Contents
Boards of Contract Appeals
(ASBCA, CBCA, PSBCA, and GAOCAB)
Jurisdiction/Standing/Timeliness/Contract
Disputes Act (CDA) Issues
In USProtect
Corporation, the contractor appealed to the CBCA from the
Contracting Officer's failure to issue a decision on a claim
within the statutory time limits. The Board docketed the appeal,
then suspended proceedings in part because the Government said
it needed additional time to issue a decision and also to permit
the parties to discuss settlement. Those discussions were
unavailing so the Government finally issued a decision on the
contractor's claim, and, at the same time, issued a decision on
a government counterclaim. The contractor did not appeal the
decision to the Board. The Government then attempted to amend
its pleadings at the Board to include the counterclaim. The
Board dismissed the counterclaim for lack of jurisdiction
because the contractor had not appealed it (and still had time
to appeal to the Court of Federal Claims). The contractor did
not have to appeal the Government's belated decision on the
contractor's claim--the docketing of the contractor's original
appeal was enough to sustain continued jurisdiction.
The ASBCA dismissed
Valenzuela
Engineering's appeal because, as a suspended corporation
under California law, it lacked the capacity to maintain the
appeal.
FloorPro
concerns situations in which third party beneficiaries have
standing and jurisdiction to pursue an appeal before the ASBCA.
In Mr.
Michael Ronchetti, the ASBCA found it lacked jurisdiction
over a subcontractor's claim that was not sponsored by the
prime.
The Board held it (i) had jurisdiction
over NSA
contract disputes; (ii) lacked jurisdiction over a claim
based on "humanitarian"
grounds; and (iii) lacked jurisdiction over Qatar
International Trading Co.'s complaint that the Government
had lost the contractor's bulldozer after having towed it from
an accident site (the actual facts are more complicated and more
interesting than this summary). The Board also held that the
Government had not extended only some services under the
"Option to Extend Services" clause, but, rather, had
extended the contract under the "Option to Extend the
Contract Term" clause, such that elimination of some
services was a partial termination for convenience or a
deductive change, entitling Wackhenhut
to compensation. The CBCA found it lacked jurisdiction over
a claim for
worker's
compensation.
In Guardian
Environmental Services, the contractor submitted a certified
claim covering monies allegedly owed under several disputed
invoices. The Government subsequently released some of the
disputed sums, but withheld the remainder. The contractor
appealed. The Government moved to dismiss because it was
preparing a claim for liquidated damages. The CBCA, however,
found it had jurisdiction over the appeal despite the
Government's unfulfilled intentions.
In Qatar
International Trading, the Board held that the Government's
defense in tort did not divest the Board of jurisdiction over
the contractor's claim (the contractor had claimed that the
Government failed to pay satellite phone service charges for
calls made from cell phones delivered to the Government by the
contractor; the Government claimed the calls had come from
cloned cell phones, i.e., had been made by tortfeasors).
In Omegaman
Fireprotection, the CBCA held it lacked jurisdiction over
what was essentially a bid protest because there was no contract
between the claimant and the Government.
Often it's the contractor that is bitten
by the release language in a termination settlement agreement.
In Government
Marketing Group, it was the Government's claims that were
precluded by such a release.
Submission of Claim
to Contracting Officer
In Bowers
Investment Company, the CBCA dismissed an appeal for lack of
jurisdiction because the contractor had failed to submit a claim
to the Contracting Officer, but instead had appealed after ADR
procedures had failed to completely resolve its disputes with
the agency.
In Tidewater
Contracting, the contractor originally submitted a claim for
an extension of the contract time/period of performance. After
its appeal of the denial of that claim had been docketed by the
Board, the Government assessed liquidated damages against
Tidewater. Tidewater argued its original appeal should cover
that assessment. The Board rejected Tidewater's contention
because Tidewater never submitted a claim to the Government for
return of the liquidated damages.
In KAMP
Systems, the contractor appealed from a government claim.
Subsequently, the contractor amended its complaint to assert
related counterclaims against the government. The Board struck
those portions of the complaint because the contractor's claims
had not been submitted to the Contracting Officer for a
decision.
Certification
In Teknocraft,
the Board dismissed a claim without prejudice after holding that
typing "//signed//" in a signature block was not a
defect in a certification that could be remedied at the Board.
Request for
Decision by Contracting Officer
Normally, a claim must include a request
for a decision from the Contracting Officer. In Fuel
Tank Maintenance Co., citing Transamerica Insurance Corp.
v. United States, 973 F.2d 1572 (Fed. Cir. 1992), the Board
held that the following situation satisfied this requirement:
[W]here [the contractor] submitted its
REA after completion of the work, presentation of a final
invoice, verbal notification of a claim, and a contracting
officer request, in light of the verbal notification of a claim,
to resolve all outstanding issues as expeditiously as possible,
and where [the contractor] included a CDA certification, the REA
requested a final decision. . . .
Appeal to Board
In Northrop
Grumman Ship Systems, the Board held that a contractor could
appeal from the Contracting Officer's failure to issue a
decision on a claim without asking the Board to direct him to do
so: "In this case, the contracting officer neither issued a
timely decision nor notified appellant when he would do so. The
CDA does not require the contractor to ask the Board to direct
the contracting officer to issue a decision before the
contractor can appeal from the deemed denial of its claim; it
merely permits the contractor to do so, at its option."
In SUFI
Network Services, the Contracting Officer returned the
contractor's claim without deciding it because the Contracting
Officer contended it was untimely filed. SUFI then appealed to
the Board, and the Board accepted the appeal because the
original claim was not untimely.
In Corners
and Edges, the ASBCA held it had jurisdiction over a notice
of appeal mailed before the date the CBCA became effective but
received by the ASBCA after that date.
In Devi
Plaza, the CBCA held that the Contracting Officer's
willingness to discuss settlement with the contractor after
issuing the Contracting officer's decision tolled the
90-day appeal period even though the Contracting Officer had
twice written the contractor to remind him that the original
decision had included a statement of his appeal rights.
Costs
and Cost Accounting Standards (CAS)
On reconsideration, the ASBCA reversed its
prior
decision in the Raytheon CAS 413 segment-closing case, which
had found the contractor liable to the Government for interest
for failing to make timely period adjustments to pension
costs. In the most recent Raytheon
decision, the Board held that its prior inferences from an
unclear record were unjustified. However, the Board also decided
that further development of the record is not necessary because
the "contract price or cost adjustment did not result
from a CAS violation or from a failure to follow a cost
accounting practice consistently, which is what the CAS statute
and CAS clause require in order for [the contractor] to be
liable for a contract price adjustment and interest. . .
."
In The
Boeing Co, Successor-in-Interest to Rockwell International Corp.,
the CBCA held that the contractor could recover its defense
costs associated with those counts on which it had prevailed in
a suit filed against it under the False Claims Act, even though
though the contractor was found liable on other counts in the
same suit.
Delays
The ASBCA's decision in the AEI
Pacific construction case includes good, black letter
discussions of accord and satisfaction; duty to cooperate;
defective specifications; and compensable delays. The contractor
prevailed on the theories of defective specifications and
constructive acceleration. Concerning the defective design
specifications, the Board noted as follows:
When government plans or specifications
specify, in design detail, the precise manner or method of
performance, the government impliedly warrants a satisfactory
performance result if they are followed. United States v.
Spearin, 248 U.S. 132, 136 (1918); Essex Electro
Engineers, Inc. v. Danzig, 224 F.3d 1283, 1289 (Fed. Cir.
2000); Weststar Revivor, Inc. (formerly Westar, Inc.),
ASBCA Nos. 52837, 53171, 06-1 BCA ¶ 33,288 at 165,030. Breach
of the warranty entitles the contractor to recover all of the
costs proximately flowing from the breach, including costs
attributable to any resulting period of delay. See La Crosse
Garment Manufacturing Co. v. United States, 193 Ct. Cl. 168,
432 F. 2d 1377, 1385 (Ct. Cl. 1970). Unlike some situations in
which the government has a reasonable time to make changes
before it becomes liable for delay, "all delay due to
defective or erroneous Government specifications are [sic] per
se unreasonable and hence compensable." Essex, 224
F.3d at 1289 quoting Chaney & James Construction Co. v.
United States, 190 Ct. Cl. 699, 421 F.2d 728, 732 (Ct. Cl.
1970).
The Board utilized the five-pronged test for that
theory espoused in Fraser Constr. Co. v. United States, 384
F.3d 1354, 1361 (Fed. App. 2004):
(1) that [the contractor] encountered
[excusable] delay . . . .; (2) that [it] made a timely and
sufficient request for an extension . . . ; (3) that the
government denied [its] request for an extension or failed to
act on it within a reasonable time; (4) that the government
insisted on completion of the contract within a period shorter
than the period to which [it] would be entitled by taking into
account the period of excusable delay, after which [it] notified
the government that it regarded the alleged order to accelerate
as a constructive change . . . ; and (5) that [it] was required
to expend extra resources to compensate for the lost time and
remain on schedule.
Tri-State
Consultants tried almost every theory of construction
contract recovery in the book, all to no avail.
The ASBCA's decision in the Fox
Construction case includes a discussion of the
"loss of production" theory of recovery:
Loss of production occurs when a
contractor is required by the government to change its method of
performance so as to proceed in a less productive manner. Luria
Brothers & Company v. United States, 369 F.2d
701, 712 (Ct. Cl. 1966). . . . To be entitled to loss of
productivity costs, a contractor must established a causal link
or relationship between the affected work and the increased
costs due to loss of productivity. DANAC, Inc., ASBCA No.
33394, 97-2 BCA ¶ 29,184 at 145,153 ("absent a greater
evidentiary link between the described phenomenon and this
project," the Board refused to accept the Corps of
Engineers' guide as sufficient proof of crew overloading); Triple
"A" South, ASBCA No. 46866, 94-3 BCA ¶ 27,194 at
135,537 (impact variables rejected because they showed no causal
relation to any particular changes).
Changes/Constructive Changes/Contract
Interpretation/Authority
The introduction to
the opinion in the Minneapolis
Community Development Agency and City of Minneapolis case is
an attention-grabber: " 'Most of the disputes in the
world arise from words.' Morgan v. Jones, (1773) 98 Eng.
Rep. 587, 596 (K.B.). As the appeal pending before us shows,
words are no less troublesome in the contract disputes of today
than they were when Lord Mansfield, Chief Justice was developing
common law to govern commercial transactions."
In Strand
Hunt Construction, the ASBCA used the following standards to
conclude that the contract was not ambiguous and that the
contractor's interpretation was unreasonable:
A contract is ambiguous only if it is
susceptible of two different and reasonable interpretations,
each of which is found to be consistent with the contract
language. Edward R. Marden Corp. v. United States, 803
F.2d 701, 705 (Fed. Cir. 1986). When the Board "steps into
the shoes of a reasonable and prudent business person, aware of
the situation" and a "plain reading of the contract as
a whole seems to yield only one reasonable interpretation,"
there is no ambiguity. Id. at 706.
It is also well-established that a
contract must be construed as a whole to give meaning to all of
its provisions. Julius Goldman's Egg City v. United States,
697 F.2d 1051 (Fed. Cir. 1983).
In Service
Rodriguez Barragan, the Board found the contract was
patently ambiguous, but the contractor still lost because it had
failed to inquire about the ambiguity prior to bidding.
In interpreting
an ambiguous contract, a forum may sometimes look the
"prior course" of dealing between the parties, but, as
the ASBCA noted in C.R.
Pittman Construction, a single transaction or occurrence is
not sufficient to constitute a course of dealing.
In General
Dynamics C4 Systems, the Board decided several issues
relating to option contracts, including whether alleged
government violations of FAR 17.202(c)(1) and 17.204(e) in
exercising options entitled the contractor to relief.
In Beyley
Construction Group, the ASBCA denied claims for changed
conditions based on a theory of quantum meruit because there was
no evidence of an implied-in-fact contract and because the
contractor's evidence for its cost estimates was
"incomprehensible."
After several
rounds of preliminary skirmishes (SUFI I, II, and III), the
ASBCA issued its decision on the merits in SUFI
Network Services, and the decision is a smorgasbord of claim
issues, theories, and defenses, including, inter alia,
breach of duty to cooperate and duty of good faith dealing,
misrepresentation, contract interpretation, contemporaneous
interpretation, course of dealing, ratification, burden of
proof, lost revenues, lost profits, claim preparation expenses,
and consulting fees.
In Alliance
General Contractors, the ASBCA rejected a defective
specification claim primarily because there was no basis to
interpret the drawings as the contractor wished, i.e., by giving
one of them precedence over the others. As a side note, the
Board found the contractor had not established a causal link
between the allegedly defective drawing and the alleged harm.
Duty
to Proceed
In
Second Street Holdings, the CBCA held that the contractor's
compliance with the directions in the Contracting Officer's
decision did not moot the claim issues on appeal.
Terminations
In Blackstone
Consulting, shortly after the contractor complained of
sexual harassment by the COR's husband, the Government began
taking more and more unilateral deductions for allegedly
inadequate performance by the contractor, until the contractor
wrote that it was being forced to exercise its right to cancel
the contract within 120 days. The next yearly option exercise
period came up before that 120 period expired, and the
Government did not exercise the option. The contractor
subsequently filed a claim for, among other things, anticipatory
profits for the unexercised option year and the succeeding
option year. The Civilian Board of Contract Appeals found the
claim for the future option year too speculative, but the claim
for the first unexercised year survived the Government's motion
for summary dismissal.
The ASBCA overturned
a default termination that had been based on a failure to make
progress because the Board found the contractor (Kostmayer
Construction) had responded satisfactorily to a cure letter.
Usually, it's the contractor that is
arguing the terms of a termination settlement agreement are
ambiguous. In Government
Marketing Group, however, the Government took this position
and argued that extrinsic evidence must be used to interpret the
document. The CBCA, however, held that (with one exception) the
agreement was clear on its face, and reliance on extrinsic
evidence was unnecessary.
The Postal Service Board of Contract
Appeals denied an appeal by a postal delivery contractor who had
been terminated
for default because he refused to comply with a unilateral
contract amendment requiring him to deliver mail by driving down
a gravel rural driveway that he considered unsafe. He lost his
appeal because, after having had the driveway inspected, the
Postal Service determined it to be narrow, but, nonetheless,
safe.
In Oregon
Woods, the CBCA held that a Contracting Officer did not
abuse his discretion in terminating for convenience a faulty
contract whose specifications would require an indeterminate
amount of time to review and correct.
Severin
Doctrine
Under the Severin doctrine, the Government is
not liable for a subcontractor's claim sponsored by the prime if
the prime has no liability to the subcontractor. The doctrine is
construed narrowly. In BearingPoint,
the Government was unsuccessful in invoking it as a defense:
The government tells us that, inasmuch
as there was no executed subcontract between BearingPoint and
Custer Battles, and no formal limitation of payments to what
would be allowable under FAR if a formal subcontract were in
place, "BearingPoint had not obligated itself to pay for
any USAID disallowed costs." The government also asserts
that following a dispute between BearingPoint and Custer Battles
regarding outstanding invoices, BearingPoint "denied any
liability for Custer Battles costs that were deemed
unallowable" by the contracting officer. (The Government�s
Motion to Dismiss With Prejudice for Lack of Jurisdiction Due to
A Want of Standing Or, In the Alternative, Summary Judgment (gov't
mot.) at 66-67)
We articulated the test governing
successful invocation of the Severin doctrine in M.A. Mortenson
Co., ASBCA No. 53761, 06-1 BCA ¶ 33,180 at 164,439. We
recognized there that the government "bears the burden to
prove that the doctrine applies. It must establish that an
iron-clad release or contract provision immunizes the prime
contractor completely from any and all liability to the
subcontractor for the government action at issue. The Severin
doctrine is construed narrowly."
Purchase Orders
In Comptech,
the ASBCA went through a lengthy and detailed analysis of the
legal status of unilateral purchase orders before concluding
that the Government properly canceled such an order because the
contractor failed to deliver conforming supplies within the
required time.
Quantum
In Southern
Oregon Ecological (SOE) , the CBCA cut SOE some slack in
specifying its damages because of its small business status:
"SOE is appearing pro se . . . and is a small business
concern, which appears to be essentially a one-man operation
that hires subcontractors to perform the work. SOE is not
expected to have the accounting system that a large company
would have."
L-3
Communications Corp. won bid preparation expenses (but not
lost profits) at the ASBCA as a result of the Government's
breach of the "fair opportunity to be considered"
provision covering the solicitation for a delivery order under
an ID/IQ contract.
The ASBCA found a government breach but declined to
award breach damages in Total
Procurement Service, Inc., because the contractor failed to
prove quantum, which is putting it mildly. The Board put it this
way: "However, appellant here has failed to prove the
amount, reasonableness and allocability of any costs that were
incurred. Because of the almost complete absence of
documentation or other corroboration of these costs and indeed
the destruction of pertinent records, as well as conflicts in
the amounts claimed, we also do not consider that a 'jury
verdict' is appropriate. The failure to maintain, preserve and
promptly produce to the government fundamental accounting data
and records goes to the credibility of the entire claim.
Appellant's actions with respect to those records were
irresponsible and militate against any award."
The ASBCA rejected the Government's attempt to charge
the Southwest
Marine for "overpaid REA interest" in the quantum
portion of an appeal because that was a new claim introduced too
late in the proceedings.
Procedure
In the Hedlund
Construction case, the CBCA denied the parties' JOINT motion
to vacate the Board's prior decision.
In Public
Warehousing Company (PWS), the ASBCA stayed the proceedings
for a limited period of time to allow the Government to wrap up
pending fraud investigations against the contractor in part
because "[i]t is clear to us . . . that PWC's
primary purpose in wishing to proceed with the appeal is to use
the Board's decision to influence the direction of the
on-going investigations, and to help its position in potential
settlement discussions."
In Palm
Springs General Trading and Contracting Establishment,
however, the ASBCA denied a motion to stay an appeal pending
criminal proceedings because, inter alia, the Government
failed to show that there were substantial similarities of
facts, issues, and witnesses between the ongoing criminal
investigation and the board appeals.
Discovery
The CBCA's decision concerning the discovery disputes
in LFH,
LLC
includes a bunch of good, black letter analysis of
attorney-client privilege issues, including the analysis of
situations in which one agency discloses allegedly protected
documents to another agency and the "common interest"
doctrine.
Equal Access to Justice Act
In Freedom
NY, the Board provided guidance to the parties concerning
(i) the concept of substantial justification and (ii) the
calculation and apportionment of Equal Access to Justice Costs
on various claims for Contract Disputes Act interest and Prompt
Payment Act interest when the contractor had originally
prevailed on only some of its claims and had rejected
substantial settlement offers from the Government.
Court of Federal Claims
Contract
Disputes Act (CDA) / Tucker Act / Jurisdiction / Standing
In Lublin
Corp., the Court of Federal Claims held that 31 U.S.C.
1501(a) is not a statute of frauds that precludes the existence
of an oral contract involving the federal government.
In Harper/Nielsen
Dillingham Builders, the court held that, under the Severin
doctrine, a prime could not sponsor a subcontractor's delay
claim, as applicable California law interpreted the
"no damages for delay" clause in the subcontract, the
prime had no liability to the sub.
The CDA covers contracts
with the United States. In Thomas
D. Affourtit, the court held it lacked jurisdiction over a pro
se suit by the President and sole shareholder of a company
because it was the company that was in privity of contract with
the Government, and it could only be represented by an
attorney.
In Metrotop
Plaza Associates, the court held that the time limit for
appealing from a Contracting Officer's decision was tolled by
his willingness to reconsider his decision and that
"[r]econsideration . . . was implicit in [his] offer to
discuss settlement."
What is a Claim?
Thirty years into the practice of the CDA, and we
still argue about whether individual submissions are
"claims" within the meaning of the statute. See,
e.g., NCLN2,
Inc. In Todd
Construction Co. the court held that an allegation that a
contractor's performance evaluation was issued without
observing the proper procedures and was substantively erroneous
constitutes a CDA claim. Similarly, in BLR
Group of America, the court held that it had jurisdiction
over a complaint filed by a contractor based on the Contracting
Officer's failure to decide the contractor's nonmonetary claim
that a Contractor Performance Assessment Report (CPAR) was
inaccurate and should be corrected. The decision is interesting
and important on several levels. First, it declines to follow a
line of ASBCA decisions that indicate quarrels over CPARs are
not CDA claims. Secondly, it finds the requirements for a claim
met when the contractor simply requested the Government to
change the CPAR, without labeling the request a claim. Third, it
reasons that a claim may be based on an assertion of any legal
right, not necessarily a right that is explicitly expressed in
the contract at issue. Finally, the court notes that recognizing
such challenges to CPARs as claims (rather than requiring the
contractor to wait and file a protest when the challenged CPAR
actually has adverse consequences on a subsequent procurement)
serves the interests of contract administration because a bid
protest significantly interferes with, even disrupts, the
procurement process, whereas a contract dispute under the CDA
does not.
Authority
In the Stout
Road Associates case, a DLA intern made hotel reservations
for herself and other interns at the site of DLA training
classes. The classes were canceled; the intern canceled the
reservations; and the hotel attempted to collect cancellation
fees from the agency pursuant to the agreement the intern had
signed. The Court of Federal Claims found the Government was not
liable because the intern did not have the authority to enter
into a government contract. The plaintiff also argued
ratification, but the court found that the intern's superiors
were not contracting officers either.
Contract Interpretation
After an interesting analysis of the scope and meaning
of the Antideficiency Act and an indemnification clause in a
World War II contract for the supply of aviation fuel to the
Government, the Court of Federal Claims found the Government
responsible for cleanup
costs for which the contractors (Shell Oil, Union Oil,
Atlantic Richfield, and Texaco) were found liable under CERCLA
long after the war and long after the contracts had expired.
In the Manhattan
Construction Company case, the Court of Federal Claims used
basic rules of grammar to determine the meaning of the
phrase "as indicated in the drawings." Specifically,
the court wrote: "Rules of grammar state that the
subordinate clause 'as indicated on the drawings' modifies the
noun or independent clause immediately preceding it. See Frederick
C. Crews, The Random House Handbook 242 (5th ed. 1987).
Also, the absence of a comma before the clause denotes that it
applies only to the final noun or clause. See Resolution
Trust Corp. v. Nernberg, 3 F.3d 62, 65 (3d Cir. 1993).
Plaintiff's interpretation might have had support if a comma set
off the subordinating clause; but the disputed clause, 'as
indicated on the drawings,' does not have an offsetting comma. See
Id. (noting that a comma preceding a subordinate clause 'may
indicate that the qualifying language [applies] to all of the
previous phrases and not merely the immediately preceding
phrase[].'); Demko v. United States, 44 Fed. Cl. 83,
87-88 (Fed. Cl. 1999) (using normal rules of punctuation to
interpret a statute). Thus, the lack of a comma setting off the
modifying phrase, 'as indicated in the drawings,' confirms that
it does not apply to all of the preceding phrases."
Changes/Defective
Specifications/Breach
In Stevens
Van Lines, the Court of Federal Claims found a contract on
the basis of the "implied actual authority" of the
Government's agents.
In Enron
Federal Solutions ("EFSI"), the contractor had a
privatization contract to buy the Government's dilapidated
utility services plant, make certain capital improvements to it,
and then provide utility services to the Government for a
10-year period, with the monthly price designed to cover the
cost of the services and gradually to pay for the original
capital improvements. After EFSI completed the capital
improvements and the first two years of service, it defaulted on
its obligations and was terminated for default. The court denied
EFSI's attempt to recoup the remaining costs of the capital
improvements. The court based its decision in large part on an
extensive analysis of the common law definition of a material
breach and the common law consequences of such a
breach.
In Metric
Construction Co., the contractor prevailed in its claim for
the costs of repairing leaks in a roof it had installed. The
court found (i) the Government's design specifications for the
roof support structure were defective (even though the specs for
the roof, itself, were performance specifications) and (ii) the
Government gave an ambiguous, misleading reply to the
contractor's request for guidance how to proceed once the
contractor noticed problems with the roof installation during
performance. In addition, the court used an approximation method
for calculating the contractor's damages: "No better
method (other than the rough calculations presented in this
opinion) for computing damages exists, given the perplexing
nature of the origin of roof leaks, which would provide a more
precise dollar amount for the [Government's] liability in this
case."
Under the constructive change doctrine, the government is liable
for additional work caused by a constructive change to the
contract. See Aydin Corp. v. Widnall, 61 F.3d 1571, 1577
(Fed. Cir. 1995) ("Where it requires a constructive change in
a contract, the Government must fairly compensate the contractor
for the costs of the change." (citing J.B. Williams Co. v.
United States, 450 F.2d 1379, 1394 (Ct. Cl. 1971))). Several
categories of constructive change have been identified: "(I)
disputes over contract interpretation during performance; (II)
Government interference or failure to cooperate; (III) defective
specifications; (IV) misrepresentation and nondisclosure of
superior knowledge; and (V) acceleration." Miller Elevator
Co. v. United States, 30 Fed. Cl. 662, 678 (1994) (citations
omitted).
A contractor may rely on specifications
provided by the government when constructing a building
according to those specifications. See Robins Maint., Inc. v.
United States, 265 F.3d 1254, 1257 (Fed. Cir. 2001) ("Whenever
the government uses specifications in a contract, there is an
accompanying implied warranty that these specifications are free
from errors.") (citing United States v. Spearin, 248
U.S. 132, 137 (1918)); Essex Electro Eng�'rs, Inc. v. Danzig,
224 F.3d 1283, 1289 (Fed. Cir. 2000) ("When the government
provides a contractor with defective specifications, the
government is deemed to have breached the implied warranty that
satisfactory contract performance will result from adherence to
the specifications, and the contractor is entitled to recover
all of the costs proximately flowing from the breach.")
(citations omitted). "The test for recovery based on
inaccurate specifications is whether the contractor was misled
by these errors in the specifications." Robins Maintenance,
265 F.3d at 1257. However, the government's implied warranty
of its specifications is generally voided if the contractor does
not follow those specifications. Mega Constr. Co. v. United
States, 29 Fed. Cl. 396, 418 (1993) (citing Al Johnson
Constr. Co. v. United States, 854 F.2d 467, 469-70 (Fed.
Cir. 1988)). "It is well-established that contractors may be
entitled to an equitable adjustment for increased costs of
performance due to defective specifications." Clearwater
Constructors, Inc. v. United States, 71 Fed. Cl. 25, 32
(2006) (citing L.W. Foster Sportswear Co. v. United States,
405 F.2d 1285 (Ct. Cl. 1969)); see also AAB Joint Venture v.
United States, 75 Fed. Cl. 414, 429-30 (2007) (holding that
when the specifications in a contract were largely inappropriate
for the construction anticipated under the contract, the
plaintiff could recover under a theory of defective
specifications); Sterling Millwrights, Inc. v. United States,
26 Cl. Ct. 49, 88 (1992) (holding that because certain
specifications, which consisted of "predominantly, if not
completely, design specifications," were defective, the
plaintiff was "entitled to be paid for the extra expenses and
time it incurred in trying to complete the project�". Even if
a specification is defective, however, contractors must be
reasonable in their conduct during construction. See Space
Corp. v. United States, 470 F.2d 536, 538 (Ct. Cl. 1972)
(stating that "when a contractor is faced with an obvious
omission, inconsistency or discrepancy of significance, he is
obligated to bring the situation to the government's attention
if he intends subsequently to resolve the issue in his own favor�"
(citations omitted). Contractors have a duty to inquire as to
inconsistent specifications which include patent, that is,
obvious or glaring, defects. See E.L. Hamm & Assocs.,
Inc. v. England, 379 F.3d 1334, 1339 (Fed. Cir. 2004) ("To
demonstrate that it was misled, the contractor-claimant must
show both that it relied on the defect and that the defect was
not an obvious omission, inconsistency or discrepancy of
significance" in other words, a patent defect "that would
have made such reliance unreasonable."); NVT Techs., Inc.
v. United States, 370 F.3d 1153, 1162 (Fed. Cir. 2004) ("If
the ambiguity is patent, it triggers a duty to inquire. A patent
ambiguity is one that is "obvious, gross, [or] glaring, so
that plaintiff contractor had a duty to inquire about it at the
start."" (quoting H & M Moving, Inc. v. United States,
499 F.2d 660, 671 (Ct. Cl. 1974))). If the erroneous nature of a
defective specification is not glaring or obvious, however, the
contractor may recover if it has been misled by the
specification. See AAB Joint Venture, 75 Fed. Cl. at
430-31.
[M]isrepresentation is another category
of constructive change. This particular type of constructive
change occurs when the government has misrepresented information
regarding a construction specification, and the contractor has
relied upon the misrepresentation to his or her detriment. See
Miller Elevator, 30 Fed. Cl. at 678 (citations omitted); see
also Meyers Cos. v. United States, 41 Fed. Cl. 303, 311
(1998) ("Misrepresentation occurs when the government
misleads a contractor by a negligently untrue representation of
fact, or fails to disclose information it has a duty to
disclose." (quoting John Massman Contracting Co. v.
United States, 23 Cl. Ct. 24, 31 (1991))). "Absent some
valid basis for a contrary conclusion (e.g., an absence
of detrimental reliance by a government contractor, a failure to
investigate 'sources which would have revealed the truth,'
or the like), the government "is liable for damage
attributable to misstatements of fact (in a contract or
specifications) which are representations made to the
contractor."" Summit Timber Co. v. United States, 677
F.2d 852, 857 (Ct. Cl. 1982) (quoting Flippin Materials Co.
v. United States, 312 F.2d 408, 413 (Ct. Cl. 1963)) (other
citations omitted). "In order for a contractor to prevail on a
claim of misrepresentation, the contractor must show that the
Government made an erroneous representation of a material fact
that the contractor honestly and reasonably relied on to the
contractor's detriment." T. Brown Constructors, Inc. v.
Pena, 132 F.3d 724, 729 (Fed. Cir. 1997); see Helene
Curtis Indus., Inc. v. United States, 312 F.2d 774, 778 (Ct.
Cl. 1963) ("Specifications so susceptible of a misleading
reading (or implication) subject the defendant to answer to a
contractor who has actually been misled to his injury."
(citations omitted). It is of no consequence that such
misrepresentations may have been innocent and inadvertent, as
long as they are material and the contractor suffers increased
costs of performance as a result. Summit Timber, 677 F.2d
at 857 (citing Everett Plywood & Door Corp. v. United
States, 419 F.2d 425, 431 (Ct. Cl. 1969) and Morrison-Knudsen
Co. v. United States, 345 F.2d 535, 539 (Ct. Cl. 1965)). In
addition, if the government misrepresents information regarding
its specifications in its communications to the contractor
during performance, the government may be liable if the
contractor relies on such misinformation. See Max Drill, Inc.
v. United States, 427 F.2d 1233, 1243 (Ct. Cl. 1970) ("When
an official of the contracting agency is not the contracting
officer, but has been sent by the contracting officer for the
express purpose of giving guidance in connection with the
contract, the contractor is justified in relying on his
representations [and may be entitled to an equitable adjustment
for such misrepresentations of fact material to contract
performance]." (citing Fox Valley Eng'r, Inc. v. United
States, 151 Ct. Cl. 228, 240 (1960)).
In the Information
Systems & Networks Corp. decision, the Court of Federal
Claims wrote: "[T]here is at least one other significant
factual kink in plaintiff's assertion that defendant hatched a
scheme to terminate it for default and seize its equipment -
namely, it was not terminated for default, but rather for
convenience."
Bell
BCI won its claim against the NIH at the Court of Federal
Claims for the cumulative impact of 200 changes, but the part of
the decision I enjoyed the most was this little gem regarding
the Government's counterclaim for liquidated damages: "NIH
did not believe that it had a factual basis to assert a
liquidated damages claim against Bell. NIH asserted this claim
only upon the advice of counsel to create negotiating leverage
in the event Bell filed a claim. . . ." The
Government's witness admitted this at trial. A Perry Mason
moment.
Carr
Forest Products complained that the Government failed to
make a reasonable estimate of the number and types of trees
available in various lots in a fixed-price timber sales
contract. The judge wrote that at one point the Government's
estimators did not determine the size of the trees with
measuring tape but instead performed "an ocular
measure." Or, as we say in Texas, they eyeballed it.
Government Breach
In Spectrum
Sciences and Software, the Court of Federal Claims delivered
a stinging rebuke to the Government and held that the Air Force
repeatedly had improperly used proprietary information
concerning a company's munitions conveyor equipment (which the
company had provided under the supposed restrictions of a
Cooperative Research and Development Agreement) to issue a
solicitation for such equipment, reveal proprietary details of
the equipment to third parties, and award a contract to
one of the contractor's competitors for equipment based on the
improper disclosure of that proprietary information.
Quantum
In Enron
Federal Solutions, the court delineated the very limited
circumstances in which it would allow quantum meruit recovery.
Equal Access to
Justice Act (EAJA)
In Bill
Hubbard, the court (as directed by the Federal Circuit)
recalculated (and reduced) an EAJA award based on the standards
in Hensley v. Eckerhart, 461 U.S. 424 (1983).
In International Air Response, the court scolded the
Government for resisting its obligations under the EAJA.
The EAJA permits the court
to adjust the statutory cap of $125 per hour for attorney's fees
to take inflation into account (the COLA adjustment). In Ace
Constructors, the court used a month-by-month analysis of
the incurred fees rather than a single midpoint average to
determine the COLA.
In Metric
Construction Co., the Court of Federal Claims found the
Government's position in litigation was substantially justified
and precluded an award of fees under the Equal Access to Justice
Act even though (i) the contractor prevailed on the majority of
its claim and (ii) the Government made almost no attempt to
rebut the plaintiff's application for attorneys' fees because:
"It was reasonable for the Government to have litigated
this dispute to its conclusion."
Procedure
In Ch2H
Hill Hanford Group, the court decided that, because of
overlapping issues, the case should be consolidated with one
before the CBCA, but, because the court did not have the
authority to demand of the CBCA that consolidation take place in
the court, the court transferred the case to the CBCA.
In Nova
Express, the court held that the owner of a sole
proprietorship may bring an action in the court without benefit
of an attorney.
In Highqbpo,
LLC, the court stayed proceedings in a contract
disputed pending criminal proceedings against the
contractor.
Discovery
In West
Bay Builders, the Court of Federal Claims refused to permit
the contractor to withdraw admissions it was deemed to have made
by failing to provide a timely response to defendant's request
for admissions. The plaintiff's cause was not aided by the fact
that (more than seven months before plaintiff finally filed its
motion requesting that its deemed admissions be withdrawn) the
plaintiff had signed a joint status report to the court noting
that the discovery responses were already overdue.
The Court of Federal Claims berated the Government for
attempting to withhold far too many documents under claimed work
product, deliberative process, and attorney-client privileges in
Chevron
U.S.A., Inc. v. United States.
In Northrop
Grumman, Military Aircraft Division, the CoFC held that
certain Claim Research Papers drafted to assist the Contracting
Officer in making a decision and prepared primarily by
contractual and technical staff were not privileged and were
properly disclosed voluntarily by the Government, even though a
government attorney had some part in their preparation and they
had been stamped with a legend that they had been prepared in
anticipation of litigation. Thus, the Government's disclosure of
the documents was not a waiver of any claim of privilege with
regard to other documents concerning the same issues.
In Multiservice
Joint Venture, during a break in a deposition, a version of
an exhibit containing handwritten notes mysteriously disappeared
and was replaced with a "clean" version of the
exhibit. After the plaintiff's deponent, representatives, and
attorneys all failed or refused to explain the situation to
defendant's counsel and (later) the judge, the Court of Federal
Claims barred the deponent from testifying at trial and ordered
the plaintiff's attorneys personally to pay the
defendant's costs of filing the motion for sanctions.
Court of Appeals for the
Federal Circuit
Jurisdiction/Standing/Res Judicata
Rick's
Mushroom Service couldn't establish a basis for jurisdiction
at the
Court of Federal Claims, and now the Federal Circuit affirms
the lower court's decision because the company's claims either
sound in tort or are based on an agreement that does not involve
a procurement of goods or services, neither of which is a proper
basis for Tucker Act or CDA jurisdiction.
In Phillips/May
Corporation, in a case of first impression, the court held
that the CDA did not alter the normal rules governing res
judicata and claim preclusion so that the outcome of nine
claims filed by the contractor at the ASBCA necessitated a
summary judgment in favor of the Government on a tenth claim
arising under the same contract and involving the same
transactional facts appealed by the contractor to the Court of
Federal Claims.
Contract
Interpretation/Changes/Authority/Breach
In denying General
Injectables & Vaccines' petition for rehearing, the
Federal Circuit held that the failure of FAR 52.212-4(f) to
state specifically that a contractor is liable for unexcused
subcontractor delays does not change the fact that the
contractor is liable for such delays.
In International
Technology Corp., the court listed four elements necessary
for a differing site conditions claims to prevail:
In order to prevail on such a site
conditions claim, a contractor must establish four elements.
First, the contractor must prove that a reasonable contractor
reading the contract documents as a whole would interpret them
as making a representation as to the site conditions. See
Renda Marine, 509 F.3d at 1376 ("[A] contractor must
first prove, as a threshold matter, that the contract contained
some identification of the conditions to be encountered at the
site."); H.B. Mac, Inc. v. United States, 153 F.3d
1338, 1345 (Fed. Cir. 1998) (explaining that the court "place[s]
itself into the shoes of a reasonable and prudent contractor and
decide[s] how such a contractor would act in interpreting the
contract documents"). This is a question of contract
interpretation reviewed de novo on appeal. H.B. Mac, 153
F.3d at 1345.
Second, the contractor must prove that the actual
site conditions were not reasonably foreseeable to the
contractor, with the information available to the particular
contractor outside the contract documents, i.e., that the
contractor "reasonably relied" on the representations.
Renda Marine, 509 F.3d at 1376 ("[T]he contractor
must demonstrate that the conditions encountered were not
reasonably foreseeable in light of all information available to
the contractor when bidding[ and] that the contractor reasonably
relied upon its original interpretation of the contract.").
This issue is factual in nature, and review is deferential. See
id. at 1378.
Third, the contractor must prove that
the particular contractor in fact relied on the contract
representation. See id. at 1376. Again, this is a fact
issue reviewed under a deferential standard. See id. at
1378.
Fourth, the contractor must prove that the
conditions differed materially from those represented and that
the contractor suffered damages as a result, which is again a
fact question. See id. at 1376.
Most interesting, though, was the following footnoted
dicta concerning a fifth element of government culpability that
was sometimes listed in certain cases:
The Board held that a showing of
government culpability was also required, relying on a series of
decisions by the Court of Claims. See Foster Constr. C.A.,
435 F.2d at 881 ("Some degree of Government culpability -- either
untruth or such error as is the legal equivalent -- must . . . be
shown, and the plaintiff's burden of proof is not satisfied
merely by proof of a variation between the subsurface conditions
as stated in the contract and as encountered."); C.W.
Blakeslee & Sons, Inc. v. United States, 89 Ct. Cl. 226
(1939); Midland Land & Improvement Co. v. United States,
58 Ct. Cl. 671 (1923). The government has declined to defend
this holding, and we are skeptical that such a showing is
required. More recently, when this court listed the elements of
a claim for misrepresentation in a government contract in T.
Brown Constructors, Inc. v. Pena, 132 F.3d 724, 729 (Fed.
Cir. 1997), we did not list any element of government
culpability. Under the general law of contracts, essentially the
same elements as those listed in the text above are required to
establish a misrepresentation claim, and no showing of
culpability is required if the representation was material. See
Restatement (Second) Contracts, ch. 7, topic 1, introductory
note. As discussed below, a similar approach, which also
requires no showing of government culpability, applies in the
context of government contract claims under the Differing Site
Conditions clause. See Renda Marine, 509 F.3d at 1377. In
light of our disposition of this case, however, we need not
reach the issue of whether government culpability must be
established.
In Northrop
Grumman Information Technology, the court found that a
document alleged to bind the government to a particular
obligation was not expressly incorporated into the subsequent,
official contract document and was, therefore, excluded by the
contract integration clause.
Anti-Assignment Act
In Delmarva
Power & Light, the court recognized the Government's
power to waive the prohibition against the assignment of claims
against the Government in the Anti-Assignment Act, 31 U.S.C.
3727(a).
Terminations
and Delays
The court upheld the ASBCA's decision
sustaining a termination for default in the General
Injectables & Vaccines case. The contractor could not
supply flu vaccine produced by its subcontractor because the FDA
found it was contaminated. The contractor argued the FDA's
action was governmental action constituting an excuse for
nonperformance. The court held that the underlying cause was the
subcontractor's default, which was attributable to the prime,
even under the controlling, commercial items, "Excusable
Delays" provision (FAR 52.212-4(f)), which does not include
the traditional language that the default must be without the
fault of the contractor "or its subcontractors. . .
"). In other words, even in contracts for commercial items,
the contractor is responsible for delays and defaults
attributable to its subcontractors.
Affirmative Actions Goals
and Preferences
In Rothe
Development Corp., the Federal Circuit held that 10 U.S.C.
2323 is unconstitutional because, in passing it, Congress did
not have a "strong basis in evidence" to conclude that
DOD was a passive participant in racial discrimination in
relevant markets across the country and that race-conscious
remedial measures were necessary. The Act (i) sets a
"goal" that five percent of federal defense
contracting dollars for each fiscal year be awarded to certain
entities including small business concerns owned and controlled
by "socially and economically disadvantaged
individuals"; (ii) incorporates the Small Business Act's
presumption that Black Americans, Asian Americans, Hispanic
Americans, and Native Americans are socially disadvantaged
individuals; and (iii) provides that the Department of Defense
shall give specified forms of assistance to the listed entities
and may, when practicable and necessary to achieve the five
percent goal, make advance payments to those
entities and award contracts to them at prices up to
ten percent above fair market cost.
Supreme Court
In the Richlin
Security Service decision, the Supreme Court held that
recovery by a prevailing party under the Equal Access to Justice
Act may include paralegal fees billed at prevailing market
rates.
In Allison
Engine Co. v. United States, the Supreme Court held that,
under section 3729(a)(2) of the False Claims Act, a
subcontractor can be found liable if it submits a false
statement to the prime contractor, intending that the prime use
the statement to induce the Government to pay the
subcontractor's claim.
|