments are due by February 2, 2009.
In Oregon
Woods, the CBCA held that a Contracting Officer did not
abuse his discretion in terminating for convenience a faulty
contract whose specifications would require an indeterminate
amount of time to review and correct.
|
| November 25 |
In its post-award protest at the Court of Federal
Claims, Lumetra
claimed, inter alia, that the Government had failed to
provide it with the opportunity to respond to a negative
in-progress performance evaluation. The court conceded that
the Government neglected to comply with a FAR 42.1503(b)
requirement that the contractor be permitted to submit
comments, additional information, or rebuttals concerning the
evaluation, but (in a somewhat tortured argument that left me
lukewarm) held that the Government's failure was not
prejudicial because Lumetra had other means to address the
alleged performance issues.
The GAO sustained a protest by Burchick
Construction Co. because the VA failed to conduct
meaningful discussions regarding weaknesses in several parts
of Burchick's technical proposal, including its past
performance, small business participation, and quality control
plan.
|
| November 24 |
The DoD
(DFARS Case 2005-D015) has adopted as final, without change,
the interim rule amending the DFARS to update requirements for
reporting
of government property in the possession of DoD
contractors. The final rule replaces DD Form 1662 reporting
requirements with requirements for DoD contractors to
electronically submit, to the Item Unique Identification
(IUID) Registry the IUID data applicable to the government
property in the contractor's possession.
The DoD
(DFARS Case 2007-D021) also has issued a final rule amending
the DFARS to address review and documentation requirements
pertaining to the use of time-and-materials
contracts for the acquisition of noncommercial services.
The rule provides for the same level of review for both
commercial and non-commercial DoD time-and-materials
contracts.
The DoD
(DFARS Case 2008-D019) also has issued a final rule revising
the list of "least
developed" countries that are designated as eligible
countries under the Trade Agreements Act (adding Liberia and
removing Cape Verde) in accordance with direction from the
United States Trade Representative.
|
| November 21 |
In DCMS-ISA,
the Court of Federal Claims upheld the Government's decision
to cancel an SDVOSB set-aside because none of the offerors
possessed sufficient past performance experience. The court
rejected the offerors' contention that the matter should have
been referred to the SBA for a responsibility determination.
|
| November 20 |
In Palm
Springs General Trading and Contracting Establishment, the
ASBCA denied a motion to stay an appeal pending criminal
proceedings because, inter alia, the Government failed
to show that there were substantial similarities of facts,
issues, and witnesses between the ongoing criminal
investigation and the board appeals.
|
| November 18 |
Comments
are being sought (i) on proposed FAR revisions that would
require contractors selling information technology (IT) products (including computer
hardware and software) to represent that such products are authentic,
(ii) concerning contractor liability if IT products sold to
the Government by contractors are not authentic, (iii)
on whether contractors who are resellers or distributors of
computer hardware and software should represent to the
Government that they are authorized by the original equipment
manufacturer to sell the information technology products to
the Government, (iv) on whether the measures contemplated
above should be extended to other items purchased by the
Government; and (v) on whether the rule should apply when
information technology is a component of a system or assembled
product.
The Bureau
of Industry and Security in the Commerce Department has
published a final rule revising the Export Administration
Regulation (EAR) to clarify
that a party cannot proceed with an export, reexport, or
transfer (in-country) that is in transit at the time the party
is informed by BIS that a license is required (in accordance
with certain end-user/end-use controls in the EAR), unless
that party first obtains a license from BIS authorizing the completion
of the transaction. These changes are intended to enhance
the ability of BIS to stop items subject to the EAR, including
items not on the Commerce Control List, from being exported,
re-exported or transferred (in-country) when there is an
unacceptable risk that such items will be used in, or diverted
to, any of the proliferation activities specified in certain
sections of the EAR. The new rule also amends the EAR by
revising the definition of the term "transfer"
and certain related terms, to provide greater clarity
regarding these provisions.
|
| November 14 |
Federal
Acquisition Circular (FAC) 2005-29 has been published. It
includes FAR Case 2007-013, Employment
Eligibility Verification, which requires certain
contractors and subcontractors to utilize the E-Verify
system administered by the Department of Homeland Security as
a means of verifying that certain of their workers are
eligible to work in the United States. The effective date is
January 15, 2009.
In ASRC
Research & Technology Solutions, the GAO sustained a
protest against a NASA evaluation that was flawed in its
analysis of (i) the technical risk associated with the costs
of hiring incumbent personnel and (ii) the differences in size
between the protested contract and the awardee's past
performance references.
|
| November 12 |
Effective
today, Federal Acquisition Circular (FAC) 2005-28 (FAR Case
2007-006), Contractor
Business Ethics Compliance Program and Disclosure
Requirement, amends the FAR and implements Public Law
110-252, Title VI, Chapter I (the "Close the Contractor
Fraud Loophole" Act) to amplify the requirements for a
contractor code of business ethics and conduct, an internal
control system, and disclosure to the Government of certain
violations of criminal law, violations of the civil False
Claims Act, or significant overpayments.
I fell a
bit behind on CBCA
decisions because I allowed one of my bookmarks to fall
out of date, but I've caught up now.
In Wheeler
Logging (over a well-written dissent), the CBCA dismissed
several revised claim elements in a contractor's appeal for
lack of a certification because: (i) there was a significant
change to the claim elements, amounts, and supporting data,
(ii) the changes occurred prior to the onset of active
litigation, and (iii) the changes were based on facts that
were in the contractor's possession at the time it filed the
original certified claim.
|
| November 10 |
In Beyley
Construction Group, the ASBCA denied claims for changed
conditions based on a theory of quantum meruit because there
was no evidence of an implied-in-fact contract and because the
contractor's evidence for its cost estimates was
"incomprehensible."
|
| November 6 |
In Rothe
Development Corp., the Federal Circuit held that 10 U.S.C.
2323 is unconstitutional because, in passing it, Congress did
not have a "strong basis in evidence" to conclude
that DOD was a passive participant in racial discrimination in
relevant markets across the country and that race-conscious
remedial measures were necessary. The Act (i) sets a
"goal" that five percent of federal defense
contracting dollars for each fiscal year be awarded to certain
entities including small business concerns owned and
controlled by "socially and economically disadvantaged
individuals"; (ii) incorporates the Small Business Act's
presumption that Black Americans, Asian Americans, Hispanic
Americans, and Native Americans are socially disadvantaged
individuals; and (iii) provides that the Department of Defense
shall give specified forms of assistance to the listed
entities and may, when practicable and necessary to achieve
the five percent goal, make advance payments to those entities
and award contracts to them at prices up to ten percent above
fair market cost.
|
| November 5 |
I still
remember as a young boy (50 years ago) visiting my grandmother
and watching her get up from her chair and turn off the
television set each time she saw a Black person appear on the
TV screen. We've come a long way since then. Congratulations
to all of us on our new President. Well done, America.
|
| October 31 |
In the
size appeal of Novalar
Pharmaceuticals, the SBA had occasion to utilize its
single-largest and multiple-largest minority shareholder rules
in finding affiliation between a number of companies.
|
| October 27 |
The DoD is
proposing to add a section 207.172 (and a contract clause) to
the DFARS to address requirements for the protection
of human subjects involved in research projects (DFARS
Case 2007-D008). Comments
are due by December 26.
|
| October 24 |
The
Department of Energy has issued a Revised Policy Statement on
the use of alternative
dispute resolution (ADR).
In Nortel
Government Solutions, the Court of Federal Claims
invalidated the DEA's override of an automatic stay pending a
GAO protest. Do we have a trend developing here? See also
the E-Management Consultants decision at the October 22 entry
below.
|
| October 23 |
The
Department of Agriculture is proposing to amend the Guidelines for
Designating Biobased
Products for Federal Procurement, by adding nine sections
to designate the following nine items within which biobased
products would be afforded federal procurement preference:
chain and cable lubricants; corrosion preventatives; food
cleaners; forming lubricants; gear lubricants; general purpose
household cleaners; industrial cleaners; multipurpose
cleaners; and parts wash solutions. USDA also is proposing
minimum biobased content for each of these items. The
authority for the proposed changes is section 9002 of the Farm
Security and Rural Investment Act of 2002 (FSRIA), as amended
by the Food, Conservation, and Energy Act of 2008 (FCEA), 7
U.S.C. 8102. Comments are due by December 22.
|
| October 22 |
The Court
of Federal Claims issued its latest decision in the Watts-Healy
Tibbitts protest, dissolving the preliminary injunction it
had issued previously. The court determined that the
Government had complied with the court's order to conduct a
new responsibility determination, which was neither arbitrary
nor capricious, even though the court might not agree with its
conclusions. See also entry at August 11 below.
In E-Management
Consultants, the Court of Federal Claims voided an agency's override of the
automatic stay issued during pendancy of a GAO protest because
the agency failed to consider the impact of the stay on the
procurement system and made an inadequate cost-benefit
analysis, which did not establish that serious consequences
would befall the agency in the absence of the override.
In Comptech,
the ASBCA went through a lengthy and detailed analysis of the
legal status of unilateral purchase orders before concluding
that the Government properly canceled such an order because
the contractor failed to deliver conforming supplies within
the required time.
|
| October 20 |
The DoD
has amended the DFARS (section 215.370) to implement Section
819 of the National Defense Authorization Act for Fiscal Year
2006, which authorizes the DoD to use an evaluation factor
reflecting whether an offeror intends to perform a contract
using employees or individual subcontractors who are members
of the Selected
Reserve.
The DoD
has issued a proposed rule designed to ensure the accuracy of
the information in the Central
Contractor Registration (CCR) database. Comments are due
by December 19.
The
Department of Labor has issued a proposed rule that would
reduce the amount of personal
data concerning individual workers in reports required by
the Davis-Bacon and Copeland Anti-Kickback Acts, in order to
protect workers' privacy. Comments are due by November 19.
In The
Management Consulting Group, the SBA's Office of Hearings
and Appeals criticized (but could do nothing about) several
SBA practices for determining whether individuals are
economically disadvantaged: "Although SBA's current
practice of determining income is the law, the practice
results in unintended inequities because the SBA fails to (1)
consider inflation, (2) distinguish between initial 8(a)
eligibility income thresholds and continuing eligibility
income thresholds to account for business growth (as is done
with net worth determinations, 13 C.F.R. 124.104(c)(2)), (3)
consider deductible expenses, such as medical expenses, and
instead considers adjusted gross income, without exception,
(4) evaluate geographical cost of living differences in
assessing the value of income, and (5) treat each business
similarly irrespective of its business organizational
form."
|
| October 18 |
In Access
Systems, the Court of Federal Claims held that the award
of a bridge contract to the incumbent during the pendancy of a
GAO protest does not constitute the override of an automatic
stay of the protested procurement.
|
| October 16 |
In Delex,
the GAO held that FAR 19.502-2(b) concerning set-asides for
small businesses applies to competitions for task and delivery
orders under multiple-award contracts and that a solicitation
for a delivery order under one such NAVAIR contract should
have been set aside for small businesses rather than being
issued on an unrestricted basis.
|
| October 14 |
The GAO
has issued the final rules
of procedure for the GAO Contract Appeals Board.
|
| October 10 |
The GSA is
proposing a rewrite of GSAR Part 514, Sealed
Bidding (GSAR Case No. 2008-G505). Comments are due by
December 9.
The SBA is
considering granting a waiver of the nonmanufacturer
rule for Control Cable and Conductors, Trailers and Heavy
Duty Truck Tractors, and Line Hardware (Insulator Strings)
Manufacturing.
|
| October 9 |
The GSA is
proposing rewrites of: (i) GSAR Part 504, Administrative
Matters (GSA Case No. 2006-G510); and (ii) GSAR Part 511, Describing
Agency Needs (GSA Case No. 2007-G507). Comments are due by
December 8.
Alabama
Aircraft won its protest at the Court of Federal Claims
against the Air Force's contract award to Boeing for
maintenance and modifications to the KC-135 Stratotanker fleet
because of the agency's faulty price realism analysis of
Boeing's proposal. The court issued an injunction setting
aside the award and requiring the agency to resolicit.
Specifically, the agency failed to take into account the
rapidly aging fleet in analyzing Boeing's price realism.
The GAO
sustained a protest by Helicopter
Transport Services in part because the agency did not
produce documentation of its past performance discussions or
evaluation.
|
| October 8 |
The
Civilian Board of Contract Appeals issued several new decisions.
One of them is Tidewater
Contracting. Tidewater originally submitted a claim for an
extension of the contract time/period of performance. After
its appeal of the denial of that claim had been docketed by
the Board, the Government assessed liquidated damages against
Tidewater. Tidewater now argues its original appeal should
cover that assessment. The Board rejects Tidewater's
contention because Tidewater never submitted a claim to the
Government for return of the liquidated damages. Something
about this decision bothers me. It seems to me that I've seen
decisions in other fora in which claims for time extensions
and those for liquidated damages have been seen to be
intertwined. Moreover, couldn't the assessment of
liquidated damages in this situation be considered a
government claim?
|
| October 7 |
The GSA is
proposing to rewrite GSAR Part 532, Contract
Financing (GSAR Case 2006-G515). Comments are due by
November 6.
|
| October 6 |
The
Architect of the Capitol proposes to implement a small-business
set-aside program for small purchases. Comments are due by
November 5.
The
Commerce Department's Bureau of Industry and Security (BIS)
has published a significant number of changes to the Export
Administration Regulations (EAR) based on a a systematic
review of the Commodity Control List (CCL).
The State
Department has added Eritrea
to its International Traffic in Arms (ITAR) regulations on
prohibited exports and sales to certain countries as a result
of its designation as a country not cooperating fully with
antiterrorism efforts.
In a
consolidated protest by Femme
Comp, among several others, the Court of Federal Claims
found the Army's Source Selection Authority improperly
converted what should have been a best value trade-off among
the evaluation factors listed in the solicitation into simple
technically acceptable, low price award decisions. The Court
ordered the Army to reevaluate using the correct
methodology.
|
| October 3 |
The GSA
(GSAR Case 2008-G506) is proposing a rewrite of GSAR Part 515,
Contracting
by Negotiation. Comments are due by December 2.
The
Commerce Department's Bureau of Industry and Security (BIS)
has proposed to amend the Export Administration Regulations
(EAR) to establish a new license exception entitled "Intra-Company
Transfer (ICT)," which (with prior authorization from
BIS) would allow an approved parent company and its approved
wholly-owned or controlled in fact entities to export,
reexport, or transfer (in-country) many items on the Commerce
Control List (CCL) among themselves for internal company use.
Comments are due by November 17.
The SBA
has issued revised rules concerning its Small
Disadvantaged Business (SDB) Program. Specifically, the
rule allows firms to self-represent their SDB status without
first receiving any SDB certification. It also recognizes that
the benefits of being an SDB for federal prime contracts
have diminished and shifts the responsibility of
identifying firms as SDBs for federal prime contracts to those
limited agencies that have authority and choose to use price
evaluation adjustments for SDBs.
L-3
Communications EoTech won its protest at the Court of
Federal Claims, which issued an injunction in its favor
because the Government relaxed and waived mandatory
solicitation requirements for only one offeror, failed to seek
readily available clarifications from the protester, and
irrationally established a competitive range of (and then
conducted further discussions only with) one offeror.
|
| October 1 |
The
Commerce Department is
revising the provisions of the Export Administration
Regulations (EAR) relating to foreign-made items that
incorporate controlled U.S.-origin items, the so-called "de
minimis" rules. Specifically, the revised rules
(i) change the de minimis calculation for foreign
produced hardware that is bundled with U.S.-origin software;
(ii) clarify the
definition of 'incorporate' as it applies to the de minimis rules and
to the medical statement of understanding; (iii) remove the
requirement to submit a one-time report to the Bureau of
Industry and Security for foreign-made software that
incorporates U.S.-origin software, and (iv) revise the
"Steps for Using the EAR" and General Prohibition
Two with regard to the de minimis rules.
The SBA
has published a final rule, effective October 31, to set forth
procedures that will govern the new Women-Owned
Small Business (WOSB) Federal Contract Assistance
Procedures as authorized in the Small Business Act. The rule
does not identify the industries in which WOSBs are underrepresented
or substantially underrepresented in Federal procurement
because SBA is awaiting comments on a proposed rule in that
area before concluding its eligibility determinations.
In White
Hawk/Todd, the OHA held that area offices may not review
mentor-protege eligibility issues in 8(a) procurements. In DCS
Night Vision JV, the OHA had occasion to clarify White
Hawk in a situation where a firm contended that it assumed the
SBA had extended its mentor-protege agreement past its
expiration date because the firm had not heard anything to the
contrary from the SBA. The OHA also published decisions in
four other size appeals, a
NAICS
appeal concerning a solicitation for counterintelligence
services, and two other NAICS decisions.
|
| September 30 |
If you
would like to find a specific 2008 development without
scrolling through nine months worth of entries in this blog
(or using the ctrl-f keys), please try the 2008
Procurement Review. I am keeping it fairly current with
this blog, and it is indexed.
|
| September 25 |
The State
Department is removing Rwanda
from the ITAR provisions on prohibited exports and sales to
certain countries as a result of United Nations Security
Council Resolution 1823, which terminated remaining arms
sanctions against that
country. The ITAR also is being amended to increase the registration
fees, change the registration renewal period, and make
other minor administrative changes.
|
| September 24 |
DFARS Case
No. 2007-D020 (Government
Property)--The DoD is proposing to amend the DFARS to
update text addressing the management of government property
in the possession of contractors. The DFARS changes are
consistent with changes made to the FAR. Comments are due by
November 24.
|
| September 23 |
In Dionyx,
Judge Miller excoriated the Government for making "the
senseless jurisdictional argument that an agency arbitrarily
can declare a protested proposal to be nonconforming, while
accepting the awardee's allegedly nonconforming proposal, and
thereby preclude the protestor from standing to challenge the
award." Warming to its task, the court also roundly
criticized several CoFC decisions regarding a protester's
"standing" because they improperly applied the
concepts of responsiveness and noncompliance to negotiated
procurements. Although Judge Miller is quite clear about what
she dislikes, she is somewhat less successful articulating
what the analysis should be, beyond the repeated admonition
that one should follow the CAFC's decision in Rex Serv.
Corp. v. United States, 448 F.3d 1305, 1307 (Fed. Cir.
2006).
Until such
time as it may lift this suspension of activities, the SBA is
no longer receiving applications for admission into the Small
Disadvantaged Business Program. Since 1994, the SBA has
processed these applications on behalf of all federal
procuring agencies. In December 2004, however, the price
evaluation preference for such businesses lapsed for most
federal agencies, and the remaining agencies have become more
reluctant to reimburse the SBA for the costs of its
administration of the program. Hence, the suspension while the
SBA reassesses the situation.
|
| September 22 |
In Veridyne,
the Court of Federal Claims decided that disputed facts
precluded summary judgment on the Government's contention that
fraud allegations merited forfeiture of the plaintiff's claim.
In providing guidance for the upcoming trial on the merits,
the court stated in part as follows: "The court takes this opportunity to
caution the parties that the law does not absolve a contractor
of a fraudulent representation, even if government personnel
are implicated or cognizant or participatory. The brand of
fraud, however, will be cosmetic and not require forfeiture of
all monies already paid or due and owing for services rendered
insofar as the fraudulent activities do not transcend that
level of deceit that amounts to engaging government personnel
in a conflict of interest or affording them some pecuniary
gain." 
|
| September 19 |
In Delmarva
Power & Light, the Court of Appeals for the Federal
Circuit recognized the Government's power to waive the
prohibition against the assignment of claims against the
Government in the Anti-Assignment Act, 31 U.S.C. 3727(a).
The GAO
sustained a protest by AT&T
Government Solutions because the Navy rejected its
proposal due to a perceived organizational conflict of
interest ("OCI") without evaluating the mitigation
plan included with the proposal and without giving AT&T
the opportunity to correct the perceived deficiencies in its
proposal, when the company's products that allegedly created
the OCI were not even available for purchase by the agency.
The
General Services Administration (GSAR Case 2008-G517) has
amended the GSAR to implement Pub.L. 110–248, The Local
Preparedness Acquisition Act, which authorizes the use by
state or local governments of GSA Federal
Supply Schedules (FSS) for alarm and signal systems,
facility management systems, firefighting and rescue
equipment, law enforcement and security equipment, marine
craft and related equipment, special purpose clothing, and
related services (as contained in Federal supply
classification code group 84 or any amended or subsequent
version of that classification group).
NASA
proposes to amend the procedures in the NASA FAR Supplement
relating to the mentor-protege
program to streamline the program; align the mentoring to
technical skills; expand the program to include Small
Disadvantaged Businesses (SDB), women-owned small businesses,
HUBZone small businesses, veteran-owned and service-disabled
veteran-owned small businesses, Historically Black Colleges
and Universities, minority institutions of higher education,
and NASA Small Business Innovation Research (SBIR) Phase II
small businesses; and include award fee incentives. Comments
are due by November
18.
The State
Department is amending the ITAR to clarify that certain
anti-tumor drugs are not within the definition of "chemical
agents."
|
| September 18 |
Five ASBCA decisions have
been published. In Corners
and Edges, the ASBCA held it had jurisdiction over a
notice of appeal mailed before the date the CBCA became
effective but received by the ASBCA after that date. In Qatar
International Trading, the Board held that the
Government's defense in tort did not divest the Board of
jurisdiction over the contractor's claim (the contractor had
claimed that the Government failed to pay satellite phone
service charges for calls made from cell phones delivered to
the Government by the contractor; the Government claimed the
calls had come from cloned cell phones, i.e., had been made by
tortfeasors).
Several CBCA decisions
also have been published. In Omegaman
Fireprotection, the Board held it lacked jurisdiction over
what was essentially a bid protest because there was no
contract between the claimant and the Government. Often it's
the contractor that is bitten by the release language in a
termination settlement agreement. In Government
Marketing Group it was the Government's claims that were
precluded by such a release.
|
| September 17 |
Federal
Acquisition Circular (FAC) 2005-27
has been published. It includes the following items: (i) FAR
Case 2007-020, entitled "Correcting Statutory References
Related to the Higher Education Act of 1965," a final
rule to reflect citation changes necessitated by the Higher
Education Amendments of 1998; (ii) FAR Case 2008-001,
entitled "Changing the Name of the Office of Small and
Disadvantaged Business Utilization for DoD," a final rule
which substitutes the new name of Office
of Small Business Programs; (iii) FAR Case 2007-015,
entitled "Changes to the FPI Blanket Waiver and the JWOD
Program Name," a final rule to increase the blanket
waiver threshold for small dollar-value purchases from
Federal Prison Industries (FPI) by Federal agencies from $2500
to $3000 and to change the name of the JWOD Program to the
AbilityOne Program; (iv) FAR Case 2006-014, entitled
"Local Community Recovery Act of 2006," a final rule
implementing amendments to the Robert T. Stafford Disaster
Relief and Emergency Assistance Act (42 U.S.C. 5150)
concerning set-asides
for major disaster or emergency assistance acquisitions to
businesses that reside or primarily do business in the
geographic area affected by the disaster or emergency; (v) FAR
Case 2007-007, entitled "Additional Requirements for
Competition Advocate Annual Reports, a final rule requiring
that annual reviews by executive
agency competition advocates be provided in writing to
both the agency senior procurement executive and the agency
chief acquisition officer, if designated, and that the reports
specifically address the quality of planning, executing, and
managing of task and delivery orders over $1 million; (vi) FAR
Case 2005-018, entitled "Contract Debts," a
significant final rule that revises the FAR's policies and
procedures concerning contract
debts; (vii) FAR Case 2007-022, entitled "Subcontractor
Requests for Bonds," a final rule to clarify that the
‘‘Prospective Subcontractor Requests for Bonds’’
clause does not apply to commercial items; (viii) FAR Case
2008-002, entitled "Extension of Authority for Use of
Simplified Acquisition Procedure for Certain Commercial
Items," which extends until January 1, 2010, the
timeframe in which an agency may use simplified
procedures to purchase commercial items in amounts greater
than the simplified acquisition threshold, but not exceeding
$5,500,000 ($11 million for acquisitions as described in
13.500(e)); (ix) FAR Case 2008–006, entitled "Enhanced
Competition for Task and Delivery Order Contracts—Section
843 of the Fiscal Year 2008 National Defense Authorization
Act," an interim rule which (a) prohibits issuing a task
or delivery order exceeding $100 million without special
authorization, (b) provides additional competition
requirements for orders in excess of $5 million, and (c)
establishes the right to protest
to the GAO for orders in excess of $10 million; (x) FAR
Case 2006-025, entitled "Online Representations and
Certifications Application Review," a final rule revising
the prescription for use of clauses for the use of Environmental
Protection Agency-designated products and toxic chemical
release reporting; (xi) FAR Case 2007-002, entitled
"Cost Accounting Standards (CAS) Administration and
Associated Federal Acquisition Regulation Clauses," an
interim rule to revise the FAR
CAS administration clauses to maintain consistency between
the FAR and CAS and to reflect various amendments made by the
CAS Board on June 14, 2007; (xii) FAR Case 2006-004, Entitled
"CAS Administration," a final rule related to CAS
administration in contracts with foreign
firms; and (xiii) FAR Case 2006-027, entitled
"Accepting and Dispensing of $1 Coin," a final rule to implement Section 104 of the
Presidential $1 Coin Act of 2005, which requires that entities
that operate any business on any premises owned or controlled
by the United States be capable of accepting and dispensing $1
coins on January 1, 2008.
|
| September 16 |
GSAR Case
2008-G503: The GSA is proposing to rewrite Part
505 of the GSAR, entitled "Publicizing Contract
Actions." Comments are due by November 17.
|
| September 15 |
Several DFARS amendments are out. DFARS
Case 2008-D002 (entitled Acquisitions in Support of
Operations in Iraq or Afghanistan) is an interim rule amending
the DFARS to
implement Sections 886 and 892 of the National Defense
Authorization Act for Fiscal Year 2008. Section 886 provides
authority for DoD to limit competition when acquiring products
or services in support of operations in Iraq or Afghanistan.
Section 892 addresses competition requirements for the
procurement of small arms for assistance to Iraq or
Afghanistan. DFARS
Case 2008-D013, entitled Limitation on Service Contracts
for Military Flight Simulators, is a final rule implementing
Section 883(b) of the National Defense Authorization Act for
Fiscal Year 2008, which changed the conditions under which DoD
may waive the prohibition on entering into a service contract
to acquire a military flight simulator. Specifically, it adds
a provision that allows a waiver of the general prohibition if
the Secretary of Defense determines it to be in the national
interest. DFARS
Case 2006-D050, Security Guard Functions, is an interim
rule extending through September 30, 2012, the period during
which contractor performance of security-guard functions at
military installations or facilities is authorized to fulfill
additional requirements resulting from the terrorist attacks
on the United States on September 11, 2001.
The Postal
Service Board of Contract Appeals has published two decisions. In one, a
postal delivery contractor was terminated
for default because he refused to comply with a unilateral
contract amendment requiring him to deliver mail by driving
down a gravel rural driveway that he considered unsafe. He
lost his appeal because, after having had the driveway
inspected, the Postal Service determined it to be narrow, but,
nonetheless, safe.
Career
Training Concepts ("CTC") lost its post-award
protest at the Court of Federal Claims. Its primary argument
was that an email to all offerors from the Contracting Officer
extending the date for receipt of proposals was ineffective
because it was not a formal solicitation amendment. The court
found that the email, especially when coupled with the
Government's change of the due date for proposals on the GSA's
e-Buy website, sufficed. The case also involved the
protester's complaints about "discussions" that
allegedly occurred. The court viewed the protester's somewhat
unusual arguments in this regard as follows: "CTC
apparently believes that it was given an opportunity to
materially revise its proposal, while [the awardee] was only
given the opportunity to clarify its proposal, and that any
additional opportunity the agency afforded CTC may be employed
to undo a competition it did not win. The record does not
support CTC’s view of the exchanges."
|
| September 12 |
In Metric
Construction Co., the Court of Federal Claims found the
Government's position in litigation was substantially
justified and precluded an award of fees under the Equal
Access to Justice Act even though (i) the contractor prevailed
on the majority of its claim and (ii) the Government made
almost no attempt to rebut the plaintiff's application for
attorneys' fees because: "It was reasonable for the
Government to have litigated this dispute to its
conclusion."
|
| September 8 |
HUD proposes to revise its regulations
implementing the Program
Fraud Civil Remedies Act. Comments are due by November 7.
A bunch of new SBA
OHA decisions are out.
|
| September 3 |
The Forest Service proposes several amendments
to its regulations concerning timber
sales contracts. Comments are due by October 3.
The Court of Federal Claims has issued three more
decisions in the Chevron U.S.A. equity process agreement
dispute: one denying the Government's motion to dismiss
certain parts of the complaint (concerning the issue whether
certain breaches were "material") for lack of jurisdiction;
anther denying the Government's motion to certify the court's
earlier discovery orders for interlocutory
appeal; and the third mostly denying the Government's
requests for reconsideration of the court's earlier rulings on
the Government's claims of attorney-client
privilege for various documents.
|
| September 2 |
The Office
of Federal Procurement Policy (OFPP) from the Office of
Management and Budget (OMB) has issued an Advance Notice of
Proposed Rulemaking to harmonize CAS
412 and 413 with the Pension Protection Act of 2006.
Comments are due by November 3.
Effective
today, the Bureau of Industry and Security is amending the
Export Administration Regulations (EAR) to establish export
licensing requirements for Kosovo.
|
| August 28 |
Effective
today, the GSA is revising the Federal Management Regulation
to clarify and amend its coverage of the replacement of
personal property pursuant to the exchange/sale
authority.
In Distributed
Solutions, Inc., and STR. L.L.C., the Court of Appeals for
the Federal Circuit reversed the prior
decision by the Court of Federal Claims and held that the
lower court had jurisdiction over a protest against the
Government's decision to abandon a proposed competition in
favor of permitting a current prime to procure items by
soliciting various subcontractors. The issue was the
meaning of the phrase "in connection with a procurement or
proposed procurement" in the Tucker Act, as amended
by the Administrative Dispute Resolution Act.
|
| August 27 |
In Benjamin
& Shaki Alli and BSA Corp., the Court of Federal
Claims discussed the elements of proof for breach claims by
and against the United States in the context of substandard
conditions at properties involved in HUD housing subsidence
programs.
|
| August 21 |
L-3
Global Communications Solutions lost its protest at the
Court of Federal Claims. L-3 complained that the awardee based
its offer on using a company other than the one required by
the solicitation for certain contract work. The court rejected
the protest because the awardee did not express this intent in
its proposal, but, instead, promised to comply with all
material solicitation requirements. Moreover, the Government
rejected the awardee's efforts to switch to the unapproved
company after award.
|
| August 20 |
The
Department of Veterans Affairs (VA) proposes to amend its
acquisition regulation (the VAAR) to implement portions of the
Veterans
Benefits, Health Care, and Information Technology Act of 2006
and Executive Order 13360 (Providing Opportunities for
Service-Disabled Veteran Businesses to Increase Their Federal
Contracting and Subcontracting). Together, the statute and
executive order authorize the VA to establish special methods
for contracting with service-disabled veteran-owned small
businesses (SDVOSBs) and veteran-owned small businesses
(VOSBs). Under the proposed changes to the VAAR, a VA
contracting officer could restrict competition in contracting
for SDVOSBs or VOSBs under certain conditions. Likewise, sole
source contracts with SDVOSBs or VOSBs would be permitted
under certain circumstances. Comments are due by October 20.
In the Tyler
Construction Group protest, the Court of Federal Claims
decided several interesting issues of statutory construction
and regulatory interpretation concerning, inter alia,
the use of ID/IQ contracts for construction services and the
prohibition on bundling in such situations.
|
| August 18 |
The DoD is
proposing to amend the DFARS to add a contract clause
requiring a contractor to notify the DoD if the contractor is
required to report its activities under the U.S.-International
Atomic Energy Agency Additional Protocol. The proposed
clause would be included in contracts for research and
development or major defense acquisition programs involving
fissionable materials, other radiological source materials, or technologies directly related to nuclear power
production.
|
| August 15 |
The SBA is
proposing to increase the thresholds for Small
Business Innovation Research (SBIR) Program awards to
offset the effects of inflation since the thresholds were
originally set in 1992. Specifically, the proposed increases
would be from $100,000 to $150,000 for Phase I awards and from
$750,000 to $1,000,000 for Phase II awards. Comments are due
by September 15.
|
| August 14 |
Effective
today, the Department of State is amending Part 121 of the International
Traffic in Arms Regulations (ITAR) to add language
clarifying how the criteria of Section 17(c) of the Export
Administration Act of 1979 ("EAA") are implemented
in accordance with the Department of State's obligations under
the Arms Export Control Act ("AECA") and
restating the Department's policy and practice of implementing
the criteria of this provision. The rule reinstates the
Section 17(c) reference in the ITAR to assist exporters in
understanding the application of the Section 17(c) criteria to
parts and components for civil aircraft. It also clarifies
that any part or component that (i) is standard equipment;
(ii) is covered by an FAA civil aircraft type certificate
(including amended type certificates and supplemental type
certificates but expressly excluding military aircraft
certified as restricted and any type certification of Military
Commercial Derivative Aircraft, defined by FAA Order 8110.101
effective date September 7, 2007 as "civil aircraft
procured or acquired by the military"); and (iii) is an
integral part of such civil aircraft, is subject to the
jurisdiction of the Export Administrative Regulations (EAR).
Where such part or component is not Significant Military
Equipment ("SME"), no Commodity Jurisdiction (CJ)
determination is required to determine whether the item meets
these criteria for exclusion under the United States Munitions
List (USML), unless doubt exists as to whether these criteria
have been met. However, where the part or component is SME, a
CJ determination is always required, except where a SME part
or component was integral to civil aircraft prior to the
effective date of this rule. Additionally, the rule adds
language in a new Note after Category VIII(h) to provide
guidelines concerning the parts or components meeting these
criteria. The change to Category VIII*(b) also identifies and
designates certain sensitive military items, formerly
controlled under Category VIII(h), as SME. Previous and current
authorizations concerning the manufacturer of these items will
not require notification in accordance with section 124.11 and will not require a "Nontransfer and Use
Certificate" DSP-83, unless they are amended, modified,
or renewed.
|
| August 13 |
The GSA is
proposing a rewrite of GSAR Part 549, Termination
of Contracts (GSAR Case 2008-G515). Comments are due
by October 14.
Non-government
contract rant (hey, it's my blog). For the past couple of
years, I have used a home PSA test kit manufactured by a
company called Biosafe to obtain prostate specific antigen
results to provide my doctor at my yearly exams. Today, when I
went to buy this year's kit, it was not on the shelf, so I
went online to try to find it. I found several web sites that
said the kit was "unavailable," including one site
that mentioned it had been discontinued because of serious
quality problems with the test results and test reporting.
Concerned, I went to the company's website (ebiosafe.com). It
was not accessible. Therefore, I tried Google's
"cache" and found a partial version of the website
dated August 8, so apparently it was available until recently.
Then, I tried calling the toll-free number listed on last
year's test report from the company. The number was
disconnected without any message or forwarding number. So, I
went to the FDA's website to find out if there were any alerts
or warnings concerning Biosafe's products. There were none.
Not satisfied, I called the FDA. After going through countless
recorded messages and switching from one department to
another, I finally was connected to a human female. I
described the situation to her, and she said all the
information she had was that Biosafe was currently registered
with the FDA. She gave me the number of the person who was
listed as the company's registered agent, and she gave me a
local number that was on file with the FDA for the company's
headquarters. I called that local number first. You guessed
it--disconnected. Then, I called the registered agent, who
alternated between telling me that he had no information and
that he was not authorized to say anything. I called the lady
at the FDA and reported to her what I had learned (i.e.,
nothing). She was not concerned. I asked her whether it was
alarming to her that a company that (until very recently) had
been producing FDA-approved products was unreachable at the
telephone number it had provided to the FDA on its latest
registration form. She said that, since it had paid its
registration fee for calendar 2008, nothing else was of
interest to her. I asked her whether it was of concern to the
FDA that the company was unreachable by its customers when its
product had apparently been pulled because of quality issues?
(I mentioned specifically that I was interested in finding out
whether my last two years' test results were worthless or,
worse, misleading.) She said that, if the company were having
quality issues, the FDA preferred to handle such issues in
private, and that such discussions between the FDA and the
company (if they had occurred) would be unavailable to the
public! Since I can't seem to find anything, do any of
my readers have any recent information on
Biosafe?
|
| August 12 |
Several
DFARS amendments have been published: (i) in compliance with
section 904 of the National Defense Authorization Act for
fiscal 2006, the Office of Small and Disadvantaged Business
Utilization has been re-designated the Office
of Small Business Programs (DFARS Case 2008-D001); (ii)
the DFARS has been updated to make its language consistent
with the FAR concerning contractor
standards of conduct and the handling of extraordinary
contractual actions (DFARS Case 2008-D004); (iii) in
compliance with Section 827 of the National Defense
Authorization Act for Fiscal Year 2008, an interim rule
requires the use of competitive procedures in the acquisition
of items for which Federal
Prison Industries has a significant market share (DFARS
Case 2008-D015); (iv) in compliance with Section 130 of
the National Defense Authorization Act for Fiscal Year 2007, a
final rule establishes a quality control policy for the
procurement, modification, repair, and overhaul of ship
critical safety items (DFARS Case 2007-D016); (v) a final
rule increases dollar
thresholds for application of the World Trade Organization
Government Procurement Agreement and the Free Trade
Agreements, as determined by the United States Trade
Representative (DFARS Case 2007-D023); and (vi) a final rule
updates and clarifies the requirements for unique
identification and valuation of items delivered under DoD
contracts and revises the applicable contract clause to
reflect the current requirements (DFARS Case 2007-D007).
|
| August 11 |
The Court
of Federal Claims modified its original order in the Watts-Healy
Tibbitts bid protest to specify the requirements for the
new responsibility determination it is requiring the
Government to make.
|
| August 8 |
Effective
today, the GSA has implemented a final rule rewriting GSAR
Part 522, Application
of Labor Laws to Government Acquisitions.
Effective
October 1, the GSA is revising the
maximum CONUS per diem lodging and meal allowance rates.
The new rates may be found here.
Boeing
already is suspicious about the air refueling tanker
resolicitation.
|
| August 7 |
Effective
September 8, the
Office of Personnel Management is updating the 2002 North
American Industry Classification System (NAICS) codes
currently used in Federal Wage System wage survey industry
regulations with the 2007
NAICS revisions published by the Office of Management and
Budget.
In Alabama
Aircraft Industries Inc. - Birmingham, the Court of
Federal Claims decided a slew of procedural issues in the
continuation of this protest that began at the GAO, including
several requests by the protester to supplement the
administrative record and several requests to obtain discovery
from the Government, e.g., requests for documents for which
the Government is asserting attorney-client or work product
protection.
The Court
of Federal Claims' decision in the Watts-Healy
Tibbitts case demonstrates how difficult it is to prevail
in request for a preliminary injunction in a bid protest. On
reconsideration, the protester prevailed, but the court noted
it was granting the injunction "with reluctance"
only because it had "no choice." The court noted
that a decision to ignore bid rigging in a responsibility
determination simply because it was a widespread and accepted
practice in Japan was too important to be made at the
Contracting Officer level without any reflection and without
any analysis of foreign policy considerations.
The GAO
sustained a protest by Consolidated
Engineering Services in part because the agency used an
unannounced evaluation factor of transition risk associated
with moving to a non-incumbent awardee.
|
| August 6 |
NASA
proposes to amend the NASA FAR Supplement to update procedures
for compliance with FAR Subpart 4.13, Personal
Identity Verification of Contractor Personnel. Comments
are due by October 6.
Often
overlooked among a contract's boilerplate provisions, the
integration clause was used by the Court of Appeals for the
Federal Circuit in Northrop
Grumman Information Technology to conclude that a
particular document was not a part of the contract.
Several
new ASBCA decisions have been published (see the top
six cases listed on my ASBCA
page).
In Inversa,
S.A., the CBCA held that the contractor's efforts to
hinder the Government from fulfilling its obligations to
restore leased premises precluded the contractor from
premising its claim on the Government's failure to do so.
Whew--busy
day.
|
| August 5 |
The GSA
proposes rewrites of GSAR Part 528, Bonds
and Insurance (GSAR Case 2006-G517); and GSAR Part 546, Quality
Assurance (GSAR Case 2008-G514). Comments are due by
October 6.
|
| August 4 |
The GSA is
proposing a rewrite of GSAR Part 503, Improper
Business Practices and Personal Conflicts of Interest
(GSAR Case 2008-G502). Comments are due by October 3.
Several
new Postal Service board
decisions have been published.
|
| August 1 |
The GSA is
proposing rewrites of GSAR Part 512, Acquisition
of Commercial Items (GSAR Case 2008-G504) and Part
513, Simplified
Acquisition Procedures (GSAR Case 2007-G502). Comments are
due by September 30.
|
| July 31 |
The CBCA's
decision concerning the discovery disputes in LFH
includes good, black-letter analyses of several
attorney-client privilege issues, including the analysis of
situations in which one agency discloses allegedly protected
documents to another agency.
|
| July 30 |
The GSA is
proposing to revise Part
525 of the GSAR regarding Foreign Acquisition. Comments
are due by September 29.
The GAO
sustained MCT
JV's protest in part because the agency neglected to
evaluate the performance risk associated with the awardee's
failure to follow solicitation instructions not to propose
unrealistically low costs.
|
| July 28 |
Effective
today, the Federal
Travel Regulation is revised to increase the cost of
operating a privately owned airplane from $1.07 to $1.26 per
mile, a privately owned automobile from $0.505 to $0.585 cents
per mile, and a privately owned motorcycle from $0.305 to
$0.585 cents per mile.
|
| July 25 |
In Metrotop
Plaza Associates, the Court of Federal Claims held that
the statute of limitations for appealing from a Contracting
Officer's decision was tolled by his willingness to reconsider
his decision and that "[r]econsideration . . . was implicit in [his]
offer to discuss settlement."
|
| July 24 |
The GAO
just issued a redacted decision (originally dated August 10
2007) sustaining a protest by Lockheed
Martin Maritime Systems & Sensors because the agency
(in violation of solicitation terms) failed to give Lockheed
an opportunity to correct defects in its prototype.
|
| July 22 |
Effective
August 21, the SBA is revising
the small
business size standard for the Heating Oil Dealers
industry (North American Industry Classification System
(NAICS) code 454311) from $11.5 million in average annual
receipts to 50 employees, and the size standard for the
Liquefied Petroleum Gas (Bottled Gas) (NAICS code 454312) from
$6.5 million in average annual receipts to 50 employees.
Comments
are due by August 15 on a proposed SBA rule retracting or
reclassifying waivers from the
non-manufacturer rule that have been erroneously extended
or granted to industry classifications that are not
manufacturing industry classifications under the NAICS
System.
I've
finished adding the latest SBA OHA decisions to the website, with the usual
caveat that I did not bother listing the appeals of that NAICS
code protesting machine, DCX/CHOL Enterprises.
|
| July 21 |
SBA's OHA
has published a slew of new decisions. I have the new size
appeals listed on the website.
I'm still working on the rest.
|
| July 19 |
DFARS
Case 2004-D010: effective July 21, the DoD is issuing an interim rule
amending the DFARS to specify requirements for complying with
export control laws and regulations when performing DoD
contracts. The rule recognizes contractor responsibilities to
comply with existing Commerce and State Department
regulations and adds two new clauses to be used when
export-controlled items, including information or technology,
may be involved in the performance of a contract. The new
clauses are: 252.204-7008--Requirements
for contracts involving export-controlled items; and
252.204-7009--Requirements regarding potential access to
export-controlled items.
DFARS
Case 2008-D003:
DoD is proposing to amend
the DFARS to address statutory restrictions on the acquisition
of specialty metals not melted or produced in the United
States. The proposed rule implements Section 842 of the
National Defense Authorization Act for Fiscal Year 2007 and
Sections 804 and 884 of the National Defense Authorization Act
for Fiscal Year 2008. Comments are due by September 19.
A
recent article claims GAO protests are the "new"
business strategy for a rapidly increasing group of
contractors. Of course, the GAO docketed 2,334 protests in
fiscal 1997 and only 1,318 in 2007, but one should never let
the facts get in the way of a catchy headline.
|
| July 18 |
The SBA
has increased its monetary
size standards by 8.7% to account for inflation since
December 2005.
|
| July 17 |
The GAO
sustained separate protests by two offerors against a lease
awarded by the GSA because it failed to alert the protesters
to significant weaknesses in their proposals and gave the
awardee credit for a part of its proposal that did not comply
with the solicitation's requirements. See Trammel
Crow and New
Jersey & H Street.
|
| July 16 |
John
L. Jones, who sometimes operates as Master B. DJ's Karaoke
& Video, had hundreds of contracts with a nonappropriated
fund instrumentality over a period of 26 years to perform at
various night clubs at Fort Bragg. The contracts typically
permitted him to take periodic 15-minute breaks. Mr. Jones
claimed that, at one point, one of the club managers directed
him not to take his breaks and that he was entitled to recover
for all the breaks he missed over the ensuing 20 plus years.
The Board noted that there was no evidence that the club
manager had any authority to change the contract or that his
alleged directions applied to other contracts or other clubs.
As part of his evidence, Mr. Jones provided an unsworn
statement from a Ms. Tina Turner Jones, who stated that she
was a regular customer at the clubs where Mr. Jones performed
between 1984 and 2004 and that for one week, breaks were taken
but discontinued because of customer dissatisfaction.
The ASBCA denied the claim.
In BearingPoint,
the Board discussed the Government's high burden of proof to
defend against a subcontractor claim by relying on the Severin
doctrine.
Several
other ASBCA decisions
were published today.
|
| July 15 |
Sealift,
Inc. lost its protest at the Court of Federal Claims
because even though the agency relaxed, waived, or
modified quite a few of the solicitation's requirements after
award, none of these actions rose to the level of a
fundamental change in the scope of the contract. Had the GAO
decided this dispute, it likely would have referred to the
Government's actions as normal matters of contract
administration.
Omega
World Travel lost its protest against a task order under
an ID/IQ contract in part because of the limits on the scope
of such protests imposed by the Federal Acquisition
Streamlining Act and in part because the Government's
allegedly improper disclosure of the protester's personnel
information occurred after the task order was awarded and,
therefore, was not a violation of the Procurement Integrity
Act.
|
| July 11 |
The CBCA
rejected Business
Management Research Associates' argument that a prior
course of dealing had altered the task ordering process in its
contract with HHS.
|
| July 9 |
The GSA is
proposing a rewrite of GSAR
Part 516, Types of Contracts: GSAR Case 2006-G504.
The Air
Force officially announced that it is reopening the air
refueling tanker contract competition in response to the
GAO's decision in Boeing's protest.
The latest
decision in the Axiom
Resource Management protest denied the Government's motion
to stay the court's order not to exercise the contract option.
|
| July 8 |
Effective
July 23, the SBA is waiving the nonmanufacturer rule for televisions.
|
| July 4 |
After last
year's effort, I decided it was too hard to write an entire
year's procurement review in one fell swoop at the end of the
year, so this time round, I am doing it in increments. The
2008 procurement review for January through June can be found here.
If you find any broken links or other errors, please email me
and let me know. Thank you.
Chapter 1
of Title VI of H.R. 2642 (the Supplemental Appropriations Act,
2008) is entitled "Close the Contractor Fraud
Loophole," and section 6102 of that chapter reads as
follows: "The Federal Acquisition Regulation shall be
amended within 180 days after the date of the enactment of
this Act pursuant to FAR Case 2007-006 (as published at 72 Fed
Reg. 64019, November 14, 2007) or any follow-on FAR case to
include provisions that require timely notification by Federal
contractors of violations of Federal criminal law or
overpayments in connection with the award or performance of
covered contracts or subcontracts, including those performed
outside the United States and those for commercial
items."
|
| July 2 |
The DoD
has published new per
diem rates for official travel in Alaska, Hawaii, Puerto
Rico, the Northern Mariana Islands and U. S. Possessions.
The
President has issued Executive
Order 13467 concerning, inter alia, new procedures
for access to classified information by contractor and
subcontractor personnel.
|
| July 1 |
Beginning
today, the prompt
payment interest rate is 5 1/8 %. |
| June 28 |
The Equal
Access to Justice Act provides in part that an application for
attorneys fees must be filed within 30 days of the date a
judgment becomes final and unappealable. Impresa
Construzioni Geom. Domenico Garufi won a bid protest at
the Court of Federal Claims and filed a request for bid and
proposal costs. The Court of Federal Claims denied it, and
Impresa appealed to the Federal Circuit, but then filed a
motion requesting that the Federal Circuit dismiss its appeal
and enter a final judgment in favor of the Government. The
Federal Circuit complied. About 114 days later, Impresa
filed an application for attorneys fees under the Equal Access
to Justice Act with the Court of Federal Claims. The court
held that the application was untimely because more than 30
days had passed since the Federal Circuit's order had become
final. Now, the Federal Circuit overturns that decision,
establishing a firm rule that the 30-day period begins to run
only after the 90-day period for requesting certiorari
expires, regardless whether there is any possibility the
Supreme Court would grant cert. Judge Rader's one-paragraph
dissent is cogent and pithy and ends with an instant classic:
"Impresa cannot now revive a corpse it buried with its
own motion."
|
| June 26 |
The redacted
version of the GAO's decision in the Boeing air refueling
tanker protest is out in record time.
The GAO
has issued interim rules
of procedure for the GAO Contract Appeals Board, which
will be codified at 4 C.F.R. Part 22.
|
| June 25 |
The GSA is
proposing a rewrite of General Services Acquisition Regulation
(GSAR) Part
509 re Contractor Qualifications, GSAR Case 2006-G512.
The Office
of Government Ethics has published final rules regarding post-employment
conflicts of interest restrictions for governmental
employees terminating governmental service on or after January
1, 1991, which are to be codified at 5 C.F.R. 2637 and 2641.
The final rules include an extensive and lengthy introduction
summarizing comments received concerning the proposed rule and
the agency's reaction to these comments.
|
| June 24 |
The GSA is
proposing rewrites of two more sections of the General
Services Acquisition Regulation (GSAR): (i) Part
542 re Contract Administration and Audit Services (and
related clauses in Part 552), GSAR Case 2008-G512; and (ii) Part
543 re Contract Modifications, GSAR Case 2008-G513.
|
| June 23 |
Effective
July 8, the SBA is waiving the nonmanufacturer rule for Other Aircraft Parts and Auxiliary
Equipment Manufacturing (Drones
and Aircraft Launching Equipment), Product Service Codes
1550 and 1720.
|
| June 18 |
The GAO
sustained Boeing's
bid protest of the aerial refueling tanker solicitation!
Klinge
Corporation won its protest at the Court of Federal Claims
in slam dunk fashion. The court declared the award invalid,
directed the agency to terminate the awardee's contract, and
awarded costs to Klinge because the agency should have
recognized that the awardee violated the Trade Agreements Act
by proposing an item essentially made in China, rather than
being a U.S.-made or qualifying country end product as
required by the certification at DFARS 252.225-7020.
FAR Case
2007-018 (organizational
conflicts of interest): the comment period has been
extended for 30 days (until July 18) for input from the
community concerning whether the FAR's current guidance on OCIs
adequately addresses the current needs of the acquisition
community or whether providing standard provisions and/or
clauses, or a set of such standard provisions and clauses,
might be beneficial.
Carr
Forest Products complained that the Government failed to
make a reasonable estimate of the number and types of trees
available in various lots in a fixed-price timber sales
contract. The judge wrote that at one point the Government's
estimators did not determine the size of the trees with
measuring tape but
instead performed "an ocular measure." Or, as we say
in Texas, they eyeballed it.
|
| June 17 |
FAR Case
2007-017 : the comment period concerning service
contract employee conflicts-of-interest proposed
rulemaking has been extended for an additional 30 days (to
July 17).
GSAR Case
2006-G502: the GSA is proposing a rewrite of GSAR
Part 501. Comments are due by August 18.
|
| June 16 |
The
Defense Department has reinstituted small
business set-asides for a number of Designated Industry
Groups under the Small Business Competitiveness Demonstration
Program because it has failed to meet its 40% goal for these
Designated Industry Groups.
The Bureau of
Industry and Security is amending the Export Administration
Regulations to reflect changes to the Missile
Technology Control Regime (MTCR) Annex that were agreed to
by MTCR member countries at the November 2007 Plenary in
Athens, Greece.
|
| June 12 |
An interim rule, effective today, amends the FAR
to implement section 6 of the Sudan Accountability and
Divestment Act of 2007, which generally requires certification that the
contractor does not conduct certain business
operations in Sudan. The interim regulation also updates
the list of countries from which most imports are prohibited,
to reflect Burma as well as Sudan. FAC 2005-26; FAR Case
2009-004.
Comments are due by August 11 on proposed amendments
to the FAR that will require contractors to utilize the U.S. Citizenship and Immigration
Services' (USCIS) E-Verify
system to verify that certain of their employees are
eligible to work in the United States. See also first
entry at June 9 below.
There's an
interesting article in today's Seattle
Times regarding the status of Boeing's GAO protest and
what Boeing's next steps might be.
|
| June 10 |
The GSA proposes to amend the General Services
Acquisition Regulation to establish a GSA
Mentor-Protege Program, GSAR Case 2006-G501. Comments are
due by August 11.
The ASBCA overturned a default termination that
had been based on a failure to make progress because the Board
found the contractor (Kostmayer
Construction) had responded satisfactorily to a cure
letter.
|
| June 9 |
President
Bush has amended
Executive Order 12989 to read in part as follows: "Sec.
5. (a) Executive departments and agencies that enter into
contracts shall require, as a condition of each contract, that
the contractor agree to use an electronic employment
eligibility verification system designated by the Secretary of
Homeland Security to verify the employment eligibility of: (i)
all persons hired during the contract term by the contractor
to perform employment duties within the United States; and
(ii) all persons assigned by the contractor to perform work
within the United States on the Federal contract."
The GAO
has amended its bid protest regulations concerning the term
"interested
party" in A-76 procurements to comply with the
requirements of the National Defense Authorization Act for
Fiscal Year 2008 and to make several other clarifications to
various sections of the rules. See also the entry
under March 21 below.
The GSA is
proposing revisions to Part 533 of the General Services
Acquisition Regulation concerning protests,
disputes, and appeals, GSAR Case 2007-G501. Comments are
due by August 8.
I've
posted links to a few new SBA
OHA decisions concerning SDVOSB status and a slew of size
decisions going back as far as March.
In the Richlin
Security Service decision, the Supreme Court held that
recovery by a prevailing party under the Equal Access to
Justice Act may include paralegal fees billed at prevailing
market rates.
In Allison
Engine Co. v. United States, the Supreme Court held that,
under section 3729(a)(2) of the False Claims Act, a
subcontractor can be found liable if it submits a false
statement to the prime contractor, intending that the prime
use the statement to induce the Government to pay the
subcontractor's claim.
Busy day.
|
| June 7 |
In the Hedlund
Construction case, the CBCA denied the parties' JOINT
motion to vacate the Board's prior decision.
|
| June 6 |
The GSA is
proposing rewrites of three parts of the General Services
Acquisition Regulation: (i) Part 537 covering service
contracting, GSAR Case 2008-G510; (ii) Part 547
covering transportation,
GSAR Case 2006-G518, and (iii) Part 517 covering special
contracting methods, GSAR Case 2007-G500.
|
| June 5 |
The GAO
recommended Sysorex
be awarded protest costs because the agency delayed until
after filing the agency report to take corrective action on a
clearly meritorious protest.
In denying
General
Injectables & Vaccines' petition for rehearing, the
Federal Circuit held that the failure of FAR 52.212-4(f) to
state specifically that a contractor is liable for unexcused
subcontractor delays does not change the fact that the
contractor is liable for such delays.
|
| June 4 |
The SBA is
proposing to waive the nonmanufacturer rule for televisions.
Comments are due by June 19.
|
| June 2 |
I have
added quite a few new decisions to the webpage of decisions by the SBA's Office of
Hearings and Appeals. The standard caveat applies: I list
decisions in chronological order; the SBA does not issue them
that way; so the new decisions are scattered in my list as far
back as February. The most interesting decision in the bunch
is Alaka'i,
in which the OHA found that the SBA improperly included the
owner's spouse's income in determining his net income and net
worth for purposes of qualifying as economically
disadvantaged.
|
| May 27 |
The Department
of Homeland Security has announced that the Transportation
Security Administration's exemption from the FAR will expire
for acquisitions initiated after June 22 and has amended the
Homeland Security Acquisition Regulation (i) to remove
provisions related to DHS' special streamlined acquisition
authority and (ii) to change the name of the Bureau of
Immigration and Customs Enforcement to U.S. Immigration and
Customs Enforcement, and the name of the Bureau of Customs and
Border Protection to U.S. Customs and Border Protection.
|
| May 23 |
The Metric
Construction Co. case includes a good discussion of how
the Court of Federal Claims views the various bases for
recovery under the constructive change doctrine.
|
| May 19 |
Effective
today, the VA has issued an interim final rule, which implements portions of the Veterans
Benefits, Health Care, and Information Technology Act of 2006.
That Act requires the VA to verify ownership and control of
veteran-owned small businesses, including service-disabled
veteran-owned small businesses. According to the new rule, a
VA contracting
officer Veterans Affairs may restrict a competition for a requirement to an SDVOSB or a VOSB if that business
is listed as "verified" in the VetBiz.gov Vendor
Information Pages (VIP) database. The rule defines the
eligibility requirements for businesses to obtain verified
status, explains examination procedures, and establishes
records retention and review processes.
|
| May 16 |
FAR Case
2007-006: a second version of proposed rules concerning contractor
compliance program and integrity reporting has been
published. Comments are due by July 15.
The SBA is
considering waiving the nonmanufacturer
rule for Other
Aircraft Parts and Auxiliary Equipment Manufacturing (Drones,
Miscellaneous Aircraft Accessories, and Components; Aircraft
Launching Equipment). Comments are due by June 2.
The
redacted version of the winning Contingency
Management Group GAO protest has been published. Five or
more attorneys were admitted to the protective order for EACH
of the winning protesters and the intervenors--TEN lawyers
from two firms for just ONE of those intervenors. It's a brave
new world where the combined hourly rate of all the
participants in a single GAO protest forms a significant
portion of the nation's GDP. ;-)
L-3
Communications Corp. won bid preparation expenses (but not
lost profits) at the ASBCA as a result of the Government's
breach of the "fair opportunity to be considered"
provision covering the solicitation for a delivery order under
an ID/IQ contract.
|
| May 14 |
On
reconsideration, the ASBCA has reversed its prior
decision in the Raytheon CAS 413 segment-closing case,
which had found the contractor liable to the Government for
interest for failing to make timely period adjustments to
pension costs. In the most recent Raytheon
decision, the Board held that its prior inferences from an
unclear record were unjustified. However, the Board also
decided that further development of the record is not
necessary because the "contract price or cost adjustment
did not result from a CAS violation or from a failure
to follow a cost accounting practice consistently, which is
what the CAS statute and CAS clause require in order for [the
contractor] to be liable for a contract price adjustment and
interest. . . ."
The
Department of Agriculture's Office of Energy Policies and New
Uses has issued three sets of regulations (to be published at
7 C.F.R. Part 2902) designating biobased items for federal
procurement. The new regulations include many categories of
designated items and are issued in three parts: Part
III; Part
IV; and Part
V.
|
| May 13 |
DFARS
Case 2006-D057: DoD has issued an interim rule amending
the DFARS in accordance with Section 852 of the National
Defense Authorization Act for Fiscal Year 2007 to ensure that pass-through charges on
contracts or subcontracts are not excessive in relation to the
cost of work performed by the contractor or subcontractor. The
interim regulation includes two, new standard contract clauses
(252.215-7003 and -7004). According to the clauses, an "excessive
pass-through charge, with respect to a contractor or
subcontractor that adds no or negligible value to a contract
or subcontract, means a charge to the Government by the
contractor or subcontractor that is for indirect costs or
profit on work performed by a subcontractor (other than
charges for the costs of managing subcontracts and applicable
indirect costs and profit based on such costs)." The
clauses generally operate when the contractor is
subcontracting more than 70% of the work.
|
| May 12 |
The GSA
has published the final rules
of procedure for the Civilian Board of Contract Appeals.
|
| May 9 |
In The
CNA Corp. pre-award protest, the Court of Federal Claims
overturned a decision by a Health and Human Services
contracting officer to exclude an offeror from a competition
on the basis of an agency ethics opinion regarding a perceived
post employment conflict of interest under 18 U.S.C.
207(a)(1).
|
| May 7 |
The Watts-Healy
Tibbitts decision by the Court of Federal Claims
demonstrates how difficult it is to win a protest. The
"one thing" that was "clear" to the court
was that neither DFARS 252.236-7010 nor the statute on which
it is based "clearly define[s] whether a joint venture
between an American company and foreign corporation is an
American company for the purposes of the twenty percent
differential to be applied to foreign corporations." The
court also found the agency's responses to bidders' questions
on the subject completely unenlightening. Nevertheless, the
court did not find the agency's subsequent interpretation of
the requirements in this particular solicitation unreasonable.
I love a
"gotcha" moment. In the Information
Systems & Networks Corp. decision, the Court of
Federal Claims wrote: "[T]here is at least one other
significant factual kink in plaintiff's assertion that
defendant hatched a scheme to terminate it for default and
seize its equipment - namely, it was not terminated for
default, but rather for convenience."
|
| May 6 |
Homeland
Security has revised its acquisition regulation to
delegate authority for one-step turnkey design-build
contracts to the Coast Guard (HSAR Case 2007-002).
The GAO
sustained a protest by Native American Industrial Distributors
because the awardee failed to provide required letters
of commitment for key personnel.
|
| May 5 |
The seminannual
regulatory agenda for the FAR is out. Many individual
agencies also are publishing their separate agendas today.
|
| May 2 |
As any aspiring writer knows, the first paragraph
is half the battle, and this one from the CBCA's decision in
the Minneapolis
Community Development Agency and City of Minneapolis case
is a doozy: " 'Most of the disputes in the world
arise from words.' Morgan v. Jones, (1773) 98 Eng. Rep.
587, 596 (K.B.). As the appeal pending before us shows, words
are no less troublesome in the contract disputes of today than
they were when Lord Mansfield, Chief Justice was developing
common law to govern commercial transactions." It
actually had me looking forward to the ensuing 70+ pages of
contract interpretation issues.
|
| May 1 |
Effective
June 2, the Cost Accounting Standards Board of the Office of
Federal Procurement Policy has revised Cost Accounting
Standard (CAS) 412, "Cost Accounting Standard for
composition and measurement of pension cost," and CAS
415, "Accounting for the cost of deferred
compensation" to address issues concerning the
recognition of the costs of Employee
Stock Ownership Plans (ESOPs) under government cost-based
contracts and subcontracts. These amendments provide criteria
for measuring the costs of ESOPs and their assignment to cost
accounting periods and specify that accounting for the
costs of ESOPs will be covered by the provisions of CAS 415.
Effective
May 16, the SBA is waiving the nonmanufacturer rule for (i) trash
bags manufacturing, (ii) safety
zone rubber gloves manufacturing, and (iii) paper
products manufacturing.
Effective
today, the the Per
Diem, Travel and Transportation Allowance Committee of the
Defense Department is publishing Civilian Personnel Per Diem
Bulletin Number 258, which lists revisions in the per
diem rates prescribed for U.S. Government employees for
official travel in Alaska, Hawaii, Puerto Rico, the Northern
Mariana Islands and United States possessions.
|
| April 30 |
Burns
and Roe offers a very short refresher course in the
standards and tests the GAO uses in deciding whether to award
protest costs.
|
| April 29 |
Bell
BCI won its claim against the NIH at the Court of Federal
Claims for the cumulative impact of 200 changes, but the part
of the decision I enjoyed the most was this little gem
regarding the Government's counterclaim for liquidated
damages: "NIH did not believe that it had a factual basis
to assert a liquidated damages claim against Bell. NIH
asserted this claim only upon the advice of counsel to create
negotiating leverage in the event Bell filed a claim. . . ." The Government's witness admitted this at trial. A
Perry Mason moment.
|
| April 28 |
The GSA's Office
of Governmentwide Policy invites comments to be submitted
by June 27 on a proposed document entitled "Federal
Acquisition System Requirements," which gives functional, process, technical and data standards
requirements for software developers of Government acquisition
and contract writing systems.
|
| April 23 |
Several
DFARS amendments have been issued, including changes related
to earned value management policy (DFARS
Case 2005-D006), a final rule implementing Section 823 of
the National Defense Authorization Act for Fiscal Year 2008
(Pub. L. 110-181), which provides a 5-year extension of the
authority for DoD to carry out a pilot program for follow-on
contracting for the production of items or processes begun as
prototype projects under other transaction agreements (DFARS
Case 2008-D008), and a final rule removing an obsolete
restriction on the acquisition of propellers from foreign
sources (DFARS
Case 2007-D027).
The DoD is
proposing to amend the DFARS (i) to revise the criteria under
which the contract administration office may permit a
contractor to release supplies for shipment without government
authorization of the shipping
documents and (ii) to address review and documentation
requirements with regard to the use of time-and-materials
contracts for the acquisition of non-commercial services in
order to provide for the same level of review for both
commercial and non-commercial DoD time-and materials
contracts.
In Phillips/May
Corp., the Court of Appeals for the Federal Circuit held
that the Contract Disputes Act does not permit splitting
claims arising under the same contract between a board and the
Court of Federal Claims in derogation of the normal standards
of res judicata.
|
| April 22 |
FAC
2005-25 is out today and includes six items, plus a
technical amendment: (i) FAR
Case 2004-038--an interim rule change to FAR Subpart 4.6
that revises the process for reporting contract actions to the
Federal Procurement Data System (FPDS); (ii) FAR
Case 2005-040--another interim rule, which requires that
small business subcontract reports be submitted using the
Electronic Subcontracting Reporting System (eSRS), rather than
Standard Form 294 - Subcontract Report for Individual
Contracts and Standard Form 295 -Summary Subcontract Report;
(iii) FAR
Case 2006-033--a rule which amends the FAR to reflect the
President's delegation of the Defense Production Act's
priorities and allocations authorities in Executive Order
12919, and the current provisions of the DPAS regulations of
the Department of Commerce in 15 CFR Part 700; (iv) FAR
Case 2005-039--effective May 22, a FAR amendment to
clarify language on the use of products containing recovered
materials, pursuant to the Resource Conservation and Recovery
Act of 1976, and Executive Order 13101; (v) FAR
Case 2006-011--also effective May 22, a FAR amendment to add conditions regarding violation
of Federal criminal tax laws and delinquent Federal taxes to
standards of contractor responsibility, causes for debarment
and suspension, and the certifications regarding debarment,
suspension, proposed debarment, and other responsibility
matters; and (vi) FAR
Case 2006-031--a final rule amending FAR 33.211(a)(4)(v)
to create a higher dollar ceiling to enable small businesses
to use the small claims procedure to appeal a contracting
officer's final decision.
The GAO
has just published the redacted version of a June 2007 winning
protest by IBM
against an award by the EPA to CGI. The GAO found the agency's
cost/price evaluation was flawed in several respects, but the
redactions are so heavy in crucial places that it is difficult
to ascertain what is going on. See, e.g., the
discussion under "Other CGI costs."
|
| April 21 |
I've added
some newly released SBA OHA
decisions. Because the SBA often does not publish its
decisions in chronological order (while I list them that way)
some of the newly added decisions (e.g., PMTech,
J.
W. Mills Management, and TKTM
Corp.) are down among others already published in my list)
while others are at the top.
I haven't
been a huge fan of the Court of Federal Claims' reasoning
concerning its procurement jurisdiction in Ezenia!
Recently, the court had occasion to distinguish that case and
provide a much more appealing (hopefully, not appealable)
decision in Savantage.
DoD is
seeking comments concerning how to define the term "nontraditional
defense contractor."
|
| April 18 |
The
Commerce Department's Bureau of Industry and Security (BIS)
has published
various technical corrections and clarifications to the Export
Administration Regulations (EAR).
The BIS
has also proposed making conforming changes in certain end-user/end-use
controls and to clarify that a party cannot proceed with
an export, reexport, or transfer (in-country) that is in
transit at the time the party is informed by BIS that a
license is required (in accordance with certain
end-user/end-use controls in the EAR), unless that party first
obtains a license from BIS authorizing the completion of the
transaction. Comments are due by June 17.
The ASBCA
found a government breach but declined to award breach damages
in Total
Procurement Service, Inc., because the contractor failed
to prove quantum, which is putting it mildly. The Board put it
this way: "However, appellant here has failed to prove
the amount, reasonableness and allocability of any costs that
were incurred. Because of the almost complete absence of
documentation or other corroboration of these costs and indeed
the destruction of pertinent records, as well as conflicts in
the amounts claimed, we also do not consider that a 'jury
verdict' is appropriate. The failure to maintain, preserve and
promptly produce to the government fundamental accounting data
and records goes to the credibility of the entire claim.
Appellant's actions with respect to those records were
irresponsible and militate against any award."
In Teknocraft,
the Board dismissed a claim without prejudice after holding
that typing "//signed//" in a signature block was
not a defect in a certification that could be remedied at the
Board.
|
| April 15 |
Several ASBCA decisions were
published yesterday. Among the more interesting: the Board
held it (i) had jurisdiction over NSA
contract disputes; (ii) lacked jurisdiction over a claim
based on "humanitarian"
grounds; and (iii) lacked jurisdiction over Qatar
International Trading Co.'s complaint that the Government
had lost the contractor's bulldozer after having towed it from
an accident site (the actual facts are more complicated and
more interesting than this summary). The Board also held that
the Government had not extended only some services under the
"Option to Extend Services" clause, but, rather, had
extended the contract under the "Option to Extend the
Contract Term" clause, such that elimination of some
services was a partial termination for convenience or a
deductive change, entitling Wackhenhut
to compensation.
|
| April 14 |
Fedcar
Company won its GAO protest against the GSA's award of a
contract to construct and lease a dedicated campus facility.
The GSA admitted it made a mistake in calculating the
awardee's price but claimed it would have made no difference
in the cost/technical tradeoff evaluation. The GAO gave this
argument short shrift:
"While the agency argues that the
outcome of the SSA's cost/technical tradeoff would be the same
regardless of the re-calculated price, our Office affords
little weight to an agency's post-protest arguments that are
based on judgments the agency asserts it would have made
because such judgments made in the heat of litigation and
based on facts that were not previously considered that are
materially different from those on which the agency relied in
making the original decision may not represent the fair and
considered judgment of the agency. Global, A 1st
Flagship Co., B-297235.2, Dec. 27, 2005 2006 CPD para. 14
at 8. Under the circumstances, we give little weight to the
agency's assertion that the outcome would have been the same,
given that Fedcar now has a significantly greater price
advantage than found by the agency when it made its source
selection decision.
Where a source selection authority bases his or her source
selection decision on figures that do not reasonably represent
the differences in costs to be incurred under competing
proposals, the source selection is not reasonably based. See
Gemmo Impianti SpA, B-290427, Aug. 9, 2002, 2002 CPD
para. 146 at 5-6."
Fedcar also obtained
meaningful relief because the agency made a counteroffer in
the contract it sent the awardee for signature post-award,
which meant no enforceable agreement was in place at the time
of the protest. Thus, the GAO did not have to worry about
disturbing an ongoing contract in fashioning a remedy.
|
| April 11 |
The State
Department is proposing to amend the ITAR
to clarify how the criteria of Section 17(c) of the Export
Administration Act of 1979 are implemented in accordance with
the Department's obligations under the Arms Export Control Act
with regard to aircraft components. Comments are due by May
12.
Infrastructure
Defense Technologies lost its pre-award bid protest
against a sole source solicitation and a related bridge
contract in part because it neither submitted a proposal nor
filed a protest prior to the date proposals were due.
AT&T
didn't win all its protest grounds, but the agency's failure
to conduct meaningful discussions with AT&T and its
unexplained final evaluation of the awardee's management
proposal were sufficient for the GAO to recommend that the
agency re-open discussions and
re-evaluate.
|
| April 8 |
FAR
Case 2005-032: Comments are due by June 9 on proposed FAR
rule changes to improve the regulations at FAR 32.001, 32.5,
and 52.232–16 related to requests for progress payments and
Standard Form (SF) 1443, Contractor’s Request for Progress
Payments.
The SBA is
considering waiving the nonmanufacturer rule for: (i) paper
products manufacturing, (ii) safety
zone rubber gloves manufacturing, and (iii) trash
bags manufacturing. Comments are due by April 23.
The Chapman
Law Firm Co. lost its latest protest at the Court of
Federal Claims. Chapman and several other contractors had
contracts to perform managing and marketing services in
Michigan and Ohio for HUD. The agency did not renew Chapman's
contract at its option exercise date. Subsequently, the agency
requested input from the remaining contractors as to whether
they would like to expand their service territories and at
what price. Chapman claimed that the agency violated the
Competition in Contracting Act by not soliciting it for these
services and that the subsequent modifications to the
incumbents' contracts were cardinal changes. The court,
however, held that limiting the pool of solicited firms to
current incumbents was reasonable and that, since each of
their contracts explicitly contemplated it might be modified
to increase their areas of service, the modifications were not
cardinal changes.
Adding
insult to injury in the latest round of the International
Air Response case, the Court of Federal Claims (i) denied
the Government's motion for reconsideration of the
original EAJA fee award to the company and (ii)
indicated that the contractor was entitled to additional EAJA
fees for responding to the motion for reconsideration.
It's my
impression that the contractor and his lawyer simply outfoxed
the Government's General Manager in drafting the termination
settlement agreement at issue in the Government
Marketing Group case and that the "clear"
meaning of the settlement was not what the Government
intended.
|
| April 7 |
Effective
today, OFCCP has issued a final rule that revises the
regulations in 41 CFR part 60-250 implementing the
nondiscrimination and affirmative action provisions of the
Vietnam Era Veterans' Readjustment Assistance Act of 1974.
The Office
of Personnel Management is finally getting around to proposing
to amend its procurement regulations to recognize the CBCA as
the replacement for the ASBCA for appeals under the Federal
Employees Group Life Insurance Federal Acquisition Regulation
(LIFAR).
|
| April 4 |
IBM's
suspension
has been lifted.
The GAO sustained a
protest against 8(a) awards for construction services because
the agency evaluated the experience
of the awardees' parents/affiliates in violation of a clear
solicitation statement that the agency would not do so.
|
| April 3 |
Rick's
Mushroom Service couldn't establish a basis for
jurisdiction at the
Court of Federal Claims, and now the Federal Circuit
affirms the lower court's decision because the company's
claims either sound in tort or are based on an agreement that
does not involve a procurement of goods or services, neither
of which is a proper basis for Tucker Act or CDA jurisdiction.
|
| April 2 |
FAR
Case 2006-022: Comments are due by June 2 on a proposed
rule that would make several changes to the FAR concerning
contractor performance information, including, inter alia,
(i) adding a definition of past performance that would include
both active and completed contracts, (ii) clarifying the use
of the Past Performance Information Retrieval System, (iii)
requiring contracting officers to evaluate past performance
for orders that exceed the simplified acquisition threshold
placed against Federal Supply Schedule contracts, or under a
task order contract or a delivery order contract awarded by
another agency (i.e. a government-wide acquisition contract or
multi-agency contract) and recommending past performance
evaluations for orders under single agency contracts, and (iv)
requiring the agency to identify the individual responsible
for each past performance evaluation.
|
| April 1 |
IBM
has been suspended--this is not an April Fool's joke. |
| March 31 |
Effective
today, the DoD has adopted a final DFARS rule (unchanged from
the interim rule) to implement policy regarding contractor
personnel authorized to accompany U.S. Armed Forces
deployed outside the United States. |
| March 28 |
FAR Case
2007-016: a corrected
table of contract thresholds has been issued for various
trade agreements.
I don't
usually report on losing GAO protests, but Brian X.
Scott complained that canceling an RFP and obtaining the
services under a pre-existing contract was beyond the proper
scope of that contract because the individuals working on it
had "no responsibility for nothing. . . ." The GAO,
however, found those individuals clearly did not have no
responsibility for nothing.
|
| March 27 |
Am I alone
in thinking the SBA's OHA decisions site is difficult to
search? At any rate, I have added a bunch of decisions to my SBA OHA Decisions webpage,
most of them from February and March, but a few going back
much further.
|
| March 26 |
Describing
the holding in the OSG
Product Tankers case is like standing in a hall of mirrors
in an arcade. OSG originally protested the agency's finding
that it was non-responsible, despite its low bid.
Subsequently, OSG moved to amend its complaint to allege that
the winning bidder was non-responsible. The Court of Federal
Claims denied that motion and now denies OSG's motion to make
an interlocutory appeal of the court's earlier ruling.
The court reasons that OSG does not have standing to challenge
the responsibility of the winning bidder because OSG has been
found non-responsible and, therefore, lacks a substantial
chance of award, even though, if OSG wins its basic protest,
it will be awarded the contract as the low, responsible
bidder.
FAR
Case 2007-017: Service Contractor Employee Personal
Conflicts of Interest--Public comments are being solicited by
May 27 concerning whether there is a need for a set of
regulatory and contract FAR provisions specifically covering
personal conflicts of interest by employees of service
contractors. Because the federal government is increasingly
using service contractors to perform work formerly performed
by federal employees, there is a concern that these private
employees are not subject to the same ethical standards and
obligations as their federal counterparts.
FAR
Case 2007-018: Organization Conflicts of Interest--for the
same reason as above, comments are also being solicited
concerning whether there is a need for increased regulatory
coverage of the the subject of organizational conflicts of
interest.
Effective
April 25, the Cost Accounting Standards Board has adopted,
without change, the proposed rule establishing a clause to be
used in CAS-covered contracts and subcontracts with foreign
entities. See 48 C.F.R. 9903.201-4.
|
| March 25 |
OMB has
established $612,196 as the maximum executive
benchmark compensation allowable under government
contracts in contractors' fiscal 2008.
|
| March 24 |
Effective
today, the State Department is amending the ITAR to deny
licenses and other approvals to export or otherwise transfer
defense articles and defense services to Sri
Lanka except, on a case-by-case basis, for technical data
or equipment made available for the limited purposes of
maritime and air surveillance and communications, in order to
comply with the Department of State, Foreign Operations, and
Related Programs Appropriations Act, 2008.
|
| March 21 |
The GAO is
proposing to amend its bid protest regulations to implement
the requirements in section 326 of the National Defense
Authorization Act for Fiscal Year 2008, which expands the
protest rights of federal employees in an A-76
competition to grant "any one individual" who
represents the majority of affected employees the status of an
"interested party" to file a protest at GAO or the
status of an intervenor to participate in a protest filed at
GAO, to remove the current restriction limiting protests of
A-76 competitions to those competitions affecting 65 or more
fulltime equivalent employees of a federal agency, and to
allow a protest of a decision to convert a function performed
by federal employees to private sector performance without a
competition. Comments are due by April 21.
Effective
April 7, the SBA is waiving the nonmanufacturer rule for
"All Other Miscellaneous Electrical Equipment and
Component Manufacturing (Indoor and Outdoor Electrical Lighting
Fixtures)."
|
| March 20 |
In the Stout
Road Associates case, a DLA intern made hotel reservations
for herself and other interns at the site of DLA training
classes. The classes were canceled; the intern canceled the
reservations; and the hotel attempted to collect cancellation
fees from the agency pursuant to the agreement the intern had
signed. The Court of Federal Claims found the Government was
not liable because the intern did not have the authority to
enter into a government contract. The plaintiff also argued
ratification, but the court found that the intern's superiors
were not contracting officers either.
Some
decisions send chills down an attorney's spine. A case in
point is West
Bay Builders, in which the Court of Federal Claims refused
to permit the contractor to withdraw admissions it was deemed
to have made by failing to provide a timely response to
defendant's request for admissions. The plaintiff's cause was
not aided by the fact that (more than seven months before
plaintiff finally filed its motion requesting that the deemed
admissions be withdrawn) the plaintiff had signed a joint
status report to the court noting that the discovery responses
were already overdue.
|
| March 19 |
The GAO
finally published the redacted version of a winning protest
originally decided in May 2007. The Defense Information
Systems Agency's evaluation of the proposal of Apptis,
Inc. was improper because the agency irrationally
evaluated past performance under technical approach risk and
failed to alert the protester to deficiencies in its proposal
during discussions. The protester's allegation that one
evaluator had a conflict of interest was untimely because the
protester knew of this grounds for protest before submitting
its offer but did not protest until after award.
Finally, a
non-Winstar 2008 Federal Circuit decision on a contract
dispute. The court upheld the ASBCA's decision sustaining a
termination for default in the General
Injectables & Vaccines case. The contractor could not
supply flu vaccine produced by its subcontractor because the
FDA found it was contaminated. The contractor argued the FDA's
action was governmental action constituting an excuse for
nonperformance. The court held that the underlying cause was
the subcontractor's default, which was attributable to the
prime, even under the controlling, commercial items,
"Excusable Delays" provision (FAR 52.212-4(f), which
does not include the traditional language that the default
must be without the fault of the contractor "or its
subcontractors. . . "). In other words, even in contracts
for commercial items, the contractor is responsible for delays
and defaults attributable to its subcontractors.
The Court
of Federal Claims has spanked the GSA a second time after its
inadequate response to an earlier protest decision. In
the original protest, the court set aside the GSA's award of a
Federal Business Opportunities ("FBO") contract to
Symplicity Corp. The GSA subsequently re-evaluated and then
re-awarded the contract to the same company. Information
Sciences protested the second award. Now, the court has set it
aside, too, and has directed the GSA to issue a revised
solicitation. Will the GSA try for a threepeat?
|
| March 18 |
Although
the contractor was not successful in its claim, the ASBCA's
decision in the Fox
Construction case includes a discussion of the seldom used
"loss of production" theory of recovery.
In Mr.
Michael Ronchetti, the ASBCA found it lacked jurisdiction
over a subcontractor's claim that was not sponsored by the
prime.
In Southern
Oregon Ecological (SOE) , the CBCA cut the appellant some
slack in specifying its damages because of its small business
status: "SOE is appearing pro se . . . and is a small
business concern, which appears to be essentially a one-man
operation that hires subcontractors to perform the work. SOE
is not expected to have the accounting system that a large
company would have."
|
| March 13 |
Effective
March 19, the FTR's mileage
allowance for privately owned vehicles is increasing from
.485 to .505 per mile. |
| March 12 |
In Northrop
Grumman, Military Aircraft Division, the CoFC held that
certain Claim Research Papers drafted to assist the
Contracting Officer in making a decision and prepared
primarily by contractual and technical staff were not
privileged and were properly disclosed voluntarily by the
Government, even though a government attorney had some part in
their preparation and they had been stamped with a legend that
they had been prepared in anticipation of litigation. Thus,
the Government's disclosure of the documents was not a waiver
of any claim of privilege with regard to other documents
concerning the same issues.
From now
on, I make no promises to keep up to date on my SBA OHA webpage with all the
NAICS code appeals of DCX/CHOL Enterprises. The company
apparently spends much of its time and energy pursuing these
appeals, but I'm just not sufficiently interested to keep
reading and posting them all.
|
| March 11 |
Boeing
is protesting the tanker contract award at the GAO.
The SBA issued several corrections/clarifications
to previously published size standards.
|
| March 10 |
FAR
Case 2006-034: This proposed rule is intended to ensure
that the FAR clearly reflects the SBA's interpretation of the
Small Business Act and the SBA's own regulations concerning
the order of precedence that applies when deciding whether to
satisfy a requirement through an award to a small business, a
HUBZone small business concern, an SDVOSB concern or an 8(a)
company. Specifically the proposed rule is intended to make
the following four things clear: (1) although there is no
order of precedence among the 8(a), HUBZone, or SDVOSB
programs, if a requirement has been accepted by SBA under the
8(a) program, it must remain there unless SBA agrees to its
release in accordance with 13 CFR 124, 125 and 126;. (2) for
acquisitions exceeding $100,000, the contracting officer must
consider making award under the 8(a), HUBZone or SDVOSB
programs (either set-aside or sole source) before the
contracting officer proceeds with a small business set-aside,
and, after such consideration, the contracting officer may set
aside an acquisition for small businesses, unless the criteria
for setting it aside for HUBZone small businesses are met; (3)
FAR 19.502-2(a) sets forth the requirement to exclusively
reserve acquisitions between $3,000 and $100,000 for small
businesses unless the contracting officer determines there is
not a reasonable expectation of obtaining offers from two or
more small businesses that are competitive in terms of market
prices, quality, and delivery, and the proposed rule clarifies
that these small business set-asides do not preclude award of
a contract to a qualified HUBZone small business, an 8(a)
concern, or an SDVOSB concern because the SBA’s regulations
give the contracting officer discretionary authority to use
the HUBZone, 8(a), or SDVOSB programs at these dollar levels
(and the rule shows that, unlike procurements that are
expected to exceed $100,000, it is not mandatory that the
contracting officer set aside an acquisition for HUBZone small
business concerns before setting aside the requirement for
small businesses); and (4) the SBA believes that progress in
fulfilling the various small business goals, as well as other
factors such as the results of market research and the
acquisition history, should be considered in making a decision
as to which program to use for the acquisition. Comments are
due by May 9.
|
| March 7 |
Effective
March 17, the GSA is revising the FTR's maximum per
diem rates for certain areas of Alabama, California,
Illinois, Missouri, and Texas.
|
| March 6 |
The Court
of Federal Claims sustained an important post-award protest by
Serco
and seven other plaintiff/offerors under the GSA's Alliant Solicitation No.
TQ2006MCB0001 because, in selecting multiple awardees, the
agency used a flawed past performance evaluation and
seemed not to have conducted a required price/technical
trade-off analysis. The court enjoined performance under all contracts
awarded in response to the solicitation.
The Court
of Federal Claims' most recent decision in the Information
Sciences protest ostensibly involves only a motion to
amend the complaint, but it includes an interesting discussion
of post-award actions by an agency of which a protester may
complain under The Competition in Contracting Act.
The SBA is
considering waiving
the Nonmanufacturer Rule for "All Other Miscellaneous
Electrical Equipment and Component Manufacturing."
Comments are due by March 21.
|
| March 4 |
The
ASBCA's decision in the AEI
Pacific construction case has some good, black letter
discussions of accord and satisfaction; duty to cooperate;
defective specifications; and compensable delays.
Tri-State
Consultants tried almost every theory of construction
contract recovery in the book, all to no avail.
The ASBCA
dismissed Valenzuela
Engineering's appeal because, as a suspended corporation
under California law, it lacked the capacity to maintain the
appeal.
FloorPro
defies a brief summary but concerns situations in which third
party beneficiaries have standing and jurisdiction to pursue
an appeal before the ASBCA.
The EPA is
proposing to amend its acquisition regulation (the EPAAR) to
revise the prescription for using the "Technical
Direction" clause and the clause, itself. The clause
describes the circumstances in which technical
direction may be provided to contractors, the types of
direction that may be provided, and the role of the
Contracting Officer's technical representative in issuing such
direction.
The GSA is
proposing to amend the Federal Travel Regulation (FTR)
provisions relating to the use of U. S. Flag air carriers
under the provisions of the Fly
America Act and to make the regulations consistent with
the Open Skies Air Transport Agreement between the U.S. and
the European Union.
|
| March 3 |
Today, the
Court of Federal Claims published a redesigned website and
changed many of the web addresses for pages in the website,
including the addresses for every decision published by the
court. I have updated all my webpage hyperlinks to CoFC
decisions accordingly. However, in that process I lost my way
to the recent International Air Response decision
related to the EAJA and referenced at the February 16
entry below, so, if anybody finds a good link to that
decision, I'd appreciate it if you would email that
information to me. Thank you.
DFARS
Case 2002-D002: Effective today, DoD has adopted as final
(with certain changes) an interim rule amending the Defense
Federal Acquisition Regulation Supplement (DFARS) to implement
Section 832 of the National Defense Authorization Act for
Fiscal Year 2002. Section 832 codified (and made modifications
to) the Berry Amendment, which requires the acquisition of
certain items from domestic sources. The latest changes affect
the following sections in the DFARS: 225.7002-2; 252.212-7001;
and 252.225-7012.
DFARS
Case 2006-D049: Also effective today, DoD has issued a
final rule amending the DFARS to require use of the Wide Area
WorkFlow electronic system for submitting and processing
payment requests and receiving reports under DoD contracts, in
order to facilitate timely and accurate payments to DoD
contractors.
|
| February 29 |
Northrop
and the manufacturer of Airbus beat out Boeing for a $35
billion Air Force contract for refueling tanker aircraft.
The
Department of Energy makes various changes to its regulations,
including its acquisition regulations (the DEAR) to conform
them to a 1991 amendment of the Defense Production Act with
regard to the Defense
Priorities and and Allocations System (DPAS). Better late
than never.
|
| February 28 |
In Axiom
Resource Management, Inc. v. United States, an important
decision involving organizational conflicts of interest, after
the Court of Federal Claims found such conflicts in Lockheed Martin Federal
Health Insurance's TRICARE contract, and the Government
refused to accede to any type of ongoing court monitoring of a
contractual mitigation plan, the court enjoined the Government
from exercising the contract options. The dialogue among the
judge, government counsel, and Lockheed's counsel, which is
included in the body of the opinion, is extremely
interesting.
Federal
Acquisition Circular (FAC) 2005-24 was published today. It
includes six items: (1) FAR Case 2005-011--(effective March
31) adding new subpart 25.3 to the FAR covering contractor
personnel that are providing support to the mission of the
United States Government in a
designated operational area or supporting a diplomatic or
consular mission outside the United States, but are not
authorized to accompany the U.S. Armed Forces; (2) FAR Case
2006-16--amending the FAR to update and clarify policy for
synopses of proposed contract actions and to delete all
references to Numbered
Notes ; (3) FAR Case 2007-16--(effective February 28), incorporating
increased
thresholds for application of the World Trade Organization
Government Procurement Agreement and the Free Trade
Agreements, as determined by the United States Trade
Representative; (4) FAR Case 2006-28--(effective February 28)
adopting (without change) the interim rule published in the
Federal Register at 72 FR 46357 (August 17, 2007) and amending
the FAR to implement the Dominican
Republic-Central America-United States Free Trade Agreement
with respect to the Dominican Republic; (5) FAR Case
2005-27--(effective March 31) amending the FAR to implement
revisions to the regulations related to the administration of
the Cost
Accounting Standards; and (6) FAR Case
2007-004--(effective March 31), amending the FAR to require
agencies to include common
security configurations in new information technology
acquisitions, as appropriate, to reduce the risks associated
with security threats and vulnerabilities and to enhance
public confidence in the confidentiality, integrity, and
availability of Government information. (This final rule
requires contracting officers to consult with the requiring
official to ensure the proper standards are incorporated in
their requirements.)
|
| February 27 |
There is
an interesting GAO report just out on the operation of the Judgment
Fund under the Contract Disputes Act.
|
| February 26 |
The SBA's
Office of Hearings and Appeals has published quite a few
decisions recently, so I have tried to catch up on my summary page.
|
| February 20 |
Because
the DoD exceeded its 5% goal for awards to small
disadvantaged businesses in fiscal 2007, it is suspending
the price evaluation adjustment for such businesses for one
year beginning March 10.
|
| February 19 |
The
Department of Energy is proposing to amend its acquisition
regulation (the DEAR) to revise the security
clause used in all contracts and subcontracts involving
access authorizations to specifically require background
checks and tests for the absence of any illegal drug of
uncleared personnel (employment applicants and current
employees) who will require access authorizations. Comments
are due by March 20.
|
| February 16 |
International
Air Response is yet another example of a judge scolding the
Government for resisting its obligations under the EAJA.
|
| February 15 |
After an
interesting analysis of the scope and meaning of the
Antideficiency Act and an indemnification clause in a World
War II contract for the supply of aviation fuel to the
Government, the Court of Federal Claims found the Government
responsible for cleanup
costs for which the contractors (Shell Oil, Union Oil,
Atlantic Richfield, and Texaco) were found liable under CERCLA
long after the war and long after the contracts had expired.
|
| February 13 |
The Cost
Accounting Standards Board has requested public comments on a
staff discussion paper concerning whether to revise the
longstanding CAS 403 thresholds (48 C.F.R. 9904.403-40(c)(2))
for determining whether home
office residual expenses must be allocated to segments.
Comments are due by April 14. The Board also announced its
decision to retain the exemption
from CAS coverage for contracts executed and performed outside
the United States.
|
| February 12 |
There are
plenty of fancy Latin-named rules for the interpretation of
ambiguous contracts, but in the Manhattan
Construction Company case, the Court of Federal Claims
used good, old-fashioned grammar to determine the meaning of
the phrase "as indicated in the drawings."
Specifically, the court wrote: "Rules of grammar state
that the subordinate clause 'as indicated on the drawings'
modifies the noun or independent clause immediately preceding
it. See Frederick C. Crews, The Random House
Handbook 242 (5th ed. 1987). Also, the absence of a comma
before the clause denotes that it applies only to the final
noun or clause. See Resolution Trust Corp. v. Nernberg,
3 F.3d 62, 65 (3d Cir. 1993). Plaintiff's interpretation might
have had support if a comma set off the subordinating clause;
but the disputed clause, 'as indicated on the drawings,' does
not have an offsetting comma. See Id. (noting that a
comma preceding a subordinate clause 'may indicate that the
qualifying language [applies] to all of the previous phrases
and not merely the immediately preceding phrase[].'); Demko
v. United States, 44 Fed. Cl. 83, 87-88 (Fed. Cl. 1999)
(using normal rules of punctuation to interpret a statute).
Thus, the lack of a comma setting off the modifying phrase,
'as indicated in the drawings,' confirms that it does not
apply to all of the preceding phrases." The
next time your children (or, in the case of my generation,
grandchildren) ask you why they have to learn these rules, you
have your answer. ;-)
In Enron
Federal Solutions ("EFSI"), the contractor had a
privatization contract to buy the Government's dilapidated
utility services plant, make certain capital improvements to
it, and then provide utility services to the Government for a
10-year period, with the monthly price designed to cover the
cost of the services and gradually to pay for the original
capital improvements. After EFSI completed the capital
improvements and the first two years of service, it defaulted
on its obligations and was terminated for default. The court
denied EFSI's attempt to recoup the remaining costs of the
capital improvements. The court based its decision in large
part on an extensive analysis of the common law definition of
a material breach and the common law consequences of such a
breach.
|
| February 8 |
The GAO
has issued a report to the Senate Armed Services Committee
recommending improvements in the DoD's practices and processes
for multiyear
procurements.
|
| February 6 |
The
ASBCA published several
decisions today.
In Northrop
Grumman Ship Systems, the Board held that a contractor
could appeal from the Contracting Officer's failure to issue a
decision on a claim without asking the Board to direct him to
do so: "In this case, the contracting officer neither
issued a timely decision nor notified appellant when he would
do so. The CDA does not require the contractor to ask the
Board to direct the contracting officer to issue a decision
before the contractor can appeal from the deemed denial of its
claim; it merely permits the contractor to do so, at its
option."
In General
Dynamics C4 Systems, the Board decided several issues
relating to option contracts, including whether alleged
government violations of FAR 17.202(c)(1) and 17.204(e) in
exercising options entitled the contractor to relief.
|
| February 5 |
The GAO
issued two decisions sustaining protests, one of which (Systems
Research and Applications Corp.) originally was decided in
September 2007 (the redactions took awhile). The other (Data
Integrators) involved the agency's improper acceptance of
a late quotation. Also, in Eagle
Home Medical Corp., the GAO recommended the protester be
reimbursed its protest costs because the agency delayed
unreasonably (until after filing the agency report and the
protester's comments) in taking corrective action on a clearly
meritorious protest.
|
| February 4 |
The Court
of Federal Claims has scolded the Government for attempting to
withhold far too many documents under claimed work product,
deliberative process, and attorney-client privileges in Chevron
U.S.A., Inc. v. United States.
In USProtect
Corporation, the contractor appealed to the Board from the
Contracting Officer's failure to issue a decision on a claim
within the statutory time limits. The Board docketed the
appeal, then suspended proceedings in part because the
Government said it needed additional time to issue a decision
and also to permit the parties to discuss settlement. Those
discussions were unavailing so the Government finally issued a
decision on the contractor's claim, and, at the same time,
issued a decision on a government counterclaim. The contractor
did not appeal the decision to the Board. The Government then
attempted to amend its pleadings at the Board to include the
counterclaim. The Board dismissed the counterclaim for lack of
jurisdiction because the contractor had not appealed it (and
still had time to appeal to the Court of Federal Claims). The
contractor did not have to appeal the Government's belated
decision on the contractor's claim--the docketing of the
contractor's original appeal was enough to sustain continued
jurisdiction.
In Bowers
Investment Company, the CBCA dismissed an appeal for lack
of jurisdiction because the contractor had failed to submit a
claim to the Contracting Officer, but instead had appealed
after ADR procedures had failed to completely resolve its
disputes with the agency.
|
| February 1 |
Executive
Order 13457 of January 29, 2008, addresses earmarking and
provides in pertinent part: "For appropriations
laws and other legislation enacted after the date of this
order, executive agencies should not commit, obligate, or
expend funds on the basis of earmarks included in any
non-statutory source, including requests in reports of
committees of the Congress or other congressional documents,
or communications from or on behalf of Members of Congress, or
any other non-statutory source, except when required by law or
when an agency has itself determined a project, program,
activity, grant, or other transaction to have merit under
statutory criteria or other merit-based decisionmaking."
In Stevens
Van Lines, the Court of Federal Claims found a contract on
the basis of the "implied actual authority" of the
Government's agents.
In Bill
Hubbard, the court (as directed by the Federal Circuit)
recalculated (and reduced) an EAJA award based on the
standards in Hensley v. Eckerhart, 461 U.S. 424 (1983)
|
| January 31 |
A proposed
FAR rule (section 6.302-2(d)) would limit the length of
contracts awarded noncompetitively under unusual
and compelling urgency circumstances to the minimum time
necessary to meet the requirements, and no longer than one
year, unless approved by the head of the contracting activity.
Biltmore
Forest Broadcasting lost a suit in district court
challenging the FCC's award of a broadcast license. It tried
again in the guise of a bid protest at the Court of Federal
Claims. The court, however, recognized the issue already had
been litigated.
|
| January 29 |
Effective
February 13, the SBA is waiving the
nonmanufacturer rule for "Irradiation Apparatus
Manufacturing, Computerized axial tomography (CT/CAT) scanners
manufacturing; CT/CAT (computerized axial tomography) scanners
manufacturing; Fluoroscopes manufacturing; Fluoroscopic X-ray
apparatus and tubes manufacturing; Generators, X-ray,
manufacturing; Irradiation equipment manufacturing; X-ray
generators manufacturing; and X-ray irradiation equipment
manufacturing."
|
| January 28 |
There is a
NAICS code protest decision by the SBA's Office of Hearings
and Appeals regarding a solicitation for portable toilets. The
protester is a firm called "King's
Thrones." 'Nuff said.
The recent
Civilian Board of Contract Appeals decision in Blackstone
Consulting is interesting. Shortly after the contractor
complained of sexual harassment by the COR's husband, the
Government began taking more and more unilateral deductions
for allegedly inadequate performance by the contractor, until
the contractor wrote that it was being forced to exercise its
right to cancel the contract within 120 days. The next yearly
option exercise period came up before that 120 period expired,
and the Government did not exercise the option. The contractor
subsequently filed a claim for, among other things,
anticipatory profits for the unexercised option year and the
succeeding option year. The Board found the claim for the
future option year too speculative, but the claim for the
first unexercised year survived the Government's motion for
summary dismissal.
I have
updated the pages listing recent
PSBCA decisions and recent decisions by the SBA's Office of Hearings and
Appeals.
|
| January 27 |
Effective
February 12, the SBA is waiving
the nonmanufacturer rule for (i) All Other Miscellaneous Electrical
Equipment and Component Manufacturing (Fluorescent Lamps,
Incandescent Lamps, etc) and (ii) All Other Miscellaneous
Electrical Equipment and Component Manufacturing (Electric
Lamp Starters and Lamp Holders, etc.).
|
| January 24 |
Several DFARS
amendments have been published: (i) DFARS
Case 2006-D045--text regarding contract close-out
procedures has been removed from the DFARS and relocated to
the DoD
Procedures, Guidance, and Information (PGI) resource; (ii)
DFARS
Case 2004-D017--text regarding combating trafficking in
persons has been removed from the DFARS (sections 222.17 and
252.222-7006) because it is now covered in the FAR; (iii) DFARS
Case 2007-D005--a new DFARS subpart 212.1 requires that, when using FAR Part 12 procedures
for acquisitions exceeding $1 million in value, the
contracting officer must determine in writing that the
acquisition meets the "commercial item" definition
in FAR 2.101, and the contracting officer must include the
written determination to this effect in the contract file;
(iv) DFARS
Case 2007-D010 deletes text regarding withholding payments
on T&M and labor-hour contracts from DFARS 232.111 and
252.232-7006, because the subject is covered in FAR 32.111 and
52.232-7; (v) DFARS
Case 2006-D053--an interim rule amending the DFARS
(sections 232.004 and 235.006) to implement Section 818 of the
National Defense Authorization Act for Fiscal Year 2007, which
requires DoD to modify its regulations regarding the
determination of contract type for major development programs
to address the assessment of program risk, and (vi) DFARS
Case 2007-D023--an interim rule amends DFARS 225.1101 and
225.7503 to reflect increased dollar thresholds for
implementation of various trade agreements.
You can read an
interesting story on earmarking issues here.
|
| January 19 |
I don't discuss
every single case here that I list on other pages of the site,
but the story behind the Court of Federal Claims' decision in
the International
Management Services (IMS) protest deserves some space.
Shortly after a firm won a small business set aside, three of
its competitors (including IMS) protested that it was not
small. They won, so the agency rescinded the contract and
awarded it to IMS. The two competitors who had originally
protested the first award with IMS then challenged IMS' small
business status, and they won. So, IMS lost its contract, and
one of the remaining two competitors ascended the throne.
There were further fights between the competitors over their
status. Then, at the CoFC, IMS claimed that both the remaining
companies were other than small and that the solicitation
should never have been set aside in the first place. IMS lost
on standing and justiciability issues, but the overriding
impression one gets from the case is the administrative
nightmare often created in the course of carrying out even a
laudable mandate.
|
| January 16 |
The GAO
sustained a protest by Superlative
Technologies. After the agency cancelled a solicitation
because source selection sensitive information may have been
improperly provided to an offeror, the agency turned around
and awarded a sole source contract to a team that included
that same offeror, which had submitted essentially the same
proposal as it had in the canceled procurement. The GAO hinted
the agency may have chosen this course of action just to avoid
further scrutiny of the original problem. The agency? The
Department of Justice.
|
| January 15 |
The
largest government contractors receive the most contracts without
competition. Now, there's a big surprise. [Sarcasm]
The VA has
rewritten its acquisition
regulation (VAAR), 48 C.F.R. Chapter 8, in
"plain language."
|
| January 14 |
LABAT-Anderson
lost its principal appeal before the ASBCA because (i) to the
extent the ambiguity of which it complained was patent, it
failed to raise the issue with the Contracting Officer prior
to bidding; and (ii) to extent the ambiguity was latent, the
contractor's interpretation was outside the "zone of
reasonableness." In any event, the contractor had not
relied on its suggested interpretation in bidding the job.
|
| January 11 |
The GAO
sustained a protest because the procuring agency determined a
bidder was nonresponsive
due to lack of SDVOSB status, a matter that is within the
exclusive jurisdiction of the SBA.
Need a
quick refresher course in constructive changes, defective
specifications, government misrepresentations, and
"jury verdict" quantum calculations? Metric
Construction Co. is the case for you. The contractor
prevailed in its claim for the costs of repairing leaks in a
roof it had installed. The court found (i) the Government's
design specifications for the roof support structure were
defective (even though the specs for the roof, itself, were
performance specifications) and (ii) the Government gave an
ambiguous, misleading reply to the contractor's request for
guidance as to how to proceed once the contractor noticed
problems with the roof installation during performance. In
addition, the court used an approximation method for
calculating the contractor's damages: "No better
method (other than the rough calculations presented in this
opinion) for computing damages exists, given the perplexing
nature of the origin of roof leaks, which would provide a more
precise dollar amount for the [Government's] liability in this
case."
EPA is
amending its acquisition regulation (48 C.F.R. Chapter 15) to
add a section 1515.401-70 (along with associated contract
clauses), which establishes award
term incentives as a means of enabling a contractor to
become eligible for additional periods of performance under a
current contract by achieving prescribed performance measures
under that contract.
A
partnership of Fluor, Honeywell, and Newport News (a.k.a.
Savannah River Nuclear Solutions) has won a 5 year, $800
million per year contract to operate and manage the Savannah
River nuclear site.
|
| January 10 |
Several
DFARS amendments have been published: (i) DFARS Case
2006-D032: revisions to harmonize DFARS online representations
and and certifications requirements (ORCA)
with those in the FAR; (ii) DFARS Case 2006-D051: an interim
rule to implement the Defense Authorization Act for Fiscal
2007 requirement that prohibits contractors who act as lead
system integrators on major systems acquisitions from
having any financial interest in the development or
construction of any system element unless an exception
applies; (iii) DFARS Case 2007-D019: a final rule to address
procedures for preparation of the written determination
required by the FAR that none of the functions to be performed
by contract are inherently
governmental; (iv) DFARS Case 2007-D016: an interim rule
implementing another section of the National Defense
Authorization Act for Fiscal 2007 to establish a quality
control policy for the procurement, modification, repair, and
overhaul of ship
critical safety items; (v) DFARS Case 2006-D023: a final
rule implementing the Federal Information Security Management
Act of 2002 (44 U.S.C. 3541 et seq.) to address
training requirements that apply to contractor personnel who
perform information
assurance functions for DoD; (vi) DFARS Case 2006-D062: an
interim rule implementing the Dominican Republic-Central
America-United States Free
Trade Agreement with respect to the Dominican Republic,
and adding Bulgaria and Romania to the list of countries
covered by the World Trade Organization Government Procurement
Agreement; and (vii) DFARS Case 2006-D024: a final rule to
address requirements for the distribution of material
inspection and receiving reports
under DoD contracts.
|
| January 9 |
Ezenia!
strove mightily to convince the CoFC that it was not
protesting the Army's earlier decision to standardize the
software it was using for a particular purpose for reasons of
interoperability (by specifying Adobe Connect software), but,
instead, was challenging an invalid sole source award. The
CoFC concluded that the standardization decision was, in
reality, what Ezenia! was protesting and that the court lacked
jurisdiction because such a protest was not of a procurement
or of a solicitation.
|
| January 8 |
In DKW
Construction, the CBCA denied the contractor's appeal from
a government claim to collect an overpayment on a T&M
contract. The contractor argued (for the first time on appeal,
which didn't help) that it was forced to enter into the
contract at a much lower ceiling price than its proposed
price. The Board noted that, since the contractor was free to
stop work when it reached the ceiling, the source of the
alleged duress was difficult to discern. The contractor also
argued that the Government's audit of its costs was improper.
The Board noted that the contractor had participated fully in
the audit process without objection.
|
| January 7 |
Two DoD
contractors have been charged with conspiring to steal
information on fuel supply contracts.
|
| January 4 |
OFPP is proposing to issue a policy letter on the
acquisition of green
products and services by federal agencies.
|
| January 3 |
In a press release, the GAO announced that it was
sustaining (in part) Pemco
Aeroplex's protest because the agency had not properly
evaluated changes in the awardee's cost proposal. The Press
Release noted the GAO was not addressing the protester's
contentions of bias because the source selection official
associated with those contentions had (apparently) committed
suicide, and the matter was still under investigation.
John Kerry has criticized
the SBA's proposed rules for women-owned small business
contracting (see December 27 entry below) as being too
narrow in scope.
|
| January 2 |
The Bureau
of Industry and Security has issued a
slew of revisions to the Export Administration Regulations
(EAR), most of which are technical corrections. However, there
are some substantive revisions, including removing certain
non-Country Group D countries from Country Group D, removing a
reference to Libya under embargoed destinations, clarifying
the requirements for obtaining an Import Certificate or an
End-User Statement, changing Validated End-User report
requirements, and removing references to certain entries on
the Commerce Control List.
The ASBCA
published five decisions, all originally issued in late
December, involving (i) government
deductions for substandard work, (ii) PPA
interest, (iii) an
interest claim released by a contract modification, (iv) a
net credit due the Government on a convenience termination,
and (v) the
prime's failure to certify a sponsored subcontractor claim (even
though the sub had certified it).
|
| January 1 |
I've
written a
review and analysis of
developments in government contracting in 2007. I'll probably be adding a few more
2007 developments to it as they straggle in over the next few
days.
If you'd
rather access the 2007 blog instead of the 2007 procurement review, you can
find the complete 2007 blog here.
|
|
_________
|
2007
|
|