Stan Hinton

 

2025 Procurement Review--Contract Disputes



Contents

Boards of Contract Appeals

Court of Federal Claims

Federal Circuit

Jurisdiction/CDA 

CDA/Jurisdiction

CDA/Jurisdiction

Changes,  Breach, Interpretation

Changes/Breach/Contract Interpretation/Defective Specs

Terminations

Terminations

Terminations

Fraud/Anti-Kickback

Costs/CAS

Costs/CAS

EAJA

Quantum

Discovery, Evidence, Procedure

Changes

Procedure

Fraud

EAJA

EAJA/Attorneys Fees

Supreme Court

 

Boards of Contract Appeals (ASBCA, CBCA, PSBCA, and GAOCAB)

Jurisdiction/Standing/Timeliness/Contract Disputes Act (CDA) Issues    

In John Blankson, the CBCA held it lacked CDA jurisdiction over an appeal from a Contracting Officer's letter terminating a contract for convenience even though that letter was labeled a COFD, notified the contractor of its appeal rights, and explained that the termination was based on certain contractor actions criticized by the Contracting Officer. Similarly, In Tesla Liliana Reyes Ramirez, the CBCA held it lacked jurisdiction over an appeal of the termination for convenience of a personal services contract absent a monetary claim from the contractor.

In Cobeal Consulting Group, an appeal from a default termination, the ASBCA held that it lacked jurisdiction over monetary claims for increased costs, return of withheld liquidated damages, and time extensions because they had not previously been properly submitted as claims to the Contracting Officer for a decision (the contractor had submitted two, uncertified REAs in excess of $100,000 to the Contracting Officer, one of which concerned matters not mentioned by the contractor on appeal and the other containing no certification at all).

In Relyant Global LLC, the ASBCA directed the Contracting Officer to issue a decision on a claim two months faster than his proposed date because taking nine months to issue a decision on a seven-page claim with two attachments was unreasonable.

In Envistacom, LLC, the ASBCA denied the Government's motion to dismiss based on contractor's alleged conflation of claims from two different contracts and ambiguities in its Complaint concerning that same alleged issue because, inter alia, the Government's own responses to the claim and the Complaint clearly indicated the Government was not under any misapprehension at all concerning the contract to which the claim related or the nature and amount of the claim. The Board also denied the contractor's motion for a default judgment based on the Government's allegedly deficient Rule 4 filing and its frivolous motion to dismiss because neither is grounds for the harsh sanction of default.

In Nanka Constr. Co., the ASBCA dismissed an appeal that did not clearly indicate the person filing it was authorized to do so under Board Rule 15(a) after the appellant failed to respond to multiple Board orders to provide that explanation.  

In Boyd Atlanta Rhodes, LLC, the CBCA denied the Government's motion to dismiss a lessor's claim for damages resulting from alleged government changes and/or breaches that delayed the date when rents would commence under a building lease, including the lessor's assertion of a "cardinal delay." The Board rejected the agency’s interpretation of the lease as giving the agency an unrestricted ability to make pre-occupancy changes without any cost. 

In KiewitPhelps, the ASBCA denied the Government's motion to dismiss an appeal for the alleged lack of a claim certification because a signature by an authorized official on a claim letter where the actual certification language is part of an attachment to that letter is a defective certification that can be corrected. 

In Frontline Support Solutions, LLC,  the ASBCA dismissed a subcontractor's appeal for lack of jurisdiction because the sub lacked privity of contract with the Government in a situation where the prime had neither sponsored the appeal nor acted as an agent for the Government. The Board rejected the sub's argument that there were extraordinary circumstances justifying its appeal (the Government's continued payments to the prime despite the Government's alleged knowledge of the prime's fraud and insolvency). 

In Direct Steel, LLC, the ASBCA denied the Government's motion to dismiss an appeal for failure to state a claim because, viewed in the light most favorable to the appellant, its Complaint alleged facts sufficient to satisfy all four elements of a superior knowledge claim.  

In Top Level Constr. Co., the CBCA first decided that the contractor had submitted four separate claims to the Contracting Officer (three under one PO and one under a second) because they were based on different facts and theories of recovery, and that only one of them had been addressed by the Contracting Officer in his decision. The Board dismissed the appeal of that claim as untimely filed. However, the Board retained jurisdiction over the appeals of the other three claims on the theory that they were deemed denied by the Contracting Officer's inaction on them. 

In US Pan American Solutions, LLC, the ASBCA dismissed an appeal (that appellant conceded was filed one day late) of a default termination notice, holding that the following language in the notice was satisfactory: "Your company has the right to appeal this decision under the Disputes clause at Federal Acquisition Regulation (FAR) 52.233-1." Subsequently, the Board denied the contractor's motion for reconsideration.

In Stormwater Plans, LLC dba SWP Contracting & Paving, which involved the appeal of the Government's affirmative claim for liquidated damages in a contract for construction of an aircraft hangar, the ASBCA denied the Government's motions to dismiss two of the contractor's claims for their alleged failure to have previously been presented to the Contracting Officer for a decision: (i) a claim for breach of the implied duty of good faith and fair dealing because it was based on the same allegations of operative facts previously presented to the Contracting Officer (specifically, numerous allegations that the agency's actions or inactions interfered with the contractor's performance—including various design issues, site conditions, and delays caused by the agency's failure to timely review and approve the contractor's proposals); and (ii) a claim for the impact of defects in the Government's drawings because those allegations would not require the Board to consider evidence different from and unrelated to those presented in the contractor's previous claim to the Contracting Officer. The Board, however, granted the Government's motion to dismiss a claim for the return of liquidated damages for work pertaining to lightweight concrete because that claim had not previously been presented to the Contracting Officer, even though the it was an affirmative defense to the Government's liquidated damages claim, because it would involve an adjustment in contract terms and, therefore, must be first presented as an affirmative claim to the Contracting Officer under the CAFC's precedent in M. Maropakis Carpentry, Inc. 

In Logistics and Rental Car SARL, the ASBCA granted the Government's motion to dismiss an appeal as tardy because the appellant did not dispute the date it had received the emailed decision from the Contracting Officer, and the appellant's President's illness and emergency operation did not excuse an appeal that was late (by more than 400 days). 

In 5 Stones Intelligence, Inc., the CBCA granted a joint motion to dismiss an appeal because the stipulated facts established that the contractor (a) never submitted a certified claim, (b) made its submission to someone other than the Contracting Officer, and (c) initiated its appeal based on that other individual's response. 

In Comp Environmental, Inc., which involved a fixed-price contract to rehabilitate a parking area, the CBCA denied the Government's motion to dismiss the appeal for failure to state a claim, holding that the appellant had plausibly alleged that extra work to raise the elevation of a levee could not be discerned by a reasonable bidder from the contract documents, which also required the Government to obtain necessary permits so that the "Permits and Responsibilities" clause did not shift responsibility for obtaining permits or liability for permit conditions to the contractor. 

In Walsh Turner Joint Venture II, although the ASBCA denied the Government's motion to dismiss the appeal for lack of jurisdiction due to the omission of the "II" in the appellant's name since that was  a mere misnomer that did not prejudice the Government, the Board granted the Government's motion to dismiss the appeal for failure to state a claim because the  issuance of an RFP for the inclusion of a  COVID-related clause in the contract and then its rescission before the contractor responded to it was not a constructive change since that clause was never incorporated in the contract. 

In King & George, LLC, which involved the interpretation of a firm, fixed-price 8(a) contract for facilities operations and maintenance services for nine federal buildings in Florida with performance-based specs and also minimum required staffing levels, the CBCA held that the plain meaning of the contract's "Application of Criteria for Deductions (Non-Performance)" clause did not permit the Government to make unilateral deductions simply for staffing shortfalls, even though the contractor seemingly had initially acquiesced in that interpretation before finally refusing to sign a bilateral mod memorializing those deductions. 

In UnlimitComp, LLC, the CBCA dismissed a direct appeal by a subcontractor for lack of jurisdiction. 

The ASBCA dismissed an appeal by GE Renewables US, LLC (which sought a declaration that FAR 52.216-4 was enforceable and, therefore, that the contractor had a right to a price adjustment under the clause) because the only result of a favorable ruling would be the price adjustment as opposed to a change in contract performance or the avoidance of costs, so the claim was essentially monetary claim, but lacked a statement of a sum certain.  

In Peace Ambition Constr. Co., which involved a contract to provide forklifts for the Government's use at an Air Force base, the ASBCA denied the Government's motion to dismiss the appeal for lack of jurisdiction (based on the Government's contention that the dispute was one between the contractor and its subcontractor on a contract entered into after the T for C of the contract that was the subject of the appeal) because an email accompanying the contractor's notice of appeal to the Board which characterized the dispute as one between the contractor and its subcontractor was irrelevant to the question of the Board's CDA jurisdiction, which depended solely on the claim actually submitted to the Contracting Officer. 

In Outside the Box, LLC, the appellant requested the CBCA to dismiss an appeal not filed within 90-day appeal limit "without prejudice." However, because the contractor had already missed the appeal window, a "without prejudice" dismissal would be inapt, and the Board noted that a "with prejudice" dismissal would be applicable only to appeals that had reached the merits.  The Board simply dismissed the appeal for lack of jurisdiction, noting that the appellant still had time to file suit in the CoFC.

In Missouri Higher Education Loan Authority, the CBCA granted the parties' joint motion to dismiss the appeal as moot after the Contracting Officer withdrew underlying decision on which it was based. 

In Scot Cardillo dba Engineers Tooling Support, the ASBCA held it lacked jurisdiction over the counts in the Complaint concerning claims not encompassed by the contractor's notice of appeal and claims that repeated those covered in an older,  unappealed Contracting Officer's decision. 

In two decisions, the PSBCA held that a "termination on notice" is a contract action rather than an appealable final decision, and thus cannot be appealed absent a separate monetary claim by the contractor, even when the Contracting Officer erroneously labels it as a final decision and and advises the contractor of its appeal rights: BAM Dart, LLC and David F Grab

In Sauer Inc., the ASBCA held that the following language in a settlement agreement between the prime and its sub to settle the sub's claim against the prime's surety in separate litigation preserved the prime's ability to file a pass-through claim on behalf of the sub and established that the prime remained conditionally liable to the  sub for the damage allegedly caused by the Government, so that the Severin doctrine was not implicated:

Notwithstanding the foregoing, the Parties reserve from this release all claims and claim rights that exist as against the Government, including any and all pass-through rights and related payment obligations, which are reserved for the sole and express purpose of satisfying any legal requirements necessary to preserve such claims for [the prime] to pursue the CDA Claim and ASBCA Appeal as contemplated herein. It is the express intent of this paragraph to preserve only such claims, rights, and obligations as are necessary to satisfy the existing requirements of the Severin doctrine consistent with its most recent interpretations by applicable authority.
The ASBCA also held that the release language in a change order between the prime and the sub was not an "iron clad" release of all liability by the prime to the sub because, inter alia, the district court overseeing the litigation between the sub and the surety had found that to be a question of fact and the Anti-Assignment Act was not applicable to this situation. 

In Geotech Environmental Services, Inc., which involved T for C claims under a contract to drill two wells, the CBCA denied the Government's motion for summary judgment, which had been based, in part, on the Government's allegation that the following statement in the Complaint was somehow disqualifying: "[Appellant] is entitled to all of its allowable costs, even when the costs do not comply in all respects to the contract requirements." The Board noted that: (i) a T for C turns a fixed-price contract into a cost reimbursable contract for work performed prior to the termination; and (ii) the contractor in this case would continue have all the usual burdens to prove up the costs it incurred for allegedly extra (changed) work prior to the termination. The Board, in other words, was not willing to dismiss an appeal based upon some inartful drafting of one sentence in the Complaint.

In Sayar Development, Inc., the ASBCA addressed the Government's motions to dismiss various of the contractor's claims. The Board dismissed the contractor's appeal of a default termination because the appeal had not been filed for more than 13 years following the original Contracting Officer's decision. The Board also dismissed claims that were not filed until the six-year limitations period had expired or that the contractor conceded had never been presented to the Contracting Officer for a decision. Concerning one claim that the Government moved to dismiss for failure to comply with the CDA's requirements for a claim, the Board held that a statement in that claim "Asking for Decision of CO to be Final about Contract and Process of our Performed work Invoices" satisfied the CDA's requirement for a "demand" for a decision, and labeling that claim document an "invoice" was not fatal where it was something other than a routine request for payment for contract items or services (here a request for costs following a default termination). 

In Samho Enterprise, the ASBCA held: (i) it lacked jurisdiction over the portion of the appellant’s appeal seeking specific performance compelling the exercise of a contractual option; and (ii) the contractor's claim for "no less than" a stated amount did not comply with the requirement for a sum certain.  

In Blanchard's Contracting LLC, the CBCA held that it lacked jurisdiction over an appeal where the purported claim was previously sent to the GSA's headquarters but did not identify any Contracting Officer as an addressee (and no Contracting Officer had issued a decision on the claim): "It is not sufficient to place the words 'contracting officer' on a document and transmit it to random individuals in a large office building. The CDA requires submittal 'to the contracting officer for a decision.' 41 U.S.C. § 7103(a)(1) (emphasis added)." 

In All Phase Services, Inc., which involved the appeal of a default termination, the CBCA held it had jurisdiction the contractor's allegation of a mistake in bid and its request for rescission of the contract absent a prior claim to the Contracting Officer on those issues because, in raising them, the contractor was not seeking money damages or an adjustment in the contract's terms.  

In Industrial Fabrication Resources, Inc., the ASBCA dismissed an appeal after the appellant/corporation failed to respond to numerous Board orders to show cause why the appeal should not be dismissed for failure to enter an appearance by a representative meeting the requirements of Board rule 15(a).  

In CGS-Ace Security LLC, the CBCA denied the Government's motion for summary judgment (based on the allegation that the  appellant was not the contractor) because (i) the appellant's was the name entered into Box 15 (labeled "Name and Address of Offeror") on the SF 33; (ii) the "Order of Precedence" clause ranked the information in the SF 33 (part of the Schedule) over a conflicting name in an exhibit to the contract; and (iii) there is no law stating that awarding a contract to an entity different from the one named in the proposal voids the contract:

[The Government] does not establish that a contract must be deemed awarded to the entity whose name is on the proposal, regardless of the plain language of the contract itself. Thus, even if the award of a contract to CGS-ACE Security LLC was found to be improper as a matter of law, such a finding would not establish that [the agency] did not enter into a contract with CGS-ACE Security LLC.

Changes/Constructive Changes/Contract Interpretation/Breach/Authority

In HDR Eng'g Inc., the ASBCA sustained an appeal by an architect-engineer (A-E) of a government claim for professional negligence in the design of a dam pursuant to FAR 52.236-23 because, under three-pronged test established in Parsons Main, Inc., the Government failed to establish that: (i) the construction contractor substantially complied with the A-E's design in the manner intended by the A-E; and (ii)  in its design, the A-E exercised its skill, ability and judgment negligently, instead of with reasonable care. 

In Fort Fairfield BP, LLC, which involved the interpretation of two lease terms ("real estate tax base" and "full assessment"), the CBCA held that the GSA had used the correct year for the real estate tax base because: (i) it was the first full tax year after the lease commenced; and (ii) that year's taxes were based on a "full assessment" since all improvements contemplated in the lease were complete before the taxing authority’s assessment date. 

In Phylway Constr., LLC, a Rule 11 proceeding, the ASBCA held that under the "Damage to Work" clause in a contract for clearing, grubbing, and vegetation removal, excavation for a new drainage canal, and placement of uncompacted embankment and compacted embankment, the contractor could not recover for its costs of clearing debris deposited on the work site by hurricane storm surge during performance because that debris did not fall within the definition of "damage" and did not require "repair" within the meaning of the clause. 

In IVA’AL Solutions, LLC, a decision on entitlement in a contract with a tribally-owned participant in the SBA's 8(a) business development program designed to provide healthcare professionals to the Air Force, the ASBCA held that: (i) in answering preaward questions from bidders, the Government withheld superior knowledge concerning a predecessor contractor's difficulties in maintaining adequate staffing and its vacancy rates for unfilled positions; (ii) the disputed FFP line items (with a quantity of hours and a unit price per hour) formed a fixed-price, level-of-effort term contract, under which the the contractor was entitled only to recover for work actually performed; (iii) a bilateral modification established the contract's billing method and superseded an allegedly contrary statement by the Contracting Officer; and (iv) the Government did not breach the implied duty to this contractor of good faith and fair dealing by failing to enforce vacancy rates on a predecessor contract with a different contractor. 

In Fluor Federal Solutions, LLC, which involved contract interpretation in a fixed price regional base operations support contract for four Naval facilities in Florida, the ASBCA held that: (i) preaward questions (RFIs) and answers were incorporated in the contract; and (ii) based on the contractor's proposal (to which the Government did not object and which was incorporated into contract), the contract specifications, and surrounding circumstances, the contract required the contractor to "maintain" a previously populated database to be provided by the Government, and the contractor was entitled to recover as a constructive change to the extent the database provided by the Government was unusable, even after the Government's efforts to scrub its data, which, in turn, required the contractor to create the data in it (not as a volunteer). The Board denied the contractor's claims for the following allegedly extra work involved in maintaining and repairing equipment: (i) claims based on the allegedly excessive age of the equipment and equipment with pre-existing conditions (because the contract stated the equipment would be made available "as is"); (ii) claims for allegedly having to make capital improvements (because this work was within the contract's definition of required "alterations"); (iii) claims based on work allegedly "not in contract" (because (a) the contract work was described in terms of systems rather than individual items, (b) the contract warned the list of items in it was not complete, and (c) the contractor's employees conceded that they developed this claim category without reference to what the contract required); (iv) various other categories of claims (e.g., negligence, incrementing, bundling, lack of access, nuisance, and force majeure) (because the contractor failed to present adequate evidence to support them or they involved work required by the contract); and (v) claims  for superior knowledge, breach of the "Government Property" clause and breach of the implied duty of good faith and fair dealing, all based on the Government's alleged misrepresentation of the condition of the equipment that needed to be repaired (because, inter alia, of the multiple statements in the fixed price contract that the equipment would be provided "as is"). Finally, in part because the contractor succeeded on one, but not all, of its claims, the record was not sufficient for the Board to determine that the agency's "marginal" and "unsatisfactory" CPAR ratings were justified, so the Board returned the case to the agency to review its CPAR ratings in light of the Board's decision.

In Quality Trust, Inc., building on its prior decision concerning a contract for road and bridge repair, the CBCA held that the contractor could not recover for suspensions of work (including a recovery based on the Eichleay formula) because: (i) the Government was not the sole cause of any delay (e.g., one of the suspensions was to allow the contractor to address a mistake in price, another to address a cure notice for deficiencies in its performance); (ii) in entering the contract, the contractor had agreed there would not be any masonry work on the bridge during bird nesting season; and (iii) the suspension periods were reasonable.

In David Boland, Inc., which involved a contractor's claim on behalf of its sub in a contract for the replacement and construction of floodwalls as part of a hurricane protection project in New Orleans, Louisiana, the ASBCA held that the contractor had failed to establish any of the four elements of a Type 1 differing site condition because:  (i) the solicitation warned of the possibility that conditions might vary from those described in the solicitation; (ii) the contractor failed to present adequate evidence that the conditions were unforeseeable, especially where the solicitation indicated they might exist; (iii) the contractor failed to present evidence of its contemporaneous interpretation of the contract documents or that it had relied on its alleged interpretation; and (iv) the contractor failed to establish the site conditions caused the alleged damages. The Board also denied a defective specification claim because the specs were performance specs which meant the Spearin doctrine (United States v. Spearin, 248 U.S. 132, 136 (1918)) was inapplicable.

In Fuel Tank Maintenance Co., LLC, over a dissent concerning one aspect of the claim, the ASBCA held that, in a contract for the construction of relief wells and various modifications to a pump station: (i) the contractor was not entitled to compensation for 21 days of delay that the contractor's own expert report stated was concurrent or for 9 non-federal holiday days during an extended holiday that the contractor took from the job without seeking the Government's approval; (ii) an email from the COR to the contractor could not vary any contract requirements regarding an electrical impact study because the COR lacked authority to change the contract; (iii) motor pump testing ordered by the Contracting Officer under the "Inspection of Construction" clause required the contractor to be compensated when it was determined the motors functioned as contractually required; (iv) the contractor was entitled to compensation for delay caused when an issue with monorail clearance that prevented a subcontractor's work was discovered while that sub was on the way to the site; (v) the contractor was required to submit a "variance" and obtain approval for a change to a water test, and  the length of suspension of work associated with this process was reasonable; (vi) the contractor was not entitled to compensation for its second excavation of a discharge pipe absent evidence the Government (or the contract) required the first excavation, which occurred before the installation of larger (changed) motors that the contractor already knew would require a separate excavation; (vii) the contractor could not change from the method of charging for field office overhead identified in its proposal by an employee with authority to do so, as it was directed to do by a special solicitation provision that was not inconsistent with FAR 31.105(d)(3) or otherwise improper, despite arguments by the dissent that the special provision was improper and that, in the circumstances, the contract should have been reformed due to a unilateral mistake by the contractor's employee.

In Maverick Constructors, LLC, the ASBCA denied all the contractor's claims in a contract for the construction of water resource area levees, canals, pumping stations, control structures, siphon, access roadways, and appurtenant work on a water conservation restoration project. Specifically, the Board held that: (i) allegedly unsuitable material (rocks) in an excavation did not constitute a Type I differing site condition because, inter alia,  the rocks were not materially different from the material clearly described in several contract documents; (ii) the Government's provision of an additional borrow area within seven days of notice from the contractor that satisfactory material in the original area had been exhausted was reasonable in the circumstances and did not breach the implied duty of good faith and fair dealing where the contractor had failed to produce evidence for its assertion that it had submitted multiple notices prior to the one at the onset of the seven day period; (iii) the contractor could not recover for its costs of reconstructing the original levee it had built that allegedly met all contract requirements because the Government's daily inspection reports during that construction repeatedly had noted deficiencies in its fill material; (iv) the Government's ACO's comments on various submittals by the contractor were intended to assist it in revising the submittals and could not properly be interpreted as change orders; (v) the contractor was on notice from the Government of a defective specification prior to undertaking the action that it now claimed was compensable due to that defect; (vi) there was insufficient evidence concerning the contractor's allegations that it was required to create a 5-foot vegetation-free zone and establish grass seed long after the period during which the work was required by the contract; (vii) the contractor was not entitled to almost two years of excusable delay and a corresponding remission of liquidated damages because the contractor failed to establish the extent of  delay, the harm resulting from alleged delay, and that any delay days were solely attributable to government actions (a complete failure of proof).

Alares Constr., Inc. is an interesting CBCA case involving claims for extra work and delays on a construction project at a VA medical center. The presiding judge died after the hearing, so a new judge read the briefs and issued the decision. In connection with its post-hearing briefing, the contractor made several unsuccessful motions. The contractor wanted the CBCA to exclude documents impeaching one of the contractor's witnesses from the Appeal File because those documents were not mentioned during the hearing. That request was denied because, inter alia, the documents had been in the appeal file for as long as for five years before the hearing, and the deadline for objecting to documents in the file had long since passed. The contractor wanted the Board to overturn the trial judge's ruling that the contractor had failed to qualify its witness as an expert on delay claims and critical path analysis. That motion was denied because the original ruling was correct and because the trial judge (without objection from the agency) had allowed the witness to present his opinions and his report as lay opinion testimony. The contractor asked the Board to draw an adverse inference (that the Contracting Officer's testimony would have benefited the contractor) from the fact that the Government had not called the Contracting Officer to testify at the hearing. The Board gave several good and sufficient reasons for denying this motion, but the only one it really needed, imo, was that the Contracting Officer was also on the contractor's witness list, but the contractor chose not to call him and also had declined the new judge's offer to re-open the hearing to allow additional testimony. On the merits, the Board found the contractor's critical path report and analysis unpersuasive, but (to the Government's apparent chagrin) instead of denying the delay claim in its entirety, as the agency had requested, the Board relied, to some extent, on the agency's expert's critical path analysis, which had concluded the contractor was entitled to some of its delay claim. The bulk of this very long decision contains analyses of many issues concerning the cause and extent of the delays, too many to summarize here. Apart from its delay claim, the contractor presented no evidence beyond speculation to support its claim that the Government had breached its implied duty of good faith and fair dealing by allegedly failing to reasonably review and approve the contractor's change order and delay requests out of fear of funding limitations. The Board denied another claim because the contractor had failed the requirement to coordinate the work of its subcontractors, which resulted in one subcontractor removing some work installed by another sub, which, in turn, necessitated the reinstallation of that work. 

In 1102 Co., a case conducted in accordance with the CBCA's small claims procedure, the Board held that in a contract to provide, inter alia,  personnel with security clearances  at fixed monthly rates for full-time equivalent work days of eight hours each, the contractor was not entitled to bill for individuals until their security clearances were approved, and the agency did not unduly delay approval of a security clearance, especially where the solicitation warned that background checks could require more than 30 days.  

In Conrad Shipyard, LLC, the ASBCA held that: (i) the Government’s solicitation (expressly promising to pay up to a $1,000,000 stipend to all offerors who competed in the solicitation with an acceptable proposal and pricing that was to remain firm until award, but did not receive the award) did not create an implied-in-fact contract as the appellant claimed, but rather amounted to an express offer by the Government to enter a unilateral contract in return for specified performance by offerors; (ii) once the appellant had submitted its proposal, the Government's offer became an irrevocable option contract; (iii) the appellant, however, did not complete its performance of the unilateral contract because it withdrew its offer before the Government made an award, so the appellant was not entitled to any of the stipend. The Board also dismissed a count in the Complaint for breach of the implied duty of good faith and fair dealing because that claim had not previously been submitted to the Contracting Officer for a decision.

In Vectrus Systems Corp., the ASBCA denied the contractor's changes, breach, and negligent estimates claims, because the "workload data" appended to a solicitation for a fixed-price contract for laundry services (and later revised in a bilateral mod) did not establish limits on the number of items that the contractor was obligated to clean for the fixed prices and did not entitle the contractor to extra compensation for certain categories of items where the work exceeded the corresponding amount listed in that data, especially where the contractor participated in deriving the workload data for the mod and was paid the full contract price even in the areas where the actual number of items cleaned was less than the number in the workload data.

In Skanska USA Civil Southeast, Inc., which involved an FFP contract with the Navy for the demolition of two existing piers and construction of a new pier at the Norfolk Naval Shipyard, the ASBCA denied the contractor's claims for extra costs associated with the difficult removal of interior timber bearing piles. First, the Board held that the contractor failed to produce sufficient evidence concerning three issues necessary to support its claim that it was impossible to fully extract the interior bearing piles while complying with the dredge limits: (i) whether any other contractor was able to comply with the specifications; (ii) whether the specifications required performance beyond the state of the art; and (iii) the extent of the contractor’s efforts in meeting the specifications. In connection with this claim, the Board held that, when read in context, neither of two communications from the Navy was an admission of impossibility. Secondly, the Board held that, although a note in the solicitation that "[a]ll timber structure including but not limited to piles, bent caps, relieving platform shall be assumed to be creosote treated" was a representation concerning a site condition, the contractor's Type 1 differing site condition claim failed because: (i) its own prior work on the site in a contract mentioned in the solicitation gave it as least constructive notice that the bearing piles were untreated, which the contractor should have foreseen; and (ii) the as-built drawings, which the contractor should have reviewed, indicated the piles were not treated. The Board also denied the contractor's Type 2 differing site condition claim because the contractor should have reasonably anticipated that the bearing piles would be degraded due to their prolonged exposure (for 70 to 90 years) to the adverse conditions under the piers.

In Sheffield Barbers, LLC (which involved a  contract to operate barber shops at AAFES locations) long after contract award, the Contracting Officer directed the contractor to stop charging extra for "fade" haircuts. The contractor submitted alternative constructive change, breach, and misleading estimate claims for the lost revenue and appealed their denials. AAFES then filed two motions for summary judgment. The first alleged that the contract required that fade cuts be charged only as regular cuts. The ASBCA denied that motion because the Contracting Officer (a) was aware that the contractor was charging extra for those fade cuts as "style" cuts, (b) acquiesced in the extra charges, and (c) did nothing to stop this practice for the first 15 months of the contract, which amounted to a waiver of AAFES' interpretation of the contract. The second motion for summary judgment was to dismiss the claim that the Government's estimates in the solicitation about the amount and type of cuts to be expected were misleading. The Board held that those estimates were based on the Government having allowed the predecessor contractor to charge extra for fades, and, therefore, were neither inaccurate nor unreasonable (and actually supported the contractor's breach and change claims). 

In ECC Int'l Constructors, LLC, one among a series of decisions involving a contract to design and construct a 20-building military compound in Afghanistan (this one involving claims for delay and remission of liquidated damages), the ASBCA held that: (i) the contractor's expert's delay analysis was not credible because he did not create a "fragnet" (fragmentary network) to analyze the effect of one significant source of delay on the project; (ii) the Government's admissions against interest that its 100% design review delayed the project could reasonably be interpreted to put that delay on the critical path, but the contractor's concurrent delay exceeded the number of days of delay caused by the Government, so the contractor was not entitled to any compensable delay; and (iii) despite failing to prove compensable delay, the contractor was entitled to recoup liquidated damages assessed by the Government for delays in the approval the 100% design submission because the contractor rightfully interpreted the contract to require the 100% design submittal only to incorporate the contractor's responses to the comments the Government had made in response to the 95% design submittal. 

In Gideon Contracting, LLC, which involved a task order to repair a dam, the ASBCA held that the order contemplated that suspensions of work would be required to allow the release of water when lake elevations exceeded a certain level, and, therefore, under the "Suspension of Work" clause, the contractor could recover only for the portions of the suspension periods where the Government inexplicably continued releasing water after the lake had reached the required level and, in another case, where the Government (again inexplicably) did not permit the contractor to return to work for five days after the required level had been reached. The Board also held that the Government waived its claim for liquidated damages for late completion of the work by waiting more than a year to assert that claim as a punitive response to the contractor's claim. 

In Chromalloy Component Services, Inc., which involved a contract to refurbish a major module of the F108 engine used on KC-135 aircraft, the ASBCA denied the incumbent contractor's claim for extra costs associated with increased prices for turbine fan blades and the Government's decision to change from contractor-acquired blades to GFM because: (i) the contractor did not properly allege, much less prove, that the Government possessed superior knowledge concerning the pricing and availability of the blades or that the contractor relied on any defective information from the Government in pricing its bid, and any alleged promise by the Contracting Officer concerning the issue came only after the contractor had submitted its bid; (ii) the contractor's claim for the costs of blades it ordered before the Government switched to providing the blades as GFM would be denied because the contract explicitly allowed the Government do do so; (iii) the contractor did not establish that a prior course of dealing existed that precluded a large order being placed near the end of the base year rather than during the first option year when it would have been performed and priced at higher option year rates, and, at any rate, the contractor had signed bilateral modifications memorializing the orders; and (iv) none of the above claims amounted to a  constructive change. 

In TransOx, Inc., a proceeding conducted in accordance with CBCA Rule 52 (its small claims procedure), the CBCA was faced with appeal involving the interpretation of  a very poorly drafted contract line item providing for a "[o]ne time delivery fee for any purchased items  . . .  each, per delivery, per patient" in a contract to provide home oxygen services to VA medical center outpatients. The Board held, inter alia, that: (i) in interpreting that provision, the Board would not look for assistance to language in the solicitation that was not incorporated into the contract; (ii) the VA's interpretation of the provision as providing only for a one-time delivery fee no matter how many deliveries were made would ignore all language in the line item after the words "one time delivery fee"; (iii) although the contractor's competing interpretation of that line item was problematic, it was within the zone of reasonableness, and since the VA had not offered a reasonable counter-interpretation, the contractor's interpretation would be adopted; and (iv) even if the language were ambiguous, it would be interpreted against the VA as its drafter. 

In UnitedHealthcare Insurance Co., which involved a contractor's (insurer's) dispute over money it had to pay out for an insurance claim, the CBCA granted the agency's motion for summary judgment concerning the  contractor's breach claim because the contractor failed to establish causation, i.e., what would have happened in the "non-breach world" if the alleged breach had not occurred. 

In A4 Constr. Co., which involved the Government's motion to dismiss appeals of claims involving defaulted firm, fixed-price ("FFP") contracts to design and construct training facilities for U.S. Special Forces in Colorado, the ASBCA held that: (i) a bilateral modification was an accord and satisfaction that clearly covered all the contractor's claims concerning delays from an earthquake and also released the Government from liability for those claims; (ii) a bilateral modification addressed (and released) claims for delays during the month of a flooding event, but the contractor could continue to pursue its claim for delays from that event in other months; (iii) a bilateral modification covered a gas piping change and clearly released further claims concerning that change; and (iv) although a mod exercising options did not contain release language and was not an accord and satisfaction of the contractor's claims for increased subcontractor costs due to the COVID pandemic, such costs are not recoverable in an FFP contract, but the contractor's claim for delay days attributable to the pandemic survived the Government's motion to dismiss. 

In GSI Pacific, Inc., which involved contract interpretation in a contract to remediate (remove munitions and explosives from) the Area M Munitions Response Site in Hawaii, the ASBCA held, inter alia, that: (i) a statement in the contract that "work is to be performed in accordance with" a "Decision Document" was sufficient to incorporate that document into the contract; (ii) a note in a section of the contract entitled "Background and History" that a Feasibility Study had  been conducted in the past was insufficient to incorporate that document into the contract; and (iii) alleged actions by adjoining landowners limiting the contractor's access to the site were not compensable because contract did not shift the risk of delays caused by third parties to the Government, which had obtained the necessary right-of-way forms from the landowners. 

In Gideon Contracting, LLC, which involved a task order to repair a dam, the ASBCA held that the order contemplated that suspensions of work would be required to allow the release of water when lake elevations exceeded a certain level, and, therefore, under the "Suspension of Work" clause, the contractor could recover only for the portions of the suspension periods where the Government inexplicably continued releasing water after the lake had reached the required level and, in another case, where the Government (again inexplicably) did not permit the contractor to return to work for five days after the required level had been reached. The Board also held that the Government waived its claim for liquidated damages for late completion of the work by waiting more than a year to assert that claim as a punitive response to the contractor's claim. 

In GSI Constr. Corp., a Rule 11 procedure involving a contract for renovation services, the ASBCA held that where the contract provided for one price during an initial base period and a higher set price in the event award was delayed, the contractor was entitled to compensation (pursuant to the "Suspension of Work" clause) where the contract had been awarded on time but notice to proceed and site access had been unreasonably delayed, even though the contractor failed to prove (a) that the delayed notice to proceed was a result of a deliberate misrepresentation by the Government and (b) that it should have received the full set contract price for a delayed award.

In Peraton, Inc., another Rule 11 proceeding, this one concerning a CPFF task order for technical systems engineering support services for the Navy’s Fleet Systems Engineering Team, the ASBCA held that a contract provision requiring the Contracting Officer to issue a contract modification if the Contracting Officer "determines, for any reason, to adjust the task order amount or the estimated total hours," was intended to cover only situations where the level of effort increased over the contract's estimated amount and did not entitle the contractor to obtain its full fixed fee when the contract work turned out to be below the estimated quantity because (i) the contractor's interpretation clashed with another contract provision; (ii) the Board's interpretation  was consistent with the normal principles of cost reimbursement contracting: (iii) the estimated quantity was just that and not a guaranteed minimum; (iv) the fixed-fee was a maximum, not a guaranteed amount; and (v) the contractor's negligent estimate breach theory was not applicable to cost-plus contracts. 

In Troop Contracting, Inc., which involved the interpretation of a contract to renovate a VA medical center, the CBCA held, inter alia, that all of the contractor's various theories of recovery (breach, constructive change, superior knowledge, etc.) for allegedly extra work in discovering and remediating lead based paint were based on the same set of allegations and failed because the contractor's interpretation that the contract had only very limited requirements for the disputed work was unreasonable, and, even if the contractor's interpretation were reasonable, the solicitation put the contractor on clear notice of the Government's contrary, reasonable interpretation, creating a patent ambiguity which the contractor was obligated to, but did not, attempt to resolve prior to bidding. 

In Tribal Health LLC, which involved a bridge contract with the Indian Health Service to provide hospital emergency room health care services, the CBCA held that the contractor was entitled to payment (in quantum meruit) at its bridge contract rates for work it performed in accordance with an email from the Contracting Officer directing it to continue to perform beyond the expiration of the bridge contract, even though the Contracting Officer's email identified rates lower than those in the bridge contract. 

In Yul Lim Construction Co., Ltd, a Rule 11 proceeding, the ASBCA held that: (i) a bilateral modification and release unambiguously covered the entirety of the contractor's delay claim, without any reservations; and (ii) the contractor failed to establish any special circumstances (e.g., duress, mistake, or misrepresentation) that would vitiate the release. Similarly, in Medical Receivables Solutions, Inc., the ASBCA held that a bilateral modification and the contractor's acceptance of the payment it called for unambiguously established both an unconditional release and an accord and satisfaction. 

In Warfighter Defense Inc., the ASBCA granted the Government's motion for summary judgment because the contractor never accepted the Government's purchase order in response to an RFQ either by signature or by performance, but instead repeatedly conditioned its performance on the Government's agreement to waive a contract requirement, which the Government never did. 

In JE Dunn Constr. Co., which involved a contract to design and construct the HVAC system for a medical clinic, the ASBCA held that: (i) the 15% safety factor required by the contract for the boiler design was clear, and even if it were ambiguous, that ambiguity was patent, obligating the contractor to inquire prior to bidding, which it did not do; (ii) the Government required the contractor to redesign the boiler system only to meet that safety factor, not to exceed it;  (iii) similarly, the Government required the contractor to redesign the humidifier system only to the extent necessary to comply with the contract requirement; (iv) the contractor's claim for compensable delay caused by the allegedly improper rejection of three of the contractor's design submittals  must be denied because, inter alia, (a) the contractor employed only a prospective, hypothetical delay analysis despite the fact that the contract had been completed, (b) there were valid reasons for the rejection of each submittal that the contractor's claim did not address, and (c) the contractor presented inconsistent, and ultimately, unsupported allegations of the length of the claimed delay; and (v) even though the Government conceded the hydronic piping installation issue was separate from the other claim issues and did delay the project's critical path, the contractor had failed to establish the extent of any delay.

The ASBCA addressed 16 claimed areas of allegedly extra costs in various way in ECC Int'l Constructors, LLC, which involved a contract to design and construct a 20-building military compound in Afghanistan. For example, although the Contracting Officer was found (repeatedly) to have essentially directed contract changes by requiring the contractor to comply with the Government's design reviewer's comments on its drawings, the Board denied claims whenever the contractor failed to present evidence of the Contracting Officer's involvement, e.g., the contractor's claim for being required to install additional electrical outlets and rework others. The Board also denied the contractor's claim for having to install dedicated electrical panels in communications rooms because that was already a clear, basic contract requirement. The Board held it lacked jurisdiction over the contractor's claim for additional spare rack capacity, which had not previously been presented to the Contracting Officer for a decision. The Board reduced other claimed amounts of damages for lack of proof or incorrect calculations by the contractor.

In Meltech Corp., which involved claims under a construction contract, the ASBCA: (i) denied the contractor's constructive change claim based upon a direction to replace some standard lighting fixtures after a test by the  fire inspector revealed inadequate emergency egress lighting because, inter alia, the contract required adequate lighting in those areas, and the contractor had immediately acquiesced in the test results, without alleging any flaws in them until much later in time; (ii) granted the contractor's Type I differing site condition claim for the added heat tracing it installed for relocated water piping due to unanticipated overhead obstructions in the first-floor corridor ceiling because, inter alia, the Government did not establish prejudice from the contractor's alleged delay in the notifying Government of the claim, and neither the pre-bid site visit nor the contract drawings put the contractor on notice of the condition; and (iii) the Government was not entitled to a credit where the contractor had installed shelving materials of the exact type and quality stated in the specifications even though the contractor had mistakenly included higher quality materials in its approved design submittal after contract award. 

In Healtheon, Inc., which involved claims under a contract to construct submersible electric pumps, diesel generators, fuel tanks, a pre-engineered metal building,  a concrete emergency shelter building, and other related work as part of a hurricane protection project, the ASBCA denied the contractor's claims based on allegedly defective specifications, constructive change, and breach of the implied duty of good faith and fair dealing related to the metal building work because the contractor failed to comply with a specification requirement that the contractor utilize a professional engineer to review the contract and provide calculations and drawings to support an enclosure classification for the building. The Board also held that: (i) the contractor had failed to sustain its burden of proof that  the compensation it had previously received from the Government for directed changes was inadequate; (ii) the Board lacked jurisdiction over a superior knowledge claim not previously presented to the Contracting Officer; and (iii) the Government had sustained its burden to support the liquidated damages it assessed for the contractor's tardy performance.    

In H&L Contracting LLC, which involved a contract to dredge shoaled sediments from harbor channels, the ASBCA held that the contractor was entitled to recover its extra costs of employing a subcontractor to utilize a larger dredge than the contractor had planned to use when it began the work because the Government had withheld superior knowledge concerning conditions at the site that would have precluded the contractor's use of the smaller dredge, and the solicitation had not put the contractor on notice to inquire about those conditions. 

In Thalle Constr. Co., the ASBCA was faced with the Government's motions for summary judgment on various contractor claims under an FFP contract for the  consruction of an auxiliary dam reinforcing berm and left rim stabilization at the Center Hill Reservoir in Dekalb County, Tennessee. Several claims involved a situation where one of the contractor's subs had gone out of business, requiring the contractor to switch to another sub. Concerning these claims, the Board held that:  (i) there was no constructive change because the contract only stated the original supplier had an acceptable product, without requiring that sub's use or guaranteeing that it would remain in business; (ii) the contractor failed to prove that the Government had superior knowledge that the original supplier could not meet the quality requirements because the Government had granted a variance to that supplier, and the contractor switched to another sub  because the original supplier went out of business, not because the original sub was unable to meet the quality requirements; (iii) the Government had not breached the implied duty of good faith and fair dealing because the Government did not know ahead of time that the supplier would go out of business and there was no showing that the Government had  forced the contractor to use another supplier; (iv) there was no showing of a defective specification regarding the sub that went out of business because the specifications contained no information promising that the sub would perform the contract. The Board denied the Government's motions for summary judgment in two other areas (topsoil claims and alleged weather delays) because genuine issues of material fact remained to be decided. 

In NES Pacific Limited Liability Co., an appeal decided by the parties' agreement to use the ASBCA's ADR procedures, the Board held that: (i) the Government's refusal to accept items whose production was delayed as a result of labor shortages caused by the COVID epidemic was improper because that constituted an excusable delay; and (ii) a bilateral modification contained insufficient information for the Board to conclude that it operated as a release, as the Government had alleged.  

In Paragon Defense Solutions, Inc., an appeal decided, without a hearing, pursuant to the ASBCA's Rule 12.2, Small Claims (Expedited) procedure, the Board held that the appellant had not accepted a  purchase order because it had not supplied conforming items, and, therefore, the purchase order had lapsed. The Board rejected the appellant's argument that the Government had taken too long under FAR § 46.407(g) to notify it that the delivered items were unacceptable and had thereby impliedly accepted them because: (i) the Government had offered to ship the items back, noting they were in "new, unused condition" and, therefore, had not taken ownership of them; and (ii) the Government could not, and did not, use the nonconforming items. 

In AECOM Technical Services, Inc., the ASBCA decided the contractor had no right to recover its considerable costs associated with its preparation of a proposal, including a feasibility study, in connection with a solicitation for a task order award under its IDIQ contract because the contract clearly and repeatedly stated such costs could not be recovered if the Government decided not to award the task order or proceed with the project  "for any reason." Specifically, the Board held that: (i) it lacked jurisdiction over any claims based on an implied-in-law contract; (ii) the contractor had not previously submitted its superior knowledge claim to the Contracting Officer for a decision; (iii) the implied duty of good faith and fair dealing cannot be used to establish a contractual right directly contradictory to the terms of a written contract; and (iv) the fact that the Contracting Officer had not given any reason for not proceeding with the project was irrelevant because the contract did not require him to provide a reason:

If the KO determines that the project is not feasible for any reason including but not limited to financial, technical, contractual, savings determination, installation mission, or organizational issues, then the Government will not be subject to any costs associated with the feasibility study unless the Government exercises its option to obtain ownership of the submitted documentation. 

 

Terminations/Liquidated Damages/Government Claims  

In Wise Developments, LLC, the CBCA overturned the agency's default termination of a building lease based on an alleged (sporadic) odor bothering the tenants that the lessor had undertaken extraordinary steps to identify but that could never be detected by third parties, much less traced to any source in the building, itself, beyond, possibly, space heaters used by the agency's employees in violation of their lease because the allegedly offensive odor did not satisfy the condition in the default clause cited by the agency to justify the default, i.e., that the lessor had failed to maintain, repair, operate or service the premises as and when specified in the lease or had failed to perform any other requirement of the lease as and when required (especially when the lease did not have any requirements concerning offensive odors). The Board also found that the situation did not constitute a common law constructive eviction because the intermittent alleged odors did not rise to the level of "living or operating conditions . . . so egregious as to constitute substantial interference with the tenant’s beneficial use and enjoyment of the leased premises."

In Eagle Peak Rock & Paving, Inc., on remand from the CAFC, which had reversed the CBCA's prior decision (overturning a default termination) on the basis that the Board had focused on the reasoning in the Contracting Officer's termination decision rather than considering the issues de novo, the CBCA again holds the termination for failure to make progress was improper because the schedules presented by the contractor complied with the contract's requirements and showed it could have completed the work on time considering that two construction seasons remained, and, in the circumstances, the contractor had made adequate progress during the first construction season. 

In Crystal Clear Maintenance, a Rule 19 proceeding solely on the written record, the CBCA denied the Government's half-baked claim for flood damage in a building after a storm (which allegedly resulted from the contractor's work on its building maintenance contract) because: (i)  the proceeding was not bifurcated into quantum and entitlement, and the  Government failed to present any evidence of quantum[!]; (ii) the Government did not establish that the contractor's actions caused the flooding event; (iii) the Government's allegation that the contractor was required to have personnel in the building during the weather event that resulted in the flooding conflicted with the clear language in the contract; and (iv) the Government's allegation that the contractor should have notified that Government that it had moved a sensor failed because the Government did not even prove the contractor actually had moved it.

In JITA Contracting, Inc., the CBCA denied cross-motions for summary judgment concerning the propriety of a default termination. The Board held that the contractor did not establish that the Government had waived its right to terminate by waiting approximately two months after the required completion date because the contractor had not presented any undisputed facts showing that  it "could . . . reasonably have believed that time was not of the essence or that its previous periods of delay had been excused." The Board denied two of the three grounds the Government contended supported its decision to terminate because they were not alleged in the Government's Complaint or any any time before reply briefing in the the Government's motion for summary judgment (this was an issue of lack of adequate notice to the contractor, and these items could still be litigated at a hearing on the merits). The Board denied the remaining portion of the Government's motion alleging that the default was justified by the contractor's failure to complete the project on time because the motion did not include any undisputed facts establishing that the contractor did not have any excusable delays. Finally, the Board granted the portion of the Government's motion alleging that "disincentive deductions" could be taken by the Government for the contractor's delays beyond the completion date because, although the contract language was not "ideally drafted," no other interpretation of the contract's language made sense. 

In Pinewood Inc. fka PNI Incorporation, a Rule 11 proceeding concerning a fixed price contract for repair of a contingency fuel delivery system at an air base in Korea, the ASBCA upheld a default termination for failure to make progress because the contractor had completed less than 4% of the work with more than half the time allotted for the job having passed, and the contractor failed to present evidence that any of its claimed excusable delays affected the critical path. The Board did note that the contractor was entitled to payment for demolition work it had performed prior to the termination. 

In U.S. Aeroteam, Inc., the ASBCA upheld the default termination for failure to make progress of a contract to furnish trailers used to transport aircraft engines because the contractor demanded payment for its disputed claims as a condition of continuing work, violating its duty to proceed pursuant to the "Disputes" clause. 

In Langdon Eng'g and Management, the ASBCA upheld the default termination of a firm, fixed-price contract to refurbish and deliver eight bow thruster nozzles used to propel a type of hovercraft because the contractor failed to deliver any of the contract items despite being granted two significant time extensions to do so and failed to prove its failure to deliver was excusable, relying instead on an unreasonable interpretation of clear specifications and failing to prove its allegations that the bow thruster nozzles (a) differed materially from the OEM drawings, (b) contained manufacturing defects, and (c) could not be refurbished. The contractor also failed to prove its contentions that: (i) the fixed-price contract was commercially impracticable to  perform (because an alleged cost overrun alone was not sufficient for such a finding); (ii) the Government had withheld superior knowledge (because the solicitation documents clearly stated the bow thruster nozzles had reached the end of their useful lives, and the contractor failed to prove that there was any knowledge that the Government possessed but failed to share with the contractor); and (iii) the Government breached the implied duty of good faith and fair dealing in managing the contract or terminating it. The Board also held that the contractor was not entitled to recover money for allegedly out-of-scope repairs because the Contracting Officer did not authorize any such repairs.

In GSC Constr., Inc., a Rule 11 proceeding concerning a contract to design and renovate an Army barracks, the ASBCA held that: (i) the contractor's floor leveling claim was part of a prior request for equitable adjustment that the contractor had released in a bilateral settlement agreement;  and (ii) the Government had established by a preponderance of the evidence that the "most probable cause" of one of two flooding events for which the contractor claimed compensation was the contractor's defective "cross threading"; but (iii) the Government had failed to establish that a second flooding event was due to defective  materials or workmanship in the contractor's Roto-Rrooter. 

In Pontchartrain Partners, LLC, which involved, as a preliminary matter, the interpretation of the scope of a release in a contract for repairs to the Corpus Christi Ship Channel, the ASBCA granted the Government partial summary judgment on the contractor's commercial impracticability claim. Both parties asked the Board to determine the issue of commercial impracticability based solely on the percentage of the contractor's cost overrun. The Board held that the Government's methodology for calculating that percentage (comparing the total alleged cost of contract performance to the total adjusted contract price) was the correct one, and the resulting percentage (37%) was not enough, standing alone, to establish commercial impracticability. 

In Gideon Contracting, LLC, which involved a task order to repair a dam, the ASBCA held that the order contemplated that suspensions of work would be required to allow the release of water when lake elevations exceeded a certain level, and, therefore, under the "Suspension of Work" clause, the contractor could recover only for the portions of the suspension periods where the Government inexplicably continued releasing water after the lake had reached the required level and, in another case, where the Government (again inexplicably) did not permit the contractor to return to work for five days after the required level had been reached. The Board also held that the Government waived its claim for liquidated damages for late completion of the work by waiting more than a year to assert that claim as a punitive response to the contractor's claim. 

In Al Muamroon Trading, which involved a contract to provide heavy material handling equipment to Saudi Arabia, the ASBCA held that: (i) it lacked jurisdiction over the contractor's claim alleging a bad faith T for C because that claim had not previously been submitted to the Contracting Officer for a decision; (ii) the contractor was not entitled to any T for C settlement costs associated with dump trucks that had been rejected as nonconforming and never corrected; and (iii) the contractor was not entitled to any recovery for costs allegedly associated with other equipment because the contractor had not delivered any of it, and the contractor's recordkeeping system was inadequate to establish it had  incurred reasonable charges leasing that undelivered equipment that it reasonably could not avoid (the pro se contractor did not even provide a copy of the purported lease to the Board). 

In All Phase Services, Inc., the CBCA granted the Government's partial motion for summary judgment because the Government established a prima facie case that the contractor was in default for failure to make progress. Specifically, after waiving the original completion date, the Contracting Officer had set a new completion date in a cure notice, and  the contractor's subsequent submission of a schedule based on that date did not establish duress or coercion on the contractor to agree to it. Moreover, the Contracting Officer had rejected an alternate schedule suggested in messages between the contractor and the COR (who lacked the authority to change the schedule), and an inadvertent reference to that alternate schedule in an attachment to one of the Contracting Officer's communications with the contractor did not constitute ratification.  

 

Costs, Defective Pricing, and Cost Accounting Standards (CAS)

In Parsons Government Services, Inc., the ASBCA  held that the proper interpretation of FAR § 31.205-36(b)(2) concerning the allowability of rental costs incurred by a contractor following the sale and leaseback of a depreciable asset (in this case a building) involves resort to FAR § 31.205-16(d) which caps the recognized gain at the difference between the acquisition cost of the asset and the undepreciated balance at the time of the sale and leaseback "to ensure that the recovery of costs [is] limited to those that would be allowable had the contractor retained title (i.e., the costs of ownership) and neither the government nor the contractor would be worse off because of a sale and leaseback than they would have been had title been retained." 

In D-STAR Eng'g, Corp., which involved a T for C of a CPFF R&D contract to build a fuel-to-power generation system for an unmanned vehicle, the ASBCA held that the DCMA: (i) had provided specific support for its finding that certain contractor-incurred costs after a partial stop work order were not reasonable, and the contractor had failed to rebut that evidence with anything more than generalizations; (ii) had correctly found that certain material costs included in the contractor's engineering overhead pool were unallowable because the contractor had been compensated for them as direct costs on a  prior contract; (iii) had established that the contractor had improperly included certain long-range planning costs in its G&A expenses to calculate its G&A rate for one calendar year because the costs were (a) unsupported or (b) included burden on top of G&A expenses; (iv) had properly documented its reasons for determining that some of the contractor's proposed termination settlement expenses were unreasonable, and the contractor had failed to provide evidence in opposition; and (v) had properly determined that the contractor's claim for various settlement expenses should be reduced by the amount already credited by the Government in its debt demand claim and by the costs of preparing the contractor's certified CDA claim. The Board also held that there was no evidence to support the contractor's claim of a verbal contract for clean-up work. Finally, the Board that the Government had improperly calculated the fee due to the contractor on the terminated contract by misinterpreting the phrase "the percentage of completion of work contemplated under the contract" in FAR § 52.249-6(h)(4)(i). Subsequently, the Board denied the contractor's motion for reconsideration.

In Caduceus Healthcare, Inc., an expedited small claims procedure on the record without a hearing, the CBCA held that the contractor could not recover for costs exceeding the ceiling price of a T&M contract because under FAR 52.232-7 it failed to notify the Contracting Officer that it was at risk of exceeding the ceiling price and failed to provide the Contracting Officer with a revised estimate of the total price to the Government for performing the contract. 

Quantum 

In AICI-Archirodon JV, the ASBCA held that the proper measure of the downward price adjustment for shipping by means other than the required U.S. flag vessel was the difference between (i) the quote the contractor had obtained for the only U.S. flag ship available and (ii) the price the contractor paid for an alternate shipping method. The Board rejected the contractor's assertion that the calculation should be based on the "reasonable" cost of a U.S. flag vessel. 

In HD, Inc., the ASBCA determined the appropriate method for calculating price adjustments for increased wages in covered labor positions in the option years of a contract subject to the Service Contract Act (SCA), which included the predecessor contractor's collective bargaining agreement (CBA). Specifically, the ASBCA held that the price adjustment for option year one was the difference between the rates in the revised CBA covering that option year and the the base year's CBA rates (based on the predecessor contractor's CBA), and for option year two, it was the difference between the CBA for option year two and the CBA for option year one. The Board specifically rejected the contractor's interpretation that the adjustment should be the difference between the appropriate CBA and the prices the contractor had originally proposed for the option years, which were based on the SCA wage rate determination for the locality, which also had been included in the solicitation (but only for the purpose of determining wage rates for positions not covered by the CBA) because the contractor's interpretation would lead to inconsistent and illogical results, would undermine the purpose of the SCA, and conflicted with (a) other provisions of the solicitation, (b) the Price Adjustment clause (FAR § 52.222-43(b)), and (c) the Government's responses to bidders' questions during the solicitation process.  

Discovery/Motions/Procedure

In Sauer Constr., Inc., the ASBCA denied the Government's motion for summary judgment that a release unambiguously barred the contractor's rust remediation claims because the language of the release could be interpreted to be limited to a specific change rather than to all claims, including the claim in dispute.

 In Government Training LLC, the ASBCA dismissed an appeal for failure to prosecute after the appellant essentially ghosted both the Board and the Government by failing to respond to numerous communications and orders from them. Similarly, In Patrick Considine, on its own motion, the CBCA dismissed an appeal for failure to prosecute after the appellant ghosted the Board by ignoring four of its orders after the Board had issued a scheduling order based on the agreement of the parties.

In The Minesen Co., the ASBCA dismissed an appeal with prejudice for failure to prosecute because the appellant failed to respond to several orders from the Board after its counsel was permitted to withdraw.  The ASBCA dismissed two more cases for failure to prosecute after the contractor in each one (a) failed to make a required filing and then (b) failed to respond to multiple Board orders requiring it to do so. Specifically, American Tattoo Society LLC failed to file its Complaint, and CKY, Inc. failed to file a required report on remand from the Federal Circuit concerning its EAJA award, which the Government had appealed.

In Delta T Jr, LLC, the CBCA denied the Government's motion for summary judgment upholding the default termination of an FFP contract to expand a cemetery because issues of fact remained as to the cause of the failure of a retaining wall and whether the contractor was obligated to follow the Contracting Officer's directions to remedy the situation or whether the "Warranty of Construction" clause limited the contractor’s obligations.

In Venergy Group, LLC, which involved the Government's motion to compel the production of certain documents, the CBCA held, inter alia, that: (i) the appellant's offer to make its accounting system available for inspection by the Government was sufficient to satisfy the Government's request for financial and project cost documents from that system, and the contractor was not required to conduct further a search within that system to find and produce specific documents; and (ii) the Government failed to explain how its broad request for audit reports for several years preceding the years at issue in the appeal would provide relevant data concerning the home office overhead costs at issue in the appeal. 

In  HECO Pacific Mfg., Inc., which involved a claim that Government-caused delays stretched performance into a time period when COVID restrictions were imposed on, and further delayed, the contractor's work, the ASBCA denied the Government's motion for summary judgment because: (i) a bilateral modification did not settle or release any claims for costs associated with the COVID requirements that were imposed after the modification and that were unrelated to its revisions to the work; (ii) the foreseeable impact of a government delay that started before COVID but lasted until after the effects of the emergency were known is not strictly limited to what might have been anticipated on the delay’s first day; and (iii) there was not enough evidence in the summary judgment motion to conclude the Government was shielded by the  sovereign acts doctrine in this instance:

The government fails to provide anything to establish that the requirements constituted genuinely public and general acts of the government or were imposed for a broader governmental objective. We have no indication that the requirements were imposed upon anyone other than HECO, or if they were only for HECO how and why they served a broader governmental objective instead of simply increasing its costs. Given that the requirements are not inconsistent with others generally imposed during COVID, it might be reasonable to infer they serve sovereign objectives. But, as the summary judgment movant, the government is not entitled to any inferences in its favor.

Equal Access to Justice Act

In Adapt Consulting, LLC, the CBCA held that: (i) the agency's actions in terminating a contract for default and in denying almost all of the appellant's monetary claims were not substantially justified; (ii) there were no defects in the attorney billing records provided by the appellant; and (iii) absent any specific objections presented by the Government, the Board on its own would determine that the appellant's success on the default termination and most of its claims merited an EAJA award of 75% of its attorneys' total billings.

The ASBCA denied an EAJA application by Michael M.. Tsontos, S.A. because the Government's litigation position had a reasonable basis in law and fact, so that it was substantially justified. 

Court of Federal Claims

Contract Disputes Act (CDA) / Tucker Act / Jurisdiction / Standing 

In The Kennedy Collective, a case that involved contract interpretation, the court dismissed the contract suit, holding that a blanket purchase agreement (BPA) awarded by NOAA to the plaintiff for PPE during COVID was not a binding contract or a requirements contract or an indefinite quantity contract because it was not based on mutuality of either consideration or obligation, so the Government was not liable on the plaintiff's claim for its inventory and disposal costs of PPE that the plaintiff acquired in anticipation of receiving orders that did not materialize, even though the BPA contained some irregularities when compared to a normal BPA, e.g., referring to itself as a contract in several places.

In BES Design/Build, LLC, which involved claims for delay damages, the court denied the Government's motion for summary judgment  concerning two constructive change claims because there were disputed issues of fact as to (a) whether the contract required the contractor to provide designs for the replacement of all plumbing and electric panels or only those that could not be reused and (b) causation, i.e., which party was responsible for the fact that the contractor's design submissions were late. The court dismissed (for lack of jurisdiction) the contractor's claim for the replacement of steam heating with a gas-powered boiler because the claim had not been previously submitted to the Contracting Officer for a decision: "The words 'steam' and 'heating' never appear in the claim. . . .  In fact, they do not even appear in [the plaintiff's] complaint."

In Textron Aviation Defense LLC, the court affirmed the prior CoFC decision granting summary judgment to the Government and dismissing the contractor's Complaint because the underlying claim was not submitted within the six-year limitations period. Specifically, the court held that: (i) the contractor failed to present evidence that it did not have enough information to know or have reason to know the claim's "sum certain" at the time the court concluded the limitations period began to run; (ii) the CoFC correctly concluded the contractor's request for payment under CAS 413 was not "routine" because the alleged amount owed had no connection to the expected or scheduled progression of contract performance, but rather arose from an unanticipated bankruptcy and associated segment closings; (iii) the contractor's predecessor-in-interest sustained damage (which started the limitations period running) when the terminations and curtailment of the pension plans triggered its ability to request CAS 413-50(c)(12) pension-cost adjustments, and not at the much later date when the Government denied its CAS 413 payment request.

In Taino Constr. Group, LLC, which involved claims under a contract to demolish buildings that was terminated for default, the court held that: (i) it lacked jurisdiction over a claim for breach of the implied duty of good faith and fair dealing because the original claim to the Contracting Officer did not provide any information beyond a request for payment, which does not suffice as the "clear and unequivocal statement" of the claim required by the CDA; and (ii) the contractor could not recover for work not accepted by the Government on the defaulted contract.

In Siemens Government Technologies, Inc., a suit for the recovery of the plaintiff's bid preparation costs in its unsuccessful bid for a task order award, which contained counts alleging both a CDA claim and claims under the court's bid protest jurisdiction, the court denied the Government's motion to dismiss the various counts. Specifically, the court held that: (i) FASA did not bar the plaintiff's claims because the plaintiff sought only to recoup the money it spent in its failed bid and did not challenge the issuance or proposed issuance of the task order; and (ii) the plaintiff adequately pled a count for breach of contract by alleging that the contract at issue gave the Contracting Officer the discretion to reimburse bid preparation costs and that he had abused that discretion in failing to do so in circumstances where the Contracting Officer had allegedly failed to perform several actions that  would have facilitated an award to plaintiff. 

In AAECON General Contracting, LLC, an unpublished decision, the court held it lacked jurisdiction over a complaint in intervention filed by the surety in a default termination case because there was no showing the surety had a claim for money damages against the Government, and there was no equitable subrogation because the surety did not establish that it had either entered into a takeover agreement with the Government or financed the completion of the defaulted contract. 

In BroadReach Healthcare Pty Ltd., the court held it lacked jurisdiction due to mootness over a claim concerning the Government's alleged wrongful use of a funding mechanism (in this case a cooperative agreement) because during the pendency of the suit, the Government had canceled the cooperative agreement and there was no possibility of it being reinstated, such that the "voluntary-cessation exception" to the mootness doctrine did not apply. In The Suddath Cos., et al., the court denied two of the consolidated plaintiffs' requests that a protest mooted by the termination of the protested contract "be resolved through an expanded published opinion," rather than "by a short-form docket entry." 

Changes/Breach/Contract Interpretation/Defective Specs/Authority

In THE CENTECH GROUP, Inc., the court held that: (i) the Government had breached a task order for the contractor's acquisition and installation of a communications infrastructure in a building on Vandenberg Air Force Base by failing to pay for materials necessary for that installation that had been ordered on the basis of Government's approval of the bill of materials, even though the Government subsequently  paused the project after which the contractor switched subcontractors and ordered different materials; (ii) the contractor's failure to invoice precisely correctly for the parts was not a "material" breach that would absolve the Government from having to pay for them; and (iii) the Government could not avoid payment by noting that the items had never been delivered because it was the Government that had prevented delivery by pausing the project.

In Sunrez Corp., interpreting, in detail, a Small Business Innovative Research contract with the Air Force to design, develop, and build next-generation air-cargo pallets, the court granted the Government's motion for summary judgment concerning the plaintiff's claim for breach of the implied duty of good faith and fair dealing because, read as a whole, the contract required the plaintiff to initiate a draft technical data package at the beginning of Phase II, develop that package during Phase II, and deliver it before beginning Phase III with enough detail to accurately depict the final product and to allow competitive re-procurement in Phase III, and the plaintiff could not identify any specific promise in the contract that the Government had breached in the various actions that the plaintiff alleged constituted the breach.

In TPMC-EnergySolutions Environmental Services 2008, LLC, which involved the interpretation of an ID/IQ contract with an 8(A) mentor-protégé JV for remediation services at nuclear waste site, the court held in a lengthy opinion, inter alia, that: (i) under the doctrine of contra proferentem, the plaintiff's interpretation of a task order as firm fixed price (rather than fixed unit price) was reasonable and would be adopted; (ii) disputed release language in one task order would not be interpreted as a waiver of the plaintiff's claim for a Type I Differing Site Condition under FAR 52.236-2 because that language differed from the waiver language in other task orders and modifications that did constitute a general release; (iii) a reasonable contractor reading the contract documents as a whole would interpret the statement  that the "top five feet of overburden associated with each burial pit is considered uncontaminated soil" as making an affirmative representation as to the site condition, which turned out to be inaccurate; (iv) the contract documents indicated to a reasonable contractor that certain contaminants would be found underground in packaging and containers, and finding them dispersed in, and not easily separated from, the soil was an unforeseeable differing site condition; (v) the agency breached the contract by failing to disclose its superior knowledge as to both these issues; (vi) the agency breached the implied duty of good faith and fair dealing by (a) improperly conditioning approval of an aspect of the contractor's work plan on its agreement to rates advocated by Government in a separate billing dispute, (b) insisting that the contractor accept language in a mod waiving its right to an equitable adjustment, when the basic contract clearly gave it such a right, and (c) threating the contractor with fines for breaching a supposed 90-day storage limit that the agency failed to disclose actually had been waived by the EPA; and (vii) the agency's actions rendered the task order mod void and unenforceable due to economic duress. 

In B.L. Harbert Int'l, LLC, which involved a contract to replace a taxiway at an Air Force base, the court granted the Government's motion for judgment on the pleadings based on general releases in two bilateral modifications. The first release stated the modification "constitutes compensation in full on behalf of the Contractor and its Subcontractors and Suppliers for all costs and markups directly or indirectly attributable for the change ordered, for all delays related thereto, for all extended overhead costs, and for performance of the change within the time frame stated." The second release covered all claims except any for a time extension that might occur in the future, and there was no such time extension.  

In SLSCO, Ltd., the court was faced with the plaintiff's challenges to CPARS involving a contract to build a section of Southern border wall, which was terminated for convenience, and held that: (i) the plaintiff lacked standing concerning its allegations as to procedural defects in the CPARS because, under the binding precedent of the CAFC's decision in Todd Construction (in which that plaintiff had alleged several of the same errors as the current plaintiff did), the plaintiff failed to show that it was "prejudiced by a significant error"; (ii) dismissed the plaintiff's breach of contract claim the because the CPARS regulation (FAR 42.15) was not incorporated in the contract and, therefore, the Government had no contractual duty to the plaintiff to provide a CPAR; and (iii) dismissed the plaintiff's substantive challenges to the "Marginal" performance ratings it received because it failed to allege facts that would establish those ratings were inconsistent with the definition of a Marginal rating in the regulations or facts that would establish such ratings were inaccurate or were arbitrary and capricious. Concerning these latter holdings, the court spent considerable time analyzing what its standard of review should be when reviewing de novo a Contracting Officer's decision under the CDA concerning the propriety of the underlying CPARS, which are reviewed under an abuse of discretion standard. 

In Platinum Services, Inc., which involved a contract to transport shipments of household goods for military service members, the court denied the plaintiff's claim that the Government had breached an alleged contract to pay plaintiff's rates for accessorial services (i.e., additional moving services beyond standard long-distance transportation) because there had been no meeting of the minds concerning the price for such services, but the court allowed the plaintiff to recover in quantum meruit for the accessorial services it had actually performed because the parties had intended to contract for those services. 

In GBA Associates Limited Partnership, which involved a dispute regarding the responsibility for paying tax assessments under a building lease, the court held  that the GSA/lessee (a) had properly reestablished the real estate tax base as the amount billed the first year that the tax bill took into account a full assessment of the property coincident with full occupancy and, therefore, (b) had not breached the lease.

In DaVinci Aircraft, Inc., the court, inter alia,  dismissed a count in the Complaint for breach of contract because negotiations between the plaintiff and the Government for the Government to purchase antennas that the plaintiff previously had acquired at a surplus property sale had never resulted in a contract, but had broken down after the plaintiff demanded an exorbitant price for the antennas, leading the Government to seize them. 

Terminations

In Intelligent Investments, Inc., which involved the Government's motion for partial summary judgment as to aspects of the contractor's T for C settlement proposal related to a contract for debris hauling and cleanup, the court held that: (i) the Government's argument that FAR 49.206-2 required the contractor to use inventory based accounting rather than a total cost basis must be denied because that provision was not incorporated into the contract and, in any event, does not mandate the use of that accounting method as a matter of law; (ii) the contractor was not entitled to settlement costs attributable to a  subcontractor that had already signed a release of its claims to those costs; (iii) a genuine issue of fact remained as to whether claimed consulting fees for a separate company that prepared the contractor's T for C claim were unallowable as being contingent on the contractor's recovery from the Government; (iv) the fees charged by the consulting company to collect past due amounts and to investigate possible fraud by an individual were not reasonably necessary to the preparation or presentation of the settlement claim pursuant to FAR 31.205-42(g)(1)(i); and finally (v) the Government's motion as to other disputed costs was granted because the plaintiff provided no response to the Government's motion other than the incorrect assertion that only the DCAA could determine the allowability of those costs. 

Discovery/Procedure

In BES Design/Build, LLC, which involved claims for delay damages, the court denied the Government's motion for summary judgment  concerning two constructive change claims because there were disputed issues of fact as to (a) whether the contract required the contractor to provide designs for the replacement of all plumbing and electric panels or only those that could not be reused and (b) causation, i.e., which party was responsible for the fact that the contractor's design submissions were late. The court dismissed (for lack of jurisdiction) the contractor's claim for the replacement of steam heating with a gas-powered boiler because the claim had not been previously submitted to the Contracting Officer for a decision: "The words 'steam' and 'heating' never appear in the claim. . . .  In fact, they do not even appear in [the plaintiff's] complaint."

In AETC II Privatized Housing, LLC et al., the court (noting it was addressing discovery issues that have not yet been consistently decided by the courts) held that, under CoFC Rule 36, requests for admission concerning the meaning of the contractual documents at issue do not involve pure questions of law (and, therefore are appropriate) so long as they connect the facts and circumstances of the case to those documents. The same holds true for requests for admission concerning the application of a federal statute to the facts of the case. Finally, the court held that the fact that a request for admission may relate to the "ultimate issue" of the case is not a valid ground for refusing to respond.

In Martin Bros. Constr., which involves CDA claims for breach of contract, the court denied the Government's motion for an extension of time to file its Answer (even with the plaintiff's consent)  because the court already had granted the Government four extensions totaling 242 days and had warned it would not grant another extension. The Government's failure to adequately staff the case due to the demands of separate tariff-related cases was not an adequate excuse, especially where Congress had allocated the appropriate personnel funds: "The government here has not established that the increase in [its counsel's] workload and the time-sensitive demands of other litigation are the result of anything more than the Department of Justice’s failure to respond to a predictable increase in case volume and a decision to reduce or not replace departing staff."

In Broadway Gold, LLC, the court denied the Government's motion to dismiss a count in the Complaint seeking a declaratory judgment because such a judgment would provide an early resolution of the issue whether the Government could exercise an option in a lease to purchase a property in light of the Government's alleged breach, and monetary damages would be insufficient to address the harm the plaintiff alleged. The court also denied the Government's motion to dismiss counts in the Complaint plausibly alleging a breach of contract because that alleged wrongdoing should be weighed in determining whether the Government's affirmative defenses of equitable conversion or merger bar the plaintiff’s claims. 

EAJA

I  

 

   

Court of Appeals for the Federal Circuit

Jurisdiction/Standing/Res Judicata 

In Tiffany Buford, the CAFCl held it lacked jurisdiction over an appeal from a CBCA decision on a civilian employee federal travel claim under 31 U.S.C. § 3702(a)(3) for reimbursement of relocation expenses. 

In Hawaiian Dredging Constr. Co., a decision labeled as nonprecedential, the CAFC held that the Court of Federal Claims should not have granted the Government's preliminary Rule 12(b)(6) motion to dismiss (for failure to state a claim) most of the contractor's claims alleging that various Government actions or inactions delayed and/or increased plaintiff's costs on a fixed-price construction contract because, accepting the allegations in the Complaint as true, as the lower court should have, there were open issues that could only be resolved by further proceedings, e.g., whether the time the Government took to obtain rights of way and approval of utility agreements was reasonable when the contract was silent on the issue.  

In Keyes Helium Co., LLC, a decision labeled as nonprecedential, the CAFC held, inter alia,  that the CoFC had  erred in granting the Government's motion to dismiss the plaintiff's breach of contract claim in a contract for the storage of helium because the plaintiff had plausibly alleged, but lower court's analysis had failed to consider, that there was a contractual obligation that the Government had breached.  

In Chizoma Onyems, the CAFC held it lacked jurisdiction over a  suit challenging  a prior ASBCA decision because it was filed in his own name by the non-attorney owner of the sole proprietorship involved in the ASBCA case, which meant that, pursuant to the CDA, he was not the "contractor" that was the litigant before the Board and also had not retained counsel to appear before the court as required by the court's rules. 

Changes/Interpretation/Breach 

In WSP USA Solutions, Inc., a decision labeled as nonprecedential, the CAFC remanded the case for further proceedings because the ASBCA had erred in concluding both that: (i) the contract at issue was an IDIQ rather than a requirements contract; and (ii) the contract unambiguously required that task orders should be priced at the time they were issued rather than at the time of performance.  

In Balfour Beatty Constr., LLC, a decision labeled as nonprecedential, the CAFC vacated and remanded (in part) the prior CBCA decision because a contract drawing indicating that the contractor should “match existing building foundations” (which were 18 inches thick) was sufficiently definite to constitute a design specification, creating an implied warranty, and the CBCA erred in construing it as a performance specification.

In FlightSafety International Inc., the CAFC affirmed the prior ASBCA decision, holding that, pursuant to 10 U.S.C. § 2320 and DFARS § 252.227-7013, the contractor's restrictive markings on commercial data necessary for operation, maintenance, installation, or training ("OMIT" data) and developed exclusively at private expense were improper because the markings would have restricted the Government's rights to use that particular type of data on future procurements.

In Sheffield Korte Joint Venture, a decision labeled as nonprecedential, the CAFC affirmed the  prior ASBCA decision, holding that a specification for a stormwater management system was a performance spec, so the Spearin implied warranty of a design specification was not applicable.

In Lessors of Abchakan Village, Logar Province, Afghanistan, which concerned an agency's alleged failure to pay property owners for use of property in Afghanistan, the CAFC vacated the prior ASBCA decision (granting the agency a summary judgment) because the lessor had raised material issues of fact concerning ownership of the property, and the Board had improperly ignored evidence supporting the lessor's position and had erroneously concluded that the act of state doctrine applied in this case.

In Amatea/Grimberg JV, a decision labeled as nonprecedential, the CAFC affirmed the prior ASBCA decision denying plaintiff's claims on a contract to design and build a laboratory because a contractor is not entitled to a presumption of excusable delay when a Contracting Officer issues a time extension and there was substantial evidence supporting the Board's determination that the contractor did not establish excusable delay when it failed to present any expert testimony  to rebut the Government's expert's critical path analysis. The court also found there were rational bases for Contracting Officer's exercise of the discretion allowed by contract to deny the contractor's requests to work outside of normal hours. 

In Williams Bldg. Co., a decision labeled as nonprecedential, the CAFC affirmed the prior CBCA decision, holding that: (i) a bilateral modification covered only the contractor's two breach of contract claims and did not concede liability for the contractor's separate cardinal change claim; and (ii) the Board did not err in granting the Government's motion for summary judgment on a claim involving cost elements first provided by the contractor in opposition to that motion and not previously identified by the contractor in response to an earlier Board decision granting the Government's request that the contractor provide a more definite statement of its alleged costs during the discovery schedule set by the Board. 

Terminations 

I

Costs/CAS

In

Fraud/Anti-Kickback

 

EAJA

 

 

      

Supreme Court


This website links to resources on the web concerning government contracting. It is not intended to provide legal advice. Moreover, I do not vouch for the completeness, currency, or accuracy of the sites to which it links. If you have comments, suggestions for new links, or corrections, please email me