| Contents   Boards of Contract Appeals
                (ASBCA, CBCA, PSBCA, and GAOCAB) Jurisdiction/Standing/Timeliness/Contract
                Disputes Act (CDA) Issues     In USProtect
                Corporation, the contractor appealed to the CBCA from the
                Contracting Officer's failure to issue a decision on a claim
                within the statutory time limits. The Board docketed the appeal,
                then suspended proceedings in part because the Government said
                it needed additional time to issue a decision and also to permit
                the parties to discuss settlement. Those discussions were
                unavailing so the Government finally issued a decision on the
                contractor's claim, and, at the same time, issued a decision on
                a government counterclaim. The contractor did not appeal the
                decision to the Board. The Government then attempted to amend
                its pleadings at the Board to include the counterclaim. The
                Board dismissed the counterclaim for lack of jurisdiction
                because the contractor had not appealed it (and still had time
                to appeal to the Court of Federal Claims). The contractor did
                not have to appeal the Government's belated decision on the
                contractor's claim--the docketing of the contractor's original
                appeal was enough to sustain continued jurisdiction.  The ASBCA dismissed 
				Valenzuela
                Engineering's appeal because, as a suspended corporation
                under California law, it lacked the capacity to maintain the
                appeal. 
				FloorPro
                concerns situations in which third party beneficiaries have
                standing and jurisdiction to pursue an appeal before the ASBCA. In Mr.
                Michael Ronchetti, the ASBCA found it lacked jurisdiction
                over a subcontractor's claim that was not sponsored by the
                prime. The Board held it (i) had jurisdiction
                over NSA
                contract disputes; (ii) lacked jurisdiction over a claim
                based on "humanitarian"
                grounds; and (iii) lacked jurisdiction over Qatar
                International Trading Co.'s complaint that the Government
                had lost the contractor's bulldozer after having towed it from
                an accident site (the actual facts are more complicated and more
                interesting than this summary). The Board also held that the
                Government had not extended only some services under the
                "Option to Extend Services" clause, but, rather, had
                extended the contract under the "Option to Extend the
                Contract Term" clause, such that elimination of some
                services was a partial termination for convenience or a
                deductive change, entitling Wackhenhut
                to compensation. The CBCA found it lacked jurisdiction over
                a claim for 
worker's
                compensation. In Guardian
                Environmental Services, the contractor submitted a certified
                claim covering monies allegedly owed under several disputed
                invoices. The Government subsequently released some of the
                disputed sums, but withheld the remainder. The contractor
                appealed. The Government moved to dismiss because it was
                preparing a claim for liquidated damages. The CBCA, however,
                found it had jurisdiction over the appeal despite the
                Government's unfulfilled intentions. In Qatar
                International Trading, the Board held that the Government's
                defense in tort did not divest the Board of jurisdiction over
                the contractor's claim (the contractor had claimed that the
                Government failed to pay satellite phone service charges for
                calls made from cell phones delivered to the Government by the
                contractor; the Government claimed the calls had come from
                cloned cell phones, i.e., had been made by tortfeasors). In Omegaman
                Fireprotection, the CBCA held it lacked jurisdiction over
                what was essentially a bid protest because there was no contract
                between the claimant and the Government. Often it's the contractor that is bitten
                by the release language in a termination settlement agreement.
                In Government
                Marketing Group, it was the Government's claims that were
                precluded by such a release.          Submission of Claim
                to Contracting Officer In Bowers
                Investment Company, the CBCA dismissed an appeal for lack of
                jurisdiction because the contractor had failed to submit a claim
                to the Contracting Officer, but instead had appealed after ADR
                procedures had failed to completely resolve its disputes with
                the agency. In Tidewater
                Contracting, the contractor originally submitted a claim for
                an extension of the contract time/period of performance. After
                its appeal of the denial of that claim had been docketed by the
                Board, the Government assessed liquidated damages against
                Tidewater. Tidewater argued its original appeal should cover
                that assessment. The Board rejected Tidewater's contention
                because Tidewater never submitted a claim to the Government for
                return of the liquidated damages.  In KAMP
                Systems, the contractor appealed from a government claim.
                Subsequently, the contractor amended its complaint to assert
                related counterclaims against the government. The Board struck
                those portions of the complaint because the contractor's claims
                had not been submitted to the Contracting Officer for a
                decision.          Certification In Teknocraft,
                the Board dismissed a claim without prejudice after holding that
                typing "//signed//" in a signature block was not a
                defect in a certification that could be remedied at the Board.  Request for
                Decision by Contracting Officer Normally, a claim must include a request
                for a decision from the Contracting Officer. In Fuel
                Tank Maintenance Co., citing Transamerica Insurance Corp.
                v. United States, 973 F.2d 1572 (Fed. Cir. 1992), the Board
                held that the following situation satisfied this requirement: [W]here [the contractor] submitted its
                REA after completion of the work, presentation of a final
                invoice, verbal notification of a claim, and a contracting
                officer request, in light of the verbal notification of a claim,
                to resolve all outstanding issues as expeditiously as possible,
                and where [the contractor] included a CDA certification, the REA
                requested a final decision. . . .         Appeal to Board In Northrop
                Grumman Ship Systems, the Board held that a contractor could
                appeal from the Contracting Officer's failure to issue a
                decision on a claim without asking the Board to direct him to do
                so: "In this case, the contracting officer neither issued a
                timely decision nor notified appellant when he would do so. The
                CDA does not require the contractor to ask the Board to direct
                the contracting officer to issue a decision before the
                contractor can appeal from the deemed denial of its claim; it
                merely permits the contractor to do so, at its option."                 In SUFI
                Network Services, the Contracting Officer returned the
                contractor's claim without deciding it because the Contracting
                Officer contended it was untimely filed. SUFI then appealed to
                the Board, and the Board accepted the appeal because the
                original claim was not untimely.  In Corners
                and Edges, the ASBCA held it had jurisdiction over a notice
                of appeal mailed before the date the CBCA became effective but
                received by the ASBCA after that date. In Devi
                Plaza, the CBCA held that the Contracting Officer's
                willingness to discuss settlement with the contractor after
                issuing the Contracting officer's decision tolled the 
                90-day appeal period even though the Contracting Officer had
                twice written the contractor to remind him that the original
                decision had included a statement of his appeal rights.         
                        
                           Costs
                and Cost Accounting Standards (CAS) On reconsideration, the ASBCA reversed its
                prior
                decision in the Raytheon CAS 413 segment-closing case, which
                had found the contractor liable to the Government for interest
                for failing to make timely period adjustments to pension
                costs.  In the most recent Raytheon
                decision, the Board held that its prior inferences from an
                unclear record were unjustified. However, the Board also decided
                that further development of the record is not necessary because
                the "contract price or cost adjustment did not result
                from a CAS violation or from a failure to follow a cost
                accounting practice consistently, which is what the CAS statute
                and CAS clause require in order for [the contractor] to be
                liable for a contract price adjustment and interest. . .
                ."        In The
                Boeing Co, Successor-in-Interest to Rockwell International Corp.,
                the CBCA held that the contractor could recover its defense
                costs associated with those counts on which it had prevailed in
                a suit filed against it under the False Claims Act, even though
                though the contractor was found liable on other counts in the
                same suit.    Delays       
                 The ASBCA's decision in the AEI
                Pacific construction case includes good, black letter
                discussions of accord and satisfaction; duty to cooperate;
                defective specifications; and compensable delays. The contractor
                prevailed on the theories of defective specifications and
                constructive acceleration. Concerning the defective design
                specifications, the Board noted as follows: When government plans or specifications
                specify, in design detail, the precise manner or method of
                performance, the government impliedly warrants a satisfactory
                performance result if they are followed. United States v.
                Spearin, 248 U.S. 132, 136 (1918); Essex Electro
                Engineers, Inc. v. Danzig, 224 F.3d 1283, 1289 (Fed. Cir.
                2000); Weststar Revivor, Inc. (formerly Westar, Inc.),
                ASBCA Nos. 52837, 53171, 06-1 BCA ¶ 33,288 at 165,030. Breach
                of the warranty entitles the contractor to recover all of the
                costs proximately flowing from the breach, including costs
                attributable to any resulting period of delay. See La Crosse
                Garment Manufacturing Co. v. United States, 193 Ct. Cl. 168,
                432 F. 2d 1377, 1385 (Ct. Cl. 1970). Unlike some situations in
                which the government has a reasonable time to make changes
                before it becomes liable for delay, "all delay due to
                defective or erroneous Government specifications are [sic] per
                se unreasonable and hence compensable." Essex, 224
                F.3d at 1289 quoting Chaney & James Construction Co. v.
                United States, 190 Ct. Cl. 699, 421 F.2d 728, 732 (Ct. Cl.
                1970). The Board utilized the five-pronged test for that
                theory espoused in Fraser Constr. Co. v. United States, 384
                F.3d 1354, 1361 (Fed. App. 2004): (1) that [the contractor] encountered
                [excusable] delay . . . .; (2) that [it] made a timely and
                sufficient request for an extension . . . ; (3) that the
                government denied [its] request for an extension or failed to
                act on it within a reasonable time; (4) that the government
                insisted on completion of the contract within a period shorter
                than the period to which [it] would be entitled by taking into
                account the period of excusable delay, after which [it] notified
                the government that it regarded the alleged order to accelerate
                as a constructive change . . . ; and (5) that [it] was required
                to expend extra resources to compensate for the lost time and
                remain on schedule. Tri-State
                Consultants tried almost every theory of construction
                contract recovery in the book, all to no avail. The ASBCA's decision in the Fox
                Construction case includes a discussion of the 
                "loss of production" theory of recovery: Loss of production occurs when a
                contractor is required by the government to change its method of
                performance so as to proceed in a less productive manner. Luria
                Brothers & Company v. United States, 369 F.2d
                701, 712 (Ct. Cl. 1966). . . . To be entitled to loss of
                productivity costs, a contractor must established a causal link
                or relationship between the affected work and the increased
                costs due to loss of productivity. DANAC, Inc., ASBCA No.
                33394, 97-2 BCA ¶ 29,184 at 145,153 ("absent a greater
                evidentiary link between the described phenomenon and this
                project," the Board refused to accept the Corps of
                Engineers' guide as sufficient proof of crew overloading); Triple
                "A" South, ASBCA No. 46866, 94-3 BCA ¶ 27,194 at
                135,537 (impact variables rejected because they showed no causal
                relation to any particular changes).   Changes/Constructive Changes/Contract
                Interpretation/Authority The introduction to
                the opinion in the Minneapolis
                Community Development Agency and City of Minneapolis case is
                an attention-grabber: " 'Most of the disputes in the
                world arise from words.' Morgan v. Jones, (1773) 98 Eng.
                Rep. 587, 596 (K.B.). As the appeal pending before us shows,
                words are no less troublesome in the contract disputes of today
                than they were when Lord Mansfield, Chief Justice was developing
                common law to govern commercial transactions." In Strand
                Hunt Construction, the ASBCA used the following standards to
                conclude that the contract was not ambiguous and that the
                contractor's interpretation was unreasonable: A contract is ambiguous only if it is
                susceptible of two different and reasonable interpretations,
                each of which is found to be consistent with the contract
                language. Edward R. Marden Corp. v. United States, 803
                F.2d 701, 705 (Fed. Cir. 1986). When the Board "steps into
                the shoes of a reasonable and prudent business person, aware of
                the situation" and a "plain reading of the contract as
                a whole seems to yield only one reasonable interpretation,"
                there is no ambiguity. Id. at 706. It is also well-established that a
                contract must be construed as a whole to give meaning to all of
                its provisions. Julius Goldman's Egg City v. United States,
                697 F.2d 1051 (Fed. Cir. 1983). In Service 
                Rodriguez Barragan, the Board found the contract was
                patently ambiguous, but the contractor still lost because it had
                failed to inquire about the ambiguity prior to bidding. In interpreting
                an ambiguous contract, a forum may sometimes look the
                "prior course" of dealing between the parties, but, as
                the ASBCA noted in C.R.
                Pittman Construction, a single transaction or occurrence is
                not sufficient to constitute a course of dealing.   In General
                Dynamics C4 Systems, the Board decided several issues
                relating to option contracts, including whether alleged
                government violations of FAR 17.202(c)(1) and 17.204(e) in
                exercising options entitled the contractor to relief. In Beyley
                Construction Group, the ASBCA denied claims for changed
                conditions based on a theory of quantum meruit because there was
                no evidence of an implied-in-fact contract and because the
                contractor's evidence for its cost estimates was
                "incomprehensible." After several
                rounds of preliminary skirmishes (SUFI I, II, and III), the
                ASBCA issued its decision on the merits in SUFI
                Network Services, and the decision is a smorgasbord of claim
                issues, theories, and defenses, including, inter alia,
                breach of duty to cooperate and duty of good faith dealing,
                misrepresentation, contract interpretation, contemporaneous
                interpretation, course of dealing, ratification, burden of
                proof, lost revenues, lost profits, claim preparation expenses,
                and consulting fees. In Alliance
                General Contractors, the ASBCA rejected a defective
                specification claim primarily because there was no basis to
                interpret the drawings as the contractor wished, i.e., by giving
                one of them precedence over the others. As a side note, the
                Board found the contractor had not established a causal link
                between the allegedly defective drawing and the alleged harm. Duty
                to Proceed  In 
                Second Street Holdings, the CBCA held that the contractor's
                compliance with the directions in the Contracting Officer's
                decision did not moot the claim issues on appeal. Terminations     In Blackstone
                Consulting, shortly after the contractor complained of
                sexual harassment by the COR's husband, the Government began
                taking more and more unilateral deductions for allegedly
                inadequate performance by the contractor, until the contractor
                wrote that it was being forced to exercise its right to cancel
                the contract within 120 days. The next yearly option exercise
                period came up before that 120 period expired, and the
                Government did not exercise the option. The contractor
                subsequently filed a claim for, among other things, anticipatory
                profits for the unexercised option year and the succeeding
                option year. The Civilian Board of Contract Appeals found the
                claim for the future option year too speculative, but the claim
                for the first unexercised year survived the Government's motion
                for summary dismissal. The ASBCA overturned
                a default termination that had been based on a failure to make
                progress because the Board found the contractor (Kostmayer
                Construction) had responded satisfactorily to a cure letter. Usually, it's the contractor that is
                arguing the terms of a termination settlement agreement are
                ambiguous. In  Government
                Marketing Group, however, the Government took this position
                and argued that extrinsic evidence must be used to interpret the
                document. The CBCA, however, held that (with one exception) the
                agreement was clear on its face, and reliance on extrinsic
                evidence was unnecessary. The Postal Service Board of Contract
                Appeals denied an appeal by a postal delivery contractor who had
                been terminated
                for default because he refused to comply with a unilateral
                contract amendment requiring him to deliver mail by driving down
                a gravel rural driveway that he considered unsafe. He lost his
                appeal because, after having had the driveway inspected, the
                Postal Service determined it to be narrow, but, nonetheless,
                safe. In Oregon
                Woods, the CBCA held that a Contracting Officer did not
                abuse his discretion in terminating for convenience a faulty
                contract whose specifications would require an indeterminate
                amount of time to review and correct. Severin
                Doctrine Under the Severin doctrine, the Government is
                not liable for a subcontractor's claim sponsored by the prime if
                the prime has no liability to the subcontractor. The doctrine is
                construed narrowly. In BearingPoint,
                the Government was unsuccessful in invoking it as a defense: The government tells us that, inasmuch
                as there was no executed subcontract between BearingPoint and
                Custer Battles, and no formal limitation of payments to what
                would be allowable under FAR if a formal subcontract were in
                place, "BearingPoint had not obligated itself to pay for
                any USAID disallowed costs." The government also asserts
                that following a dispute between BearingPoint and Custer Battles
                regarding outstanding invoices, BearingPoint "denied any
                liability for Custer Battles costs that were deemed
                unallowable" by the contracting officer. (The Government�s
                Motion to Dismiss With Prejudice for Lack of Jurisdiction Due to
                A Want of Standing Or, In the Alternative, Summary Judgment (gov't
                mot.) at 66-67) We articulated the test governing
                successful invocation of the Severin doctrine in M.A. Mortenson
                Co., ASBCA No. 53761, 06-1 BCA ¶ 33,180 at 164,439. We
                recognized there that the government "bears the burden to
                prove that the doctrine applies. It must establish that an
                iron-clad release or contract provision immunizes the prime
                contractor completely from any and all liability to the
                subcontractor for the government action at issue. The Severin
                doctrine is construed narrowly."  Purchase Orders In Comptech,
                the ASBCA went through a lengthy and detailed analysis of the
                legal status of unilateral purchase orders before concluding
                that the Government properly canceled such an order because the
                contractor failed to deliver conforming supplies within the
                required time. Quantum  In Southern
                Oregon Ecological (SOE) , the CBCA cut SOE some slack in
                specifying its damages because of its small business status:
                "SOE is appearing pro se . . . and is a small business
                concern, which appears to be essentially a one-man operation
                that hires subcontractors to perform the work. SOE is not
                expected to have the accounting system that a large company
                would have."   
				L-3
                Communications Corp. won bid preparation expenses (but not
                lost profits) at the ASBCA as a result of the Government's
                breach of the "fair opportunity to be considered"
                provision covering the solicitation for a delivery order under
                an ID/IQ contract. The ASBCA found a government breach but declined to
                award breach damages in Total
                Procurement Service, Inc., because the contractor failed to
                prove quantum, which is putting it mildly. The Board put it this
                way: "However, appellant here has failed to prove the
                amount, reasonableness and allocability of any costs that were
                incurred. Because of the almost complete absence of
                documentation or other corroboration of these costs and indeed
                the destruction of pertinent records, as well as conflicts in
                the amounts claimed, we also do not consider that a 'jury
                verdict' is appropriate. The failure to maintain, preserve and
                promptly produce to the government fundamental accounting data
                and records goes to the credibility of the entire claim.
                Appellant's actions with respect to those records were
                irresponsible and militate against any award." The ASBCA rejected the Government's attempt to charge
                the Southwest
                Marine for "overpaid REA interest" in the quantum
                portion of an appeal because that was a new claim introduced too
                late in the proceedings. Procedure In the Hedlund
                Construction case, the CBCA denied the parties' JOINT motion
                to vacate the Board's prior decision. In Public
                Warehousing Company (PWS), the ASBCA stayed the proceedings
                for a limited period of time to allow the Government to wrap up
                pending fraud investigations against the contractor in part
                because "[i]t is clear to us . . .  that PWC's
                primary purpose in wishing to proceed with the appeal is to use
                the Board's decision to influence the direction of the
                on-going investigations, and to help its position in potential
                settlement discussions." In Palm
                Springs General Trading and Contracting Establishment,
                however, the ASBCA denied a motion to stay an appeal pending
                criminal proceedings because, inter alia, the Government
                failed to show that there were substantial similarities of
                facts, issues, and witnesses between the ongoing criminal
                investigation and the board appeals. Discovery The CBCA's decision concerning the discovery disputes
                in LFH, 
				LLC
                includes a bunch of good, black letter analysis of
                attorney-client privilege issues, including the analysis of
                situations in which one agency discloses allegedly protected
                documents to another agency and the "common interest"
                doctrine. Equal Access to Justice Act In Freedom
                NY, the Board provided guidance to the parties concerning
                (i) the concept of substantial justification and (ii) the
                calculation and apportionment of Equal Access to Justice Costs
                on various claims for Contract Disputes Act interest and Prompt
                Payment Act interest when the contractor had originally
                prevailed on only some of its claims and had rejected
                substantial settlement offers from the Government.                    Court of Federal Claims Contract
                Disputes Act (CDA) / Tucker Act / Jurisdiction / Standing  In Lublin
                Corp., the Court of Federal Claims held that 31 U.S.C.
                1501(a) is not a statute of frauds that precludes the existence
                of an oral contract involving the federal government.  In Harper/Nielsen
                Dillingham Builders, the court held that, under the Severin
                doctrine, a prime could not sponsor a subcontractor's delay
                claim,  as applicable California law interpreted the
                "no damages for delay" clause in the subcontract, the
                prime had no liability to the sub. The CDA covers contracts
                with the United States. In Thomas
                D. Affourtit, the court held it lacked jurisdiction over a pro
                se suit by the President and sole shareholder of a company
                because it was the company that was in privity of contract with
                the Government, and it could only be represented by an
                attorney.  In Metrotop
                Plaza Associates, the court held that the time limit for
                appealing from a Contracting Officer's decision was tolled by
                his willingness to reconsider his decision and that
                "[r]econsideration . . . was implicit in [his] offer to
                discuss settlement."         What is a Claim? Thirty years into the practice of the CDA, and we
                still argue about whether individual submissions are
                "claims" within the meaning of the statute. See,
                e.g., NCLN2,
                Inc.  In Todd
                Construction Co. the court held that an allegation that a
                contractor's performance evaluation was issued without
                observing the proper procedures and was substantively erroneous
                constitutes a CDA claim. Similarly, in  BLR
                Group of America, the court held that it had jurisdiction
                over a complaint filed by a contractor based on the Contracting
                Officer's failure to decide the contractor's nonmonetary claim
                that a Contractor Performance Assessment Report (CPAR) was
                inaccurate and should be corrected. The decision is interesting
                and important on several levels. First, it declines to follow a
                line of ASBCA decisions that indicate quarrels over CPARs are
                not CDA claims. Secondly, it finds the requirements for a claim
                met when the contractor simply requested the Government to
                change the CPAR, without labeling the request a claim. Third, it
                reasons that a claim may be based on an assertion of any legal
                right, not necessarily a right that is explicitly expressed in
                the contract at issue. Finally, the court notes that recognizing
                such challenges to CPARs as claims (rather than requiring the
                contractor to wait and file a protest when the challenged CPAR
                actually has adverse consequences on a subsequent procurement)
                serves the interests of contract administration because a bid
                protest significantly interferes with, even disrupts, the
                procurement process, whereas a contract dispute under the CDA
                does not.    Authority In the Stout
                Road Associates case, a DLA intern made hotel reservations
                for herself and other interns at the site of DLA training
                classes. The classes were canceled; the intern canceled the
                reservations; and the hotel attempted to collect cancellation
                fees from the agency pursuant to the agreement the intern had
                signed. The Court of Federal Claims found the Government was not
                liable because the intern did not have the authority to enter
                into a government contract. The plaintiff also argued
                ratification, but the court found that the intern's superiors
                were not contracting officers either. Contract Interpretation After an interesting analysis of the scope and meaning
                of the Antideficiency Act and an indemnification clause in a
                World War II contract for the supply of aviation fuel to the
                Government, the Court of Federal Claims found the Government
                responsible for cleanup
                costs for which the contractors (Shell Oil, Union Oil,
                Atlantic Richfield, and Texaco) were found liable under CERCLA
                long after the war and long after the contracts had expired.  In the Manhattan
                Construction Company case, the Court of Federal Claims used
                basic rules of  grammar to determine the meaning of the
                phrase "as indicated in the drawings." Specifically,
                the court wrote: "Rules of grammar state that the
                subordinate clause 'as indicated on the drawings' modifies the
                noun or independent clause immediately preceding it. See Frederick
                C. Crews, The Random House Handbook 242 (5th ed. 1987).
                Also, the absence of a comma before the clause denotes that it
                applies only to the final noun or clause. See Resolution
                Trust Corp. v. Nernberg, 3 F.3d 62, 65 (3d Cir. 1993).
                Plaintiff's interpretation might have had support if a comma set
                off the subordinating clause; but the disputed clause, 'as
                indicated on the drawings,' does not have an offsetting comma. See
                Id. (noting that a comma preceding a subordinate clause 'may
                indicate that the qualifying language [applies] to all of the
                previous phrases and not merely the immediately preceding
                phrase[].'); Demko v. United States, 44 Fed. Cl. 83,
                87-88 (Fed. Cl. 1999) (using normal rules of punctuation to
                interpret a statute). Thus, the lack of a comma setting off the
                modifying phrase, 'as indicated in the drawings,' confirms that
                it does not apply to all of the preceding phrases."   Changes/Defective
                Specifications/Breach In Stevens
                Van Lines, the Court of Federal Claims found a contract on
                the basis of the "implied actual authority" of the
                Government's agents.  In Enron
                Federal Solutions ("EFSI"), the contractor had a
                privatization contract to buy the Government's dilapidated
                utility services plant, make certain capital improvements to it,
                and then provide utility services to the Government for a
                10-year period, with the monthly price designed to cover the
                cost of the services and gradually to pay for the original
                capital improvements. After EFSI completed the capital
                improvements and the first two years of service, it defaulted on
                its obligations and was terminated for default. The court denied
                EFSI's attempt to recoup the remaining costs of the capital
                improvements. The court based its decision in large part on an
                extensive analysis of the common law definition of a material
                breach and the common law consequences of such a
                breach.    In  Metric
                Construction Co., the contractor prevailed in its claim for
                the costs of repairing leaks in a roof it had installed. The
                court found (i) the Government's design specifications for the
                roof support structure were defective (even though the specs for
                the roof, itself, were performance specifications) and (ii) the
                Government gave an ambiguous, misleading reply to the
                contractor's request for guidance how to proceed once the
                contractor noticed problems with the roof installation during
                performance. In addition, the court used an approximation method
                for calculating the contractor's damages: "No better
                method (other than the rough calculations presented in this
                opinion) for computing damages exists, given the perplexing
                nature of the origin of roof leaks, which would provide a more
                precise dollar amount for the [Government's] liability in this
                case."          
                Under the constructive change doctrine, the government is liable
                for additional work caused by a constructive change to the
                contract. See Aydin Corp. v. Widnall, 61 F.3d 1571, 1577
                (Fed. Cir. 1995) ("Where it requires a constructive change in
                a contract, the Government must fairly compensate the contractor
                for the costs of the change." (citing J.B. Williams Co. v.
                United States, 450 F.2d 1379, 1394 (Ct. Cl. 1971))). Several
                categories of constructive change have been identified: "(I)
                disputes over contract interpretation during performance; (II)
                Government interference or failure to cooperate; (III) defective
                specifications; (IV) misrepresentation and nondisclosure of
                superior knowledge; and (V) acceleration." Miller Elevator
                Co. v. United States, 30 Fed. Cl. 662, 678 (1994) (citations
                omitted). A contractor may rely on specifications
                provided by the government when constructing a building
                according to those specifications. See Robins Maint., Inc. v.
                United States, 265 F.3d 1254, 1257 (Fed. Cir. 2001) ("Whenever
                the government uses specifications in a contract, there is an
                accompanying implied warranty that these specifications are free
                from errors.") (citing United States v. Spearin, 248
                U.S. 132, 137 (1918)); Essex Electro Eng�'rs, Inc. v. Danzig,
                224 F.3d 1283, 1289 (Fed. Cir. 2000) ("When the government
                provides a contractor with defective specifications, the
                government is deemed to have breached the implied warranty that
                satisfactory contract performance will result from adherence to
                the specifications, and the contractor is entitled to recover
                all of the costs proximately flowing from the breach.")
                (citations omitted). "The test for recovery based on
                inaccurate specifications is whether the contractor was misled
                by these errors in the specifications." Robins Maintenance, 
				265 F.3d at 1257. However, the government's implied warranty
                of its specifications is generally voided if the contractor does
                not follow those specifications. Mega Constr. Co. v. United
                States, 29 Fed. Cl. 396, 418 (1993) (citing Al Johnson
                Constr. Co. v. United States, 854 F.2d 467, 469-70 (Fed.
                Cir. 1988)). "It is well-established that contractors may be
                entitled to an equitable adjustment for increased costs of
                performance due to defective specifications." Clearwater
                Constructors, Inc. v. United States, 71 Fed. Cl. 25, 32
                (2006) (citing L.W. Foster Sportswear Co. v. United States,
                405 F.2d 1285 (Ct. Cl. 1969)); see also AAB Joint Venture v.
                United States, 75 Fed. Cl. 414, 429-30 (2007) (holding that
                when the specifications in a contract were largely inappropriate
                for the construction anticipated under the contract, the
                plaintiff could recover under a theory of defective
                specifications); Sterling Millwrights, Inc. v. United States,
                26 Cl. Ct. 49, 88 (1992) (holding that because certain
                specifications, which consisted of "predominantly, if not
                completely, design specifications," were defective, the
                plaintiff was "entitled to be paid for the extra expenses and
                time it incurred in trying to complete the project�". Even if
                a specification is defective, however, contractors must be
                reasonable in their conduct during construction. See Space
                Corp. v. United States, 470 F.2d 536, 538 (Ct. Cl. 1972)
                (stating that "when a contractor is faced with an obvious
                omission, inconsistency or discrepancy of significance, he is
                obligated to bring the situation to the government's attention
                if he intends subsequently to resolve the issue in his own favor�"
                (citations omitted). Contractors have a duty to inquire as to
                inconsistent specifications which include patent, that is,
                obvious or glaring, defects. See E.L. Hamm & Assocs.,
                Inc. v. England, 379 F.3d 1334, 1339 (Fed. Cir. 2004) ("To
                demonstrate that it was misled, the contractor-claimant must
                show both that it relied on the defect and that the defect was
                not an obvious omission, inconsistency or discrepancy of
                significance" in other words, a patent defect "that would
                have made such reliance unreasonable."); NVT Techs., Inc.
                v. United States, 370 F.3d 1153, 1162 (Fed. Cir. 2004) ("If
                the ambiguity is patent, it triggers a duty to inquire. A patent
                ambiguity is one that is "obvious, gross, [or] glaring, so
                that plaintiff contractor had a duty to inquire about it at the
                start."" (quoting H & M Moving, Inc. v. United States,
                499 F.2d 660, 671 (Ct. Cl. 1974))). If the erroneous nature of a
                defective specification is not glaring or obvious, however, the
                contractor may recover if it has been misled by the
                specification. See AAB Joint Venture, 75 Fed. Cl. at
                430-31. [M]isrepresentation is another category
                of constructive change. This particular type of constructive
                change occurs when the government has misrepresented information
                regarding a construction specification, and the contractor has
                relied upon the misrepresentation to his or her detriment. See
                Miller Elevator, 30 Fed. Cl. at 678 (citations omitted); see
                also Meyers Cos. v. United States, 41 Fed. Cl. 303, 311
                (1998) ("Misrepresentation occurs when the government
                misleads a contractor by a negligently untrue representation of
                fact, or fails to disclose information it has a duty to
                disclose." (quoting John Massman Contracting Co. v.
                United States, 23 Cl. Ct. 24, 31 (1991))). "Absent some
                valid basis for a contrary conclusion (e.g., an absence
                of detrimental reliance by a government contractor, a failure to
                investigate 'sources which would have revealed the truth,'
                or the like), the government "is liable for damage
                attributable to misstatements of fact (in a contract or
                specifications) which are representations made to the
                contractor."" Summit Timber Co. v. United States, 677
                F.2d 852, 857 (Ct. Cl. 1982) (quoting Flippin Materials Co.
                v. United States, 312 F.2d 408, 413 (Ct. Cl. 1963)) (other
                citations omitted). "In order for a contractor to prevail on a 
				claim of misrepresentation, the contractor must show that the 
				Government made an erroneous representation of a material fact 
				that the contractor honestly and reasonably relied on to the 
				contractor's detriment." T. Brown Constructors, Inc. v.
                Pena, 132 F.3d 724, 729 (Fed. Cir. 1997); see Helene
                Curtis Indus., Inc. v. United States, 312 F.2d 774, 778 (Ct.
                Cl. 1963) ("Specifications so susceptible of a misleading
                reading (or implication) subject the defendant to answer to a
                contractor who has actually been misled to his injury."
                (citations omitted). It is of no consequence that such
                misrepresentations may have been innocent and inadvertent, as
                long as they are material and the contractor suffers increased
                costs of performance as a result. Summit Timber, 677 F.2d
                at 857 (citing Everett Plywood & Door Corp. v. United
                States, 419 F.2d 425, 431 (Ct. Cl. 1969) and Morrison-Knudsen
                Co. v. United States, 345 F.2d 535, 539 (Ct. Cl. 1965)). In
                addition, if the government misrepresents information regarding
                its specifications in its communications to the contractor
                during performance, the government may be liable if the
                contractor relies on such misinformation. See Max Drill, Inc.
                v. United States, 427 F.2d 1233, 1243 (Ct. Cl. 1970) ("When
                an official of the contracting agency is not the contracting
                officer, but has been sent by the contracting officer for the
                express purpose of giving guidance in connection with the
                contract, the contractor is justified in relying on his
                representations [and may be entitled to an equitable adjustment
                for such misrepresentations of fact material to contract
                performance]." (citing Fox Valley Eng'r, Inc. v. United
                States, 151 Ct. Cl. 228, 240 (1960)). In the Information
                Systems & Networks Corp. decision, the Court of Federal
                Claims wrote: "[T]here is at least one other significant
                factual kink in plaintiff's assertion that defendant hatched a
                scheme to terminate it for default and seize its equipment -
                namely, it was not terminated for default, but rather for
                convenience." Bell
                BCI won its claim against the NIH at the Court of Federal
                Claims for the cumulative impact of 200 changes, but the part of
                the decision I enjoyed the most was this little gem regarding
                the Government's counterclaim for liquidated damages: "NIH
                did not believe that it had a factual basis to assert a
                liquidated damages claim against Bell. NIH asserted this claim
                only upon the advice of counsel to create negotiating leverage
                in the event Bell filed a claim. . . ." The
                Government's witness admitted this at trial. A Perry Mason
                moment. Carr
                Forest Products complained that the Government failed to
                make a reasonable estimate of the number and types of trees
                available in various lots in a fixed-price timber sales
                contract. The judge wrote that at one point the Government's
                estimators did not determine the size of the trees with
                measuring tape but instead performed "an ocular
                measure." Or, as we say in Texas, they eyeballed it. Government Breach In Spectrum
                Sciences and Software, the Court of Federal Claims delivered
                a stinging rebuke to the Government and held that the Air Force
                repeatedly had improperly used proprietary information
                concerning a company's munitions conveyor equipment (which the
                company had provided under the supposed restrictions of a
                Cooperative Research and Development Agreement) to issue a
                solicitation for such equipment, reveal proprietary details of
                the equipment to third parties,  and award a contract to
                one of the contractor's competitors for equipment based on the
                improper disclosure of that proprietary information. Quantum In Enron
                Federal Solutions, the court delineated the very limited
                circumstances in which it would allow quantum meruit recovery.          Equal Access to
                Justice Act (EAJA) In Bill
                Hubbard, the court (as directed by the Federal Circuit)
                recalculated (and reduced) an EAJA award based on the standards
                in Hensley v. Eckerhart, 461 U.S. 424 (1983). In International Air Response, the court scolded the
                Government for resisting its obligations under the EAJA.   The EAJA permits the court
                to adjust the statutory cap of $125 per hour for attorney's fees
                to take inflation into account (the COLA adjustment). In Ace
                Constructors, the court used a month-by-month analysis of
                the incurred fees rather than a single midpoint average to
                determine the COLA. In Metric
                Construction Co., the Court of Federal Claims found the
                Government's position in litigation was substantially justified
                and precluded an award of fees under the Equal Access to Justice
                Act even though (i) the contractor prevailed on the majority of
                its claim and (ii) the Government made almost no attempt to
                rebut the plaintiff's application for attorneys' fees because:
                "It was reasonable for the Government to have litigated
                this dispute to its conclusion."  Procedure In Ch2H
                Hill Hanford Group, the court decided that, because of
                overlapping issues, the case should be consolidated with one
                before the CBCA, but, because the court did not have the
                authority to demand of the CBCA that consolidation take place in
                the court, the court transferred the case to the CBCA. In Nova
                Express, the court held that the owner of a sole
                proprietorship may bring an action in the court without benefit
                of an attorney.   In Highqbpo,
                LLC, the  court stayed proceedings in a contract
                disputed pending criminal proceedings against the
                contractor.      Discovery In West
                Bay Builders, the Court of Federal Claims refused to permit
                the contractor to withdraw admissions it was deemed to have made
                by failing to provide a timely response to defendant's request
                for admissions. The plaintiff's cause was not aided by the fact
                that (more than seven months before plaintiff finally filed its
                motion requesting that its deemed admissions be withdrawn) the
                plaintiff had signed a joint status report to the court noting
                that the discovery responses were already overdue.          The Court of Federal Claims berated the Government for
                attempting to withhold far too many documents under claimed work
                product, deliberative process, and attorney-client privileges in
                Chevron
                U.S.A., Inc. v. United States.  In Northrop
                Grumman, Military Aircraft Division, the CoFC held that
                certain Claim Research Papers drafted to assist the Contracting
                Officer in making a decision and prepared primarily by
                contractual and technical staff were not privileged and were
                properly disclosed voluntarily by the Government, even though a
                government attorney had some part in their preparation and they
                had been stamped with a legend that they had been prepared in
                anticipation of litigation. Thus, the Government's disclosure of
                the documents was not a waiver of any claim of privilege with
                regard to other documents concerning the same issues. In Multiservice
                Joint Venture, during a break in a deposition, a version of
                an exhibit containing handwritten notes mysteriously disappeared
                and was replaced with a "clean" version of the
                exhibit. After the plaintiff's deponent, representatives, and
                attorneys all failed or refused to explain the situation to
                defendant's counsel and (later) the judge, the Court of Federal
                Claims barred the deponent from testifying at trial and ordered
                the plaintiff's attorneys personally to pay the
                defendant's costs of filing the motion for sanctions.    Court of Appeals for the
                Federal Circuit Jurisdiction/Standing/Res Judicata  Rick's
                Mushroom Service couldn't establish a basis for jurisdiction
                at the
                Court of Federal Claims, and now the Federal Circuit affirms
                the lower court's decision because the company's claims either
                sound in tort or are based on an agreement that does not involve
                a procurement of goods or services, neither of which is a proper
                basis for Tucker Act or CDA jurisdiction. In Phillips/May
                Corporation, in a case of first impression, the court held
                that the CDA did not alter the normal rules governing res
                judicata and claim preclusion so that the outcome of nine
                claims filed by the contractor at the ASBCA necessitated a
                summary judgment in favor of the Government on a tenth claim
                arising under the same contract and involving the same
                transactional facts appealed by the contractor to the Court of
                Federal Claims. Contract
                Interpretation/Changes/Authority/Breach In denying General
                Injectables & Vaccines' petition for rehearing, the
                Federal Circuit held that the failure of FAR 52.212-4(f) to
                state specifically that a contractor is liable for unexcused
                subcontractor delays does not change the fact that the
                contractor is liable for such delays. In International
                Technology Corp., the court listed four elements necessary
                for a differing site conditions claims to prevail: In order to prevail on such a site
                conditions claim, a contractor must establish four elements.
                First, the contractor must prove that a reasonable contractor
                reading the contract documents as a whole would interpret them
                as making a representation as to the site conditions. See
                Renda Marine, 509 F.3d at 1376 ("[A] contractor must
                first prove, as a threshold matter, that the contract contained
                some identification of the conditions to be encountered at the
                site."); H.B. Mac, Inc. v. United States, 153 F.3d
                1338, 1345 (Fed. Cir. 1998) (explaining that the court "place[s]
                itself into the shoes of a reasonable and prudent contractor and
                decide[s] how such a contractor would act in interpreting the
                contract documents"). This is a question of contract
                interpretation reviewed de novo on appeal. H.B. Mac, 153
                F.3d at 1345. Second, the contractor must prove that the actual
                site conditions were not reasonably foreseeable to the
                contractor, with the information available to the particular
                contractor outside the contract documents, i.e., that the
                contractor "reasonably relied" on the representations.
                Renda Marine, 509 F.3d at 1376 ("[T]he contractor
                must demonstrate that the conditions encountered were not
                reasonably foreseeable in light of all information available to
                the contractor when bidding[ and] that the contractor reasonably
                relied upon its original interpretation of the contract.").
                This issue is factual in nature, and review is deferential. See
                id. at 1378. Third, the contractor must prove that
                the particular contractor in fact relied on the contract
                representation. See id. at 1376. Again, this is a fact
                issue reviewed under a deferential standard. See id. at
                1378. Fourth, the contractor must prove that the
                conditions differed materially from those represented and that
                the contractor suffered damages as a result, which is again a
                fact question. See id. at 1376.          Most interesting, though, was the following footnoted
                dicta concerning a fifth element of government culpability that
                was sometimes listed in certain cases: The Board held that a showing of
                government culpability was also required, relying on a series of
                decisions by the Court of Claims. See Foster Constr. C.A.,
                435 F.2d at 881 ("Some degree of Government culpability -- either
                untruth or such error as is the legal equivalent -- must . . . be
                shown, and the plaintiff's burden of proof is not satisfied
                merely by proof of a variation between the subsurface conditions
                as stated in the contract and as encountered."); C.W.
                Blakeslee & Sons, Inc. v. United States, 89 Ct. Cl. 226
                (1939); Midland Land & Improvement Co. v. United States,
                58 Ct. Cl. 671 (1923). The government has declined to defend
                this holding, and we are skeptical that such a showing is
                required. More recently, when this court listed the elements of
                a claim for misrepresentation in a government contract in T.
                Brown Constructors, Inc. v. Pena, 132 F.3d 724, 729 (Fed.
                Cir. 1997), we did not list any element of government
                culpability. Under the general law of contracts, essentially the
                same elements as those listed in the text above are required to
                establish a misrepresentation claim, and no showing of
                culpability is required if the representation was material. See
                Restatement (Second) Contracts, ch. 7, topic 1, introductory
                note. As discussed below, a similar approach, which also
                requires no showing of government culpability, applies in the
                context of government contract claims under the Differing Site
                Conditions clause. See Renda Marine, 509 F.3d at 1377. In
                light of our disposition of this case, however, we need not
                reach the issue of whether government culpability must be
                established. In Northrop
                Grumman Information Technology, the court found that a
                document alleged to bind the government to a particular
                obligation was not expressly incorporated into the subsequent,
                official contract document and was, therefore, excluded by the
                contract integration clause. Anti-Assignment Act   In Delmarva
                Power & Light, the court recognized the Government's
                power to waive the prohibition against the assignment of claims
                against the Government in the Anti-Assignment Act, 31 U.S.C.
                3727(a). Terminations
                and Delays The court upheld the ASBCA's decision
                sustaining a termination for default in the General
                Injectables & Vaccines case. The contractor could not
                supply flu vaccine produced by its subcontractor because the FDA
                found it was contaminated. The contractor argued the FDA's
                action was governmental action constituting an excuse for
                nonperformance. The court held that the underlying cause was the
                subcontractor's default, which was attributable to the prime,
                even under the controlling, commercial items, "Excusable
                Delays" provision (FAR 52.212-4(f)), which does not include
                the traditional language that the default must be without the
                fault of the contractor "or its subcontractors. . .
                "). In other words, even in contracts for commercial items,
                the contractor is responsible for delays and defaults
                attributable to its subcontractors. Affirmative Actions Goals
                and Preferences In Rothe
                Development Corp., the Federal Circuit held that 10 U.S.C.
                2323 is unconstitutional because, in passing it, Congress did
                not have a "strong basis in evidence" to conclude that
                DOD was a passive participant in racial discrimination in
                relevant markets across the country and that race-conscious
                remedial measures were necessary. The Act (i) sets a
                "goal" that five percent of federal defense
                contracting dollars for each fiscal year be awarded to certain
                entities including small business concerns owned and controlled
                by "socially and economically disadvantaged
                individuals"; (ii) incorporates the Small Business Act's
                presumption that Black Americans, Asian Americans, Hispanic
                Americans, and Native Americans are socially disadvantaged
                individuals; and (iii) provides that the Department of Defense
                shall give specified forms of assistance to the listed entities
                and may, when practicable and necessary to achieve the five
                percent goal, make advance payments to those
                  entities and award contracts to them at prices up to
                ten percent above fair market cost. Supreme Court In the Richlin
                Security Service decision, the Supreme Court held that
                recovery by a prevailing party under the Equal Access to Justice
                Act may include paralegal fees billed at prevailing market
                rates. In Allison
                Engine Co. v. United States, the Supreme Court held that,
                under section 3729(a)(2) of the False Claims Act,  a
                subcontractor can be found liable if it submits a false
                statement to the prime contractor, intending that the prime use
                the statement to induce the Government to pay the
                subcontractor's claim.             |