| May
18 |
The
Commerce Department's Bureau
of Industry and Security (BIS) is proposing (i) to
delineate how auxiliary and miscellaneous military equipment and
related articles the President determines no longer warrant control under
Category XIII (Auxiliary Military Equipment) of the United States
Munitions List (USML) would be controlled under the Commerce Control
List (CCL) in new Export Control Classification Numbers (ECCNs) 0A617,
0B617, 0C617, 0D617, and 0E617 as part of the proposed new
"600 series" of ECCNs; (ii) to integrate into these five new ECCNs
those items within the scope of Wassenaar Arrangement Munitions List
(WAML) Category 17 that would be removed from the USML, or that are not specifically identified on
the USML or CCL but that are currently subject to USML
jurisdiction; and (iii) to control some items now classified under ECCNs 0A018,
0A918 and 0E018 under new ECCNs 0A617 and 0E617, in order to consolidate
auxiliary and miscellaneous military equipment and related articles on the
CCL in the proposed new "600 series." Comments are
due by July 2.
The State
Department proposes to amend the ITAR to revise Category
XIII (materials and miscellaneous articles) of the USML to describe more precisely the
materials warranting control on the USML. Comments are due by
July 2.
|
| May
17 |
FAR
Case 2011-019: A proposed FAR revision would remove
references to specific paragraphs in superseded Financial
Accounting Standard 106 from FAR 31.205-6 (Compensation
for Personal Services) because they are obsolete. Comments are
due by July 16.
|
| May
16 |
The SBA is
proposing extensive revisions to its regulations at 13 C.F.R.
Parts 121 and 124-127 to reflect the provisions of the Small
Business Jobs Act of 2010 that concern multiple-award
schedule contracts (and orders placed against such
contracts) and the consolidation of contracts, including
proposed revisions to the following sections (among many
others): 121.103 (how the SBA determines affiliation); 121.402
(what size standards are applicable to federal procurements);
121.404 (the date the size of a business concern is
determined); 121.1001 (who may initiate a size protest);
121.1004 (the time limits for filing size protests); 121.1103
(the procedures for NAICS or size standard designations); and
125.1 (definitions governing SBA's government contracting
programs). Comments are due by July 16.
|
| May
15 |
The SBA
has issued corrections
to several errors in its previously published rule concerning
8(a) business development/small disadvantaged business status
determinations at 13 C.F.R. Part 124.
In order
to implement provisions of the National Defense Authorization Act for Fiscal
Year 2012, the SBA is proposing to amend its regulations governing size
and eligibility for the Small Business Innovation Research (SBIR) and Small
Business Technology Transfer (STTR) Programs by
addressing ownership, control and affiliation for program
participants, including those that are majority owned by multiple
venture capital operating companies, private equity firms, or hedge funds.
Comments are due by July 16.
|
| May
13 |
In 360Training.com,
Inc., the Court of Federal Claims held it had jurisdiction
under 28 U.S.C. 1491(b)(1) over a post-award protest
involving a "request for application" issued by OSHA
under which successful applicants would be awarded
nonfinancial cooperative agreements to provide online OSHA Outreach Training Program
courses. The court noted as follows:
[T]he Court recognizes that not all cooperative agreements are procurements under
the Tucker Act. Where an agency, pursuant to a statutory directive, is distributing funds or
providing assistance to service providers to ensure a service’s availability, it is not conducting a
procurement. However, where an agency has a statutory mandate to provide a service, and the
agency decides to use a cooperative agreement to obtain the provision of that service, that agency
has engaged in a procurement process under the Tucker Act and this Court has jurisdiction over
protests in connection with that process.
The SBA's
OHA published two size decisions.
In Size
Appeal of Hardie's Fruit & Vegetable Company South, LP
(the latest decision in the epic battle between that firm and
M&S Foods Co.), the OHA vacated the Area Office's
determination and remanded the case for further analysis
because (i) it was not clear which NAICS codes were used for
the procurements, which in turn, might have affected which
protest allegations the Area Office should have considered;
and (ii) the Area Office improperly applied the simplified
acquisition exemption to its analysis of the
procurements.
In Size
Appeal of RGB Group, Inc., the OHA upheld the Area Office's finding of
affiliation through identity of interest with no clear fracture
between a husband and wife who had numerous ties to one another in
operation of various firms.
|
| May
11 |
DoD has
published an interim final rule to establish a voluntary cyber
security information sharing program between DoD and eligible
Defense Industrial Base companies in order to enhance participants’
capabilities to safeguard DoD information that resides on, or transits,
unclassified information systems. Comments are due by July 10.
|
| May
10 |
Federal
Acquisition Circular (FAC) 2005-59 has been published and
includes the following three items:
FAR
Case 2012-013 (Prohibition on Contracting With Inverted
Domestic Corporations): An interim rule amends the FAR to implement a section of the Consolidated
Appropriations Act, 2012, which prohibits the award of contracts using
appropriated funds to any foreign incorporated entity that is treated as an
inverted domestic corporation or to any subsidiary of such an entity.
Comments are due by July 9.
FAR
Case 2012-012 (Free Trade Agreement--Columbia): Effective
May 15, another interim rule amends the FAR to implement the United States-Colombia
Trade Promotion Agreement, which provides for mutually non-discriminatory treatment of eligible
products and services from Colombia. Comments are due by July
9.
FAR
Case 2012-003 (Revision of Cost Accounting Standards
Threshold): A final rule amends the FAR to revise the threshold for
the applicability of cost accounting standards (by
substituting "$700,000" for "$650,000" in
several FAR sections and clauses) in order to implement a recent rule of the Cost
Accounting Standards Board and statutory requirements.
In CPR
Restoration, LLC, the CBCA dismissed an appeal for lack of
jurisdiction because the appellant did not have a contract
with the agency and appeared to have been only a
subcontractor, with no right of direct appeal.
|
| May
9 |
In Terex
Corp., a post-award protest, although the Court of Federal
Claims could not determine which party's interpretation of
test data (concerning whether or not a test vehicle improperly
stalled) was correct, it denied the protest because (i) the
agency had thoroughly analyzed the data as part of a rational
evaluation of the relevant factors (and the court was not in a
position to substitute its judgment for that of the agency's
evaluators); and (ii) the solicitation did not require
offerors to build and test an actual production vehicle, but
only to present test data from similar vehicles to the one it
planned to provide, which would be predictive, rather than
conclusive.
In California
Industrial Facilities Resources, Inc., the court held that an RFQ
and the proposed award of the resulting task order were
unobjectionable because they did not exceed the scope of the
underlying ID/IQ contracts.
|
| May
8 |
In Kellogg
Brown & Root Services, Inc., the Court of Federal
Claims ruled on a very complex factual situation involving the
contractor's burden of proving the reasonableness of its
claimed costs in connection with a contract to provide dining
facility services to troops in Iraq, in a situation that was
further complicated by the fact that two of the contractor's
managerial employees accepted kickbacks from a subcontractor,
which, in turn, resulted in government counterclaims for (i)
violations of Anti-Kickback Act and (ii) common law fraud
(with the court ultimately deciding that the contractor was
liable only for the return of the amount of the kickbacks
accepted by those employees).
In
Distributed
Solutions, Inc. and STR, L.L.C. (after the CAFC reversed
the Court of Federal Claims' prior decision that it did not
have jurisdiction over this type of protest), the Court of
Federal Claims held that the procuring agency had not provided
a rational basis for switching from proposed direct
procurements of two types of software to having its prime
contractor to procure the software.
In Pew
Forest Products, the plaintiff argued (unsuccessfully, in
both cases) that (i) its timber logging contracts came into
existence at the time bids were opened and its bid was
declared to be the best bid (as opposed to when the Government
later signed the contracts), and (ii) its logging operations
were compensably delayed by contingencies that the
solicitation and contract documents clearly stated might
occur.
In
Versar,
Inc., the ASBCA denied both parties' delay claims against
the other because neither party presented evidence (i)
concerning concurrent delay or (ii) segregating its own and
its opponent's delays.
The ASBCA
denied an appeal by Hartman
Walsh Painting Co. because, in connection with its
misrepresentation claim, the contractor failed to prove that
the Government made an erroneous representation of material
fact.
In CACI,
International, Inc., the ASBCA held it had jurisdiction
over the contractor's appeal from a government finding of
noncompliance with CAS 403 even though there was no allegation
of a monetary impact due to the alleged noncompliance.
In Waterstone
Environmental Hydrology and Engineering, Inc., the ASBCA
dismissed an appeal not filed at the Board within 90 days of
receipt of the Contracting Officer's decision (the contractor,
without the assistance of counsel, had initially appealed to
the wrong forum).
|
| May
6 |
In Size Appeal of
Bosco Constructors, Inc., the SBA's OHA held that, even though
the Area Office erroneously concluded that the protester had
been eliminated from the competition (and lacked standing),
the appeal should be dismissed as moot because the agency was
in the process of making a new award decision, which might
result in an award to a different firm from the one whose size
had been protested.
|
| May
3 |
The
Commerce Department's Bureau of Industry and Security (BIS)
has published a proposed
rule (i) describing how energetic materials and related articles that the President
determines no longer warrant control under Category V (Explosives and
Energetic Materials, Propellants, Incendiary Agents and Their Constituents) of the United States
Munitions List (USML) would be controlled under the Commerce Control
List (CCL) in new Export Control Classification Numbers (ECCNs) 1B608,
1C608, 1D608, and 1E608; (ii) controlling (under ECCN 1C111) some of
the aluminum powder and hydrazine and derivatives thereof that are now
controlled under Category V of the USML; (iii) placing control equipment for the
"production" of explosives and solid propellants, currently controlled under ECCN
1B018.a, and related "software," currently controlled under ECCN
1D018, under new ECCNs 1B608 and 1D608, respectively; and (iv)
placing commercial charges and devices containing energetic materials, which
are currently controlled under ECCN 1C018, under new ECCN 1C608.
Comments are due by June 18.
FAR
Case 2011-028: A proposed
rule would amend the FAR to implement Executive Order
13495 and the related DOL regulations concerning the nondisplacement
of qualified workers on successor service contracts.
Comments are due by July 2.
In Englewood
Terrace Limited Partnership, a
nonprecedential decision, the Court of Appeals for the Federal
Circuit remanded
the case to the CoFC for a recalculation of a lost profit
award following a breach because the lower court had not
subtracted the costs saved by reason of the breach.
|
| May
2 |
Effective
June 1, the State Department is amending section
123.17 of the ITAR, inter alia, (i) to add an exemption for the temporary export of
chemical agent protective gear for personal use; (ii) to
revise the exemption for body armor to also cover helmets when they are included with the body
armor; and (iii) to clarify the exemption for firearms and
ammunition by removing certain extraneous language that does not change the meaning of the
exemption.
The State
Department also is proposing to amend the ITAR in order to
revise Category
V (explosives and energetic materials, propellants, incendiary agents, and their
constituents) of the U.S. Munitions List to describe more precisely the
articles warranting control thereunder. Comments are due by
June 18.
|
| May
1 |
The
Department of Agriculture is proposing extensive amendments to
nine sections of 7 C.F.R. Part 3201: "Guidelines for
Designating Biobased Products for Federal Procurement."
Comments are due by July 2.
In 5860
Chicago Ridge, LLC, the Court of Federal Claims (i) upheld
the Government's default termination of a building lease due
to numerous, longstanding water leak problems even though the
Government failed to strictly comply with lease's cure period
requirements because the contractor indicated it could not
have fixed all the leaks within the full cure period, but (ii)
denied the Government's claims for relocation costs (because
the Government failed to meet its burden of proof to show
which of those costs were necessary) and excess reprocurement
costs of substitute rental space (because the Government's
witness failed to compare the relocated space with the
original space to establish they were similar).
In
BayFirst
Solutions, LLC, the Government cancelled an 8(a) set-aside
solicitation and awarded a task order to a firm under its
already existing ID/IQ contract as a bridge to tide the
Government over until it could issue a new solicitation.
BayFirst protested that task order (and the cancellation of
the original solicitation) because BayFirst claimed that
transferring the incumbent's employees to the bridge
contractor during the interim period would deprive BayFirst of
the advantage it would have had bidding on the original
solicitation since it had planned to offer to use the
incumbent's employees (by utilizing the incumbent as its
subcontractor). Although the court found it had jurisdiction
over significant portions of the protest, which were not
affected by the limits on task order protests, the court
denied the protest because BayFirst failed to prove that the
cancellation was unfair or unjustified or that the task order
was beyond the scope of the ID/IQ contract. (BayFirst had won
an earlier protest on this competition; see January 14
entry below.)
In
Three
S Consulting, the court held that (i) the protester lacked
standing to challenge the original contract award because it
was not a qualified offeror and (ii) the alleged actions of a
government employee (who was not authorized to enter into
government contracts) in facilitating agreements between
private parties to complete work on a cancelled contract were
not within the court's bid protest jurisdiction.
In Top
Painting Co., the ASBCA granted the Government's motion
for summary judgment and rejected the contractor's claim for
Differing Site Conditions because (i) the contractor had
failed to conduct a pre-award site visit; (ii) the conditions
encountered by the contractor were visible (neither subsurface
nor latent); and (iii) the contract required the contractor to
deal with conditions of that type.
|
| April
30 |
In Midwest
Tube Fabricators, Inc., the Court of Federal Claims
granted the protester's motion to supplement the
administrative record by deposing the Contracting Officer
(whose declaration had already been filed by the Government)
and by filing declarations of its own relating to a simplified
acquisition procurement under FAR Part 13 because of gaps in
the record attributable to the informal procedures used in the
procurement.
|
| April
29 |
The CBCA
upheld the default termination of a roadway vegetation
maintenance contract held by D&M
Grading, Inc., because the conditions encountered by
contractor (which it claimed excused its failure to complete
the work) did not amount to either a Type I or Type II
Differing Site Condition.
The CBCA
also granted in part a motion for reconsideration by Bannum,
Inc., of a prior
decision (which had dismissed its claim as time barred)
because the contractor had complained of many acts by the
Government that occurred more recently than six years in the
past.
|
| April
24 |
In Triad
Mechanical, Inc., the ASBCA dismissed an appeal for lack
of CDA jurisdiction because (i) the contractor's termination
for convenience settlement proposal was not a claim despite
the fact that contractor had labeled it as such, and
(ii) a government request for additional documentation before
completing its audit of the proposal did not signify an
impasse over it.
In Valley
Apparel, LLC, the ASBCA denied an appeal because one
statement in a footnote to a solicitation for an indefinite
quantity contract to supply parkas regarding the percentage of
each size parka the Government "anticipated"
ordering was not a guarantee that the Government would order
those percentages, especially when read in connection with
numerous other solicitation provisions indicating the amounts
to be ordered were uncertain.
In Size
Appeal of Williams Adley & Company -- DC, LLP, the
SBA's OHA upheld the Area Office's use (in a size
determination) of a firm's most recent tax return, which had
not been filed until after the firm's self-certification but
which was available at the time of the SBA's size
review.
Aldevra
won another GAO protest because, once again, the VA failed to
consider whether an acquisition should be set aside for
SDVOSBs before proceeding with FSS requirements. Why does this
remind me of Jeff Probst's signature redundancy: "Once
again, immunity is back up for grabs"?
|
| April
22 |
In Parsons
Global Services, Inc., the Court of Appeals for the
Federal Circuit affirmed an ASBCA decision dismissing an
appeal for lack of CDA jurisdiction because a prime
contractor's request for payment of its subcontractor's
overhead and G&A costs (at a rate specified in the
subcontract) submitted two years after a termination for
convenience was "routine" and, therefore, not a
claim within the meaning of the CDA. It's hard to argue with
the court's reasoning, but read the dissent to get a feel for
the frustration (shared by many in the government contracting
community) with the procedural hassles still being engendered
by a statute that was intended to be much simpler in its
application than it has turned out to be.
|
| April
20 |
In an
elliptical, qualified, and verbose opinion, the Court of
Federal Claims held that Triad
Logistics Services Corp., the incumbent contractor, lacked
standing to challenge the DoD's insourcing decision because
its contract had been completed before it filed its second
complaint. The protester had begun challenging the DoD's
decision at the GAO before its contract expired and filed its
first complaint in the court the day the contract expired,
after which the court dismissed that complaint without
prejudice because the agency voluntarily undertook corrective
action, which the plaintiff promptly challenged when it
learned of the results. Because the timing of the second
complaint was dictated by the actions of the Government, the court's
reasoning is suspect.
|
| April
19 |
The State
Department announced that on April 13, 2012, (i) the treaty between the
United States, Great Britain, and Northern Ireland concerning defense
trade cooperation (Treaty Doc. 110–7) came into force;
and (ii) the rule previously announced at 77 Fed. Reg. 16592 implementing the
treaty and making other updates to the ITAR (see March
22 entry below) became effective.
|
| April
18 |
Federal
Acquisition Circular (FAC) 2005-58
has been published and includes the following three items
(plus technical amendments):
FAR
Case 2010-004 (Biobased Procurements): Effective May 18, a
final rule amends the FAR to implement changes (due to the Farm
Security and Rural Investment Act) that require contractors to report the
biobased products purchased under service and construction
contracts, which will enable agencies to monitor compliance with the
federal preference for purchasing biobased products.
FAR
Case 2010-018 (Representation Regarding Export of
Sensitive Technology to Iran): Effective May 18, a final rule
adopts, with changes, the prior interim rule amending the FAR
to add a representation to implement section 106 of the Comprehensive Iran Sanctions,
Accountability, and Divestment Act of 2010, which imposes a procurement prohibition relating to
contracts with persons that export certain sensitive technology to Iran.
FAR
Case 2009-038 (Justification and Approval of Sole-Source
8(a) Contracts): A final rule adopts (without change) the
prior interim rule amending the FAR to implement a section of the National
Defense Authorization Act for Fiscal Year 2010, which requires the
head of an agency to execute (and make public prior to award) the justification
for an 8(a) sole-source contract in an amount exceeding $20
million.
The VA is
proposing to amend its acquisition regulations to require contractors to submit
payment requests
in electronic format. Comments are due by June 18.
|
| April
17 |
Effective
May 17, the State Department is amending the ITAR to to remove
references to the International Import
Certificate (Form BIS–645P/ATF–4522/DSP–53), which
will end the Department’s current practice of accepting DSP–53
submissions. Instead, the DSP–61 is to be used by importers when necessary.
The
Commerce Department's Bureau of Industry and Security (BIS) proposes to
amend the Export Administration Regulations (EAR) (i) by adding a
requirement for persons shipping under Authorization Validated End-User
(Authorization VEU) to send written notice of such shipments to the recipient
VEU and (ii) to clarify that when items subject to item-specific conditions under Authorization
VEU no longer require a license for export or reexport or become eligible for
shipment under a license exception, as set forth in the EAR, VEUs are no longer
bound by the conditions associated with such items. Comments
are due by June 18.
Contracting,
Consulting, Engineering, LLC, won its post-award protest
at the Court of Federal Claims because the agency's evaluators
irrationally supplied required information missing from the
awardee's proposal by assuming that the experience of the
awardee's proposed employees was consistent with the
evaluators' knowledge of the length of typical agency tours of
duty.
The same
court found a post-award protest by Contract
Services, Inc., untimely because, prior to submitting its
proposal, the protester had not objected to a solicitation
requirement that it appear on the list of HUBZone certified
firms at the time of proposal submission, even though it had
been aware it was not on the list and had asked the SBA to
speed up the process of including its name.
The ASBCA
published several decisions.
In A-1
Horton's Moving Service, Inc., the Board denied the
Government's motion to dismiss for lack of CDA jurisdiction
and held that a claim for breach of a transportation
services contract when no services have been provided (as
opposed to a claim for monies due once services under such an
agreement have been provided) is governed by the CDA rather
than section 3726 of the Transportation Act.
In Ironhorse
Ltd., the Board held that a reminder letter sent by the
contractor three months after its submission of the original
REAs to the Contracting Officer converted those REAs into
claims filed within the CDA's six-year statute of limitations.
In Kellogg
Brown & Root Services, Inc., the Board denied both
parties' dispositive motions because there remained material
issues of fact even after the Board concluded that the
contract contained no categorical prohibition on the use of armed private security
companies (without the express permission of the Theater
Commander) to supplement the government force protection where necessary to accomplish the logistical support mission.
In SplashNote
Systems, Inc., the Board denied the contractor's motion
for reconsideration of the Board's prior
decision disallowing (i) deferred IR&D costs and (ii)
a large bonus which the Board had concluded was a distribution
of profit.
|
| April
16 |
The CBCA
published two decisions.
In ASP
Denver, LLC, the Board denied the Government's motion to
dismiss for lack of CDA jurisdiction because the fact that the
real estate tax assessment in dispute was under appeal to the
taxing authority (and, therefore, ultimately might be reduced)
did not change the fact that the contractor had claimed a
definite amount as a sum certain in its claim.
In Singleton
Enterprises, the Board upheld a default termination after a
contract had been reinstated following an earlier default because there
was no reasonable prospect the contractor could meet newly agreed upon
completion date and because the contractor had not shown performance was
impossible due to an allegedly defective spec.
|
| April
13 |
The
Commerce Department's Bureau of Industry and Security (BIS)
has published a final rule amending the Export Administration
Regulations (EAR) by adding a new a new Export Control Classification Number (ECCN) series,
0Y521,
to the Commodity Control List (CCL) to cover items that warrant control
on the CCL but are not yet identified in an existing ECCN.
|
| April
11 |
The GAO
published two decisions sustaining protests by The Emergence
Group on the same solicitation. In the
first, the GAO found that the agency (i) did not
meaningfully evaluate the relevance of prior contracts in the
past performance evaluation and (ii) did not evaluate the
protester's proposal consistently with evaluation of other
offeror's proposals. Dissatisfied with the results of the
corrective action undertaken by the agency in response to the
first protest, the protester filed a
supplemental protest against the revised past performance
evaluation, which the GAO subsequently found to be
unreasonable and not in accordance with the solicitation's
evaluation criteria.
|
| April
10 |
The GAO
sustained a protest by DNO,
Inc., because the procuring agency did not properly
investigate whether the solicitation should have been set
aside for small businesses.
|
| April
6 |
In HP
Enterprise Services, LLC, a successful post-award protest,
the Court of Federal Claims held that the agency wrongfully
awarded a contract to a higher-priced offeror on the basis of
an unstated evaluation criterion improperly used to disqualify
the protester's proposal.
The CBCA
has published several decisions.
Fluor
Intercontinental, Inc. lost on every one of its many
construction contract claims because (i) the Government did
not warrant that infrastructure would be in place at the
construction site; (ii) the contract included only a
performance specification and placed the onus of performing a
site investigation and the risk of a faulty design on the
contractor; (iii) changes in contractor's design for a
perimeter wall were its own responsibility; and (iv) the
contractor failed to give proper notice to the Contracting
Officer concerning its claim for constructive acceleration and
did not receive directions to accelerate from the Contracting
Officer.
In CDA,
Inc., the CBCA upheld both (i) a termination for cause of
a commercial items contract on the basis of late delivery
(despite the lack of cure notice) because the contractor
failed to meet numerous schedules and reported it could not
timely meet other contract requirements, and (ii) the
Government's subsequent assessment of excess reprocurement
costs because the Government showed (a) the reprocured supplies or services
were the same as or similar to those involved in the termination;
(b) the Government actually incurred excess costs; and (c) the Government
acted reasonably to minimize excess costs.
In The
Timber Harvester, Inc., which involved primarily issues of
contract interpretation, the CBCA denied the Government's
claim for allegedly uncut timber under a scaled salvage timber
sale contract because the Government did not prove that any
remaining timber met the contract's utilization standards, as
defined by its sawtimber and merchantability descriptions.
In The
Carrington Group, Inc., the CBCA concluded that a contract
stating it was an indefinite delivery/indefinite quantity
contract, but lacking any minimum quantity, was defective and
that, therefore, the contractor was entitled "only to the compensation agreed upon in
the contract attributable to the work performed, with the reasonable value of the work
measured by the contract prices." The Board also denied
the contractor's claim submitted long after the conclusion of
contract performance for services not listed in contract
schedule absent proof Government actually ordered the
services. My favorite part of the decision, however, is the
following lament by the Board:
The terms of this contract, Carrington’s performance and billing, and the VA’s
administration and payments were presented to the Board in a jumble of facts with notable
gaps that took significant time to unravel. The VA appears to have used numbers for funding
mechanisms and obligations interchangeably with contract numbers, making the tracking of
payments, contracts, and obligations very difficult to sort out. Whatever system the VA had
was understood, at best, only by the VA, or, possibly, not at all. The confusion caused by
funding issues complicated what should have been a very simple procurement.
Even
construing the board filings by the pro se claimant liberally,
the CBCA denied
various payment, termination, and harassment claims by House
of Joy Transitional Programs as entirely unsupported.
|
| April
5 |
DFARS
Case 2011-D056: DoD is proposing an extensive set of
changes to many parts of the the DFARS in order (i) to clarify
the clauses required in commercial item contracts and the
flowdowns applicable to subcontracts under such contracts and
(ii) to simplify the prescriptions for such clauses. Comments
are due by June 4.
|
| April
4 |
In SWR,
Inc., the ASBCA denied the Government's motion to dismiss
a claim for lack of jurisdiction and held that the contractor
took sufficient steps under 11 U.S.C. 1123 to preserve its
claim in bankruptcy by adequately disclosing the claim in its
reorganization plan and disclosure statement.
|
| April
3 |
In
Raytheon
Co., the Court of Federal Claims held that the CDA's
six-year statute of limitations barred a Contracting Officer's
decision on a government claim issued ten years after
the advance agreement on allowable costs that the decision
purported to challenge and that (i) the continuing
claims doctrine, (ii) equitable tolling under the FAR
"Credits" clause, and (iii) the accrual suspension
doctrine did not apply in this situation. The Government's
claim had been based on an audit conducted after the
expiration of the six-year period, apparently motivated by
criticism of the original audit conducted within that
period.
In
Clinton
Reilly, the court held that a bid protest filed more than
nine months after the plaintiff learned of the facts forming
the basis of the protest was barred by the doctrine of laches.
In The
Electronic On-Ramp, Inc., a successful pre-award protest,
the plaintiff convinced the court that the Government's
rejection of a proposal as late was unreasonable because the
electronic copy had been delivered on time and the only
problem with delivery of the hard copy was the Government's
delay after the plaintiff's courier made it to the security
checkpoint on time.
|
| April
1 |
In Size
Appeal of Ma-Chis Lower Creek Indian Tribe Enterprises, Inc.,
the SBA's OHA held that a firm lacked standing to appeal
statements about its own size included in another firm's size
determination (but was free to raise those issues if its own
size were ever challenged).
|
| March
30 |
DFARS
Case 2012-D018: Effective April 30, the DFARS is being
amended to reduce the threshold for DoD peer reviews of noncompetitive
contracts from the current level of $1 billion to $500 million.
DFARS
Case 2012-D016: An interim rule amends the DFARS to implement a section of the
National Defense Authorization Act for Fiscal Year 2012, which requires that the
statutory limitation on the acquisition of right-hand drive passenger sedans be
included on the list of dollar thresholds subject to inflation adjustment.
Comments are due by May 29.
DFARS
Case 2011-D048: A final rule amends the DFARS to separate provisions and clauses that are currently
combined in order to comply with DFARS drafting conventions
concerning the distinction between (i) solicitation provisions
that are not part of the resulting contract and (ii) contract
clauses.
DFARS
Case 2012-D020: A final rule amends the DFARS to remove a congressional notification
requirement for single source task-order or delivery-order contract awards over
$103 million.
A
technical amendment to the DFARS adds a section 203.806 to
provide an address for reporting suspected
lobbying violations.
The Guzar Mirbachakot Transportation
protest is an example of the closer review a protester may
receive at the Court of Federal Claims as opposed to the GAO.
In this case, the GAO had dismissed a protest based on (i) the
agency's assertion that the solicitation prohibited the
submission of proposals via "zip" files and (ii) a
message sent to by the agency's contract specialist to the
protester just a few hours before the proposal deadline
stating that such files were prohibited. The Court of Federal
Claims, however, allowed expert testimony and determined (i)
that the solicitation contained a latent ambiguity on the
issue, (ii) that the protester's interpretation was
reasonable, and (iii) that the last-minute email from the
contract specialist was not enough to change the court's
opinion, especially because the agency had waived other
responsiveness requirements for other offerors. Of course, a
protest at the court is generally much more expensive than one
at the GAO, but you get what you pay for.
|
| March
29 |
The Court
of Federal Claims held that, pursuant to 10
U.S.C. 2304c(e)(1),
it lacked subject matter jurisdiction over a protest filed by Mission
Essential Personnel, LLC against corrective action
undertaken by the agency as a result of a prior GAO protest
because Mission Essential's complaint was filed "in
connection with" the issuance of a task order.
The
CBCA did not buy National
Fruit Product Co.'s arguments that its late deliveries
were excused by a stinkbug outbreak, but concluded the
Government had vastly overstated the amount of liquidated
damages that were due. The contractor and the Government each
interpreted the liquidated damages provision in an equally
preposterous manner: the contractor claimed only $33.53 were
due, and the Government had assessed more than $500,000. The
Board concluded that the proper interpretation of the clause
resulted in an assessment of $9,650.
|
| March
28 |
The GAO
sustained a protest by Y&K
Maintenance, Inc., because the agency did not evaluate the
protester's key personnel in accordance with the
solicitation's stated evaluation criteria.
|
| March
27 |
Effective
April 26, NASA is adopting, without change, a final rule amending the
NASA
FAR Supplement (NFS) to update the "Award Fee for Service Contracts" clause
(NFS 1852.216–76) in order to clarify that the amount of award fee held in reserve, if
any, shall not exceed $100,000 for the contract, and add similar language to
the "Award Fee for End-Item Contracts" clause (NFS 1852.216–77)
to allow the Contracting Officer to hold in reserve fee
payments at a not-to-exceed amount of $100,000 in order to protect the Government’s interests
relative to an orderly and timely closeout of the contract.
In InGenesis,
Inc., a bid protest based on the plaintiff's disagreement
with a NAICS decision
by the SBA's OHA, the Court of Federal Claims, like the OHA
before it, upheld the Contracting Officer's choice of NAICS
code 621111 (Physician's Services) as opposed to 622110 for
the solicitation at issue.
In
Maggie's
Landscaping, Inc., the ASBCA denied an EAJA application,
in part because the Government's litigation position, though
incorrect, was substantially justified and also because it was
the Board, on its own initiative, which had to search the
record to come up with evidence to support one of the
contractor's original claims.
In Weigel Hochdrucktechnik
GmbH & Co. KG, which involved a contract performed in
Spain, the ASBCA (i) held that the Government had failed to
prove that the water testing it required the contractor to
perform was required by either the contract or Spanish law and
(ii) denied the contractor's claim for waterproofing certain
containers because the Government merely acquiesced in
contractor's (ultimately unsuccessful) suggested method for
doing so, without waiving the contract requirement that they
be waterproof.
|
| March
26 |
Numerous
corrections have been issued to the original Federal Register
pages (see March 2 entry below) concerning the changes
to FAR Part 52 related to FAR
Case 2010-015 (Women-Owned Small Business (WOSB) Program)
and FAR
Case 2011-030 (New Designated Country (Armenia) and other
Trade Agreements Updates).
In
NAICS
Appeal of Hummingbird Solutions, the SBA's OHA
dismissed, as untimely, a NAICS appeal filed more than 10 days
after issuance of the solicitation.
|
| March
25 |
I've
fixed quite a few broken links to Federal Circuit decisions
(and have corrected a few additional citations) on the Winstar
decisions page.
|
| March
23 |
In
Crosstown
Courier Service, Inc., the GAO held that the VA violated
the requirement of the Veterans Benefits, Health Care, and Information Technology Act of 2006
by issuing an FSS acquisition without having first determined
whether two or more SDVOSBs could meet the agency's
requirements at a reasonable price.
|
| March
22 |
In Boston
Harbor Development Partners, LLC, the Court of Federal
Claims held that the protester lacked standing because its
complaint (that a lease should be terminated to allow the
procuring agency to complete corrective action in response to
a prior protest without possible bias towards the current
awardee in the reevaluation) was purely speculative.
In
Contracting
Consulting Engineering LLC, the court included a good
discussion of the standards for permitting supplementation of
the administrative record and (tongue-in-cheek, I hope, since
it works so well on that level) responded to the plaintiff's
proffer of a set of procurement regulations:
Defendant is correct that Army regulations are legal authorities and not a matter for
supplementation. They can be cited as authorities in plaintiff’s brief, and the court will
regard them as authorities in support of plaintiff’s moving brief. The court is grateful
nonetheless that plaintiff provided the court with a copy of the 700 pages of regulations.
Leaving
the effective date to be announced in the future, the State
Department has issued a final rule that will (i) amend the
ITAR to implement the Defense Trade Cooperation Treaty
between the United States and the United Kingdom and (ii) identify
(via a supplement) the defense articles and defense services that may not be
exported pursuant to the Treaty.
|
| March
21 |
The GAO
sustained a protest by Sea
Box, Inc., and held that (i) the failure of the
protester's quotation in response to an RFQ to include the
90-day acceptance period stated in the solicitation did not
render it unacceptable because quotations are not offers, and
(ii) the awardee's failure to comply with the RFQ's
requirements to submit technical information concerning its
quotation meant the record did not support the agency's
decision that its quotation was acceptable.
In Size
Appeal of Fuel Cell Energy, Inc., the SBA's OHA held
that (i) the Area Office correctly dismissed a protest as
insufficiently specific, and (ii) allegations regarding an
alleged violation of the ostensible subcontractor rule raised
for first time on appeal would not be considered.
In Matter
of RUSH-LINK ONE Joint Venture, the OHA upheld the
determination that the protested firm was not a properly
constituted SDVOSB joint venture because (i) the SDV did not
(a) own and control the SDVOSB member (having received
commercially irregular loans from the minority owners) or (b)
control the board of directors of the joint venture; and (ii)
the proposed project manager for the contract at issue was not
an employee of the SDVOSB.
|
| March
20 |
The ASBCA
has published four decisions denying various motions for
summary judgment and for reconsideration, which you can find here.
|
| March
19 |
In
denying Veleta
Corp.'s claim under the "Changes" clause,
the CBCA held that the contractor failed to present any
evidence of either (i) work beyond that required by the
specifications specs or (ii) increased costs caused by this
allegedly extra work.
In Walsh/Davis
Joint Venture, the CBCA held that an unambiguous sentence
in various contract modifications barred the contractor from
passing through its construction subcontractor's subsequent
claims for cumulative labor inefficiencies.
|
| March
18 |
In
Communication
Construction Services, the Court of Federal Claims ordered
additional briefing on the issues of what type of (i) record
(standard administrative record or something broader) and (ii)
procedural vehicle (cross motions (a) for judgment on the
administrative record or (b) for summary judgment) are to be
used in the relatively rare bid protests brought under 28
U.S.C. 1491(a) (for breach of the implied contract of fair
dealing) as opposed to the more common 1491(b) protests.
The same
court dismissed two contract claims for lack of subject matter
jurisdiction.
In L-3
Services, Inc., Aerospace Electronics Division, the court
noted it lacked jurisdiction over claims under maritime
contracts and that allegations of violations of the FAR and
the Antideficiency Act were not sufficient to establish
jurisdiction.
In
Township
of Saddle Brook, the court dismissed a claim based on an
implied-in-fact contract (because the allegations in the
complaint were not adequate to establish either the mutual
intent to contract or an exchange of consideration) and held
there is no jurisdiction in the court over claims for
promissory estoppel.
|
| March
16 |
Aldevra
won its GAO protest because the VA failed to consider
whether the FSS acquisition should have been set aside for SDVOSBs.
Proposed
rule changes would amend HUD's
acquisition regulation (HUDAR) to (i) remove provisions that are now
obsolete, (ii) refine provisions for approving requests for deviation from the HUDAR,
(iii) update provisions that address the organizational structure of HUD, and
(iv) add provisions on contractor record retention. Comments
are due by May 15.
|
| March
15 |
Digital
Technologies won its GAO protest because the price
realism analysis lacked a rational basis: the agency failed to
follow the solicitation's clear requirement to consider the
proposed prices of all offerors in determining whether
the protester's price was realistic.
|
| March
14 |
The GAO
sustained a protest by ERIE
Strayer Co. because the agency conducted discussions only
with the awardee and downgraded the protester's proposal in an
area concerning which the agency could have, but did not,
request clarifications.
In
Solute
Consulting, the Court of Federal Claims held it lacked
jurisdiction over a post-award protest of an agency's
evaluation of task order proposals (and rejected the
protester's definition of the term "scope" in its attempt
to fit its protest into the exception for protests of task
order awards beyond the scope of the underlying contracts).
|
| March
13 |
In
Mission
Critical Solutions, the Court of Federal Claims denied the
plaintiff's claim that the agency had violated the court's
injunction against a contract award because (i) the new award
was not for the same contract covered by the injunction, and
(ii) the Government had a good faith basis to interpret the
injunction as applying only to the initial procurement, given
significant intervening changes in the applicable statute
occurring after the date of that procurement.
In
Contracting
Consulting Engineering LLC, the court denied the
protester's motion for a preliminary injunction in a
post-award protest even though the protester raised
"troubling" allegations concerning the agency's
evaluations of the experience of the awardee's and protester's
key employees (but still set a briefing schedule for a
decision on a permanent injunction).
In
JRS
Management, the CBCA dismissed an appeal for lack of
jurisdiction (no contract) because the contractor had
responded to a government order for services by announcing it
was substituting a different individual from the one specified
in the order, thus making a counteroffer the Government then
rejected.
In Bannum,
Inc., the CBCA dismissed an appeal involving a claim
barred by the CDA's six-year statute of limitations because it
was filed more than six years after it originally accrued.
|
| March
12 |
The SBA's
OHA has published several decisions.
In Matter
of HANA-JV, the OHA affirmed a finding that a JV
failed to meet multiple requirements at 13 C.F.R. 125.15 for
qualified SDVOSB JVs, including the requirement to designate
an SDVO SBC as the managing venturer of the joint venture.
In Size
Appeal of Advent Environmental, Inc., the OHA affirmed
the Area Office's finding of affiliation through common
ownership and control and held that, pursuant to 13 C.F.R.
121.103(c)(2), one of the four owners of 25% shares in a
company (who also served on its board of managers) had the
power to control it and was not merely a passive investor.
In Size
Appeal of BR Construction, LLC, the OHA held that an
appellant was barred by the doctrine of issue preclusion from
raising the same issues decided against it in an earlier
appeal.
DFARS
Case 2011-D041: A final rule amends the DFARS (i) to require higher-level approval for
commercial item determinations for acquisitions exceeding $1 million when
the determination is based on "of a type" or
"offered for sale" language contained in the definition of
commercial item and (ii) to clarify approval requirements for determinations for acquisitions of
services exceeding $1 million, which utilize Part 12 procedures
but which do not meet the definition of "commercial item."
DFARS
Case 2012-D006: A proposed rule would revise the DFARS clause at
252.225–7040 ("Contractor Personnel Authorized to Accompany
U.S. Armed Forces Deployed Outside the United States" to expand coverage
on contractor requirements and responsibilities regarding alleged crimes
by or against contractor personnel to apply to contingency operations, humanitarian
or peacekeeping operations, or other military operations when the latter are
designated by the combatant commander at any location
worldwide (these requirements currently apply only to DoD contracts
performed in Iraq and Afghanistan). Expanding the coverage worldwide will
provide contractors the guidance they need to take actions if such alleged
offenses occur. Comments are due by May 11.
In Joyce
Terry d/b/a Shirt Shack, the Court of Federal Claims
dismissed (i) a discrimination claim for lack of jurisdiction,
(ii) a promissory estoppel claim because it was based on
a contract implied in law, for which the Government has not
waived sovereign immunity, and (iii) breach claims for failure
to allege facts that establish any breach.
|
| March
9 |
Numerous corrections
have been issued to the original publications of the final
rules related to (i) FAR Case 2010-015 (Women-Owned Small
Business (WOSB) Program) and (ii) FAR Case 2011-030 (New Designated Country
(Armenia) and Other Trade Agreements Updates).
See March 2 entry below for the original publications.
|
| March
7 |
FAC
2005-56 has been published and includes only the following
item:
FAR
Case 2012-004 ("United States-Korea Free Trade
Agreement"): Effective March 15, an interim rule amends
FAR Part 25 (and corresponding clauses in Part 52) to implement the
United States-Korea Free Trade Agreement (see the United States-Korea
Free Trade Agreement Implementation Act (Pub. L. 112–41) (19 U.S.C. 3805
note)). Comments are due by May 7.
|
| March
4 |
In M.E.S.,
Inc., the ASBCA decided several claims by a construction
contractor for alleged changes and compensable delays
(including claims for extended field and home office
overheads) opposed by various government defenses, including
the sovereign acts doctrine, concurrent delays, and lack of
proof of quantum.
In Delta
Industries, Inc., the ASBCA held that a purchase order was
an offer that lapsed when Delta failed to deliver within the
required time.
|
| March
3 |
The award
for zaniest judicial reasoning of the year goes to the Court
of Appeals for the Federal Circuit's majority opinion in The
Minesen Co. v. McHugh, enforcing a provision in the
"Disputes" clause of a NAFI contract that stated the
ASBCA's decision on any appeal would be final and
unreviewable. Following are just a few of the lapses in logic
that permeate the opinion.
First, the
court declines to rule whether (post Slattery v. United States, 635 F.3d 1298 (Fed. Cir. 2011))
the CDA even applies to NAFI contracts, but then proceeds to
base its decision largely on its interpretation of the
CDA.
Secondly,
the court repeatedly refers to the parties' 'mutual agreement'
in the contract that the ASBCA's decision would be final, as
if a government contractor ever has a say in the language of a
"Disputes" clause.
Third, the
court tries to avoid the clear language of 41 U.S.C 7107(1)
(which specifically provides that "[t]he decision of an agency
board is final, except that . . . a contractor may appeal the decision
to the United States Court of Appeals for the Federal Circuit within 120 days from the
date the contractor receives a copy of the decision. . .
.") by noting that the provision does not state it cannot
be waived, while 41 U.S.C. 7104 (which the court suggests is
the analogous provision that applies to disputes at the Court
of Federal Claims) can be. The latter provision states that a
contract provision may not waive the contractor's option to
appeal a Contracting Officer's decision to the Court of
Federal Claims--it says nothing at all about whether the
parties could agree that the decision of the Court of Federal
Claims would be unreviewable. In fact, nothing in the CDA,
itself, states that a decision of the Court of Federal Claims
can be appealed to the Court of Appeals for the Federal
Circuit. So, the court disregards the only language in the CDA
that gives contractor the right to appeal to the court
(without qualification).
Finally,
the court includes several passages from the legislative
history of the CDA that allegedly support its position, not
one of which really does. Here is an example:
Nor does anything in the CDA’s legislative history
demonstrate that Congress did not intend for parties to be able to
agree to the finality of ASBCA decisions. On the contrary, Congress recognized first among the express
purposes of the CDA “induc[ing] resolution of more contract disputes
by negotiation prior to litigation,” S. Rep. No. 95-1118, at
1 (1978), and “encourag[ing] the informal, quick resolution of disputes before they can develop into
expensive and time-consuming administrative tangles or
litigation,” 124 Cong. Rec. 31,645 (1978).
[Emphases added]
Those
statements reflect one aim of the CDA: to encourage resolution
of claims before they are appealed to either a board or the
Court of Federal Claims. They say nothing about whether the
parties may agree a board's decision will be final and
unreviewable.
There
probably was a way to reach the same result using logic--the
court opted for gibberish.
|
| March
2 |
In Size
Appeal of Hummingbird Data Systems, LLC, the SBA's OHA
held that the Area Office was correct in dismissing a size
protest because the protester had been eliminated from the
competition for reasons unrelated to size and, therefore,
lacked standing.
Federal
Acquisition Circular (FAC) 2005-56
has been published and includes the following seven items plus
technical amendments:
FAR
Case 2010-015 ("Women-Owned Small Business (WOSB)
Program"): Effective April 2, a final rule adopts, with
changes, the interim rule amending the FAR to implement the
SBA's regulations establishing the WOSB program, specifically
to authorize the restriction of competition for federal contracts in certain
industries to economically disadvantaged women-owned small business
(EDWOSB) concerns or WOSB concerns eligible under the WOSB
program.
FAR
Case 2008-030 ("Proper Use and Management of
Cost-Reimbursement Contracts"): Also effective April 2, a
final rule adopts, with changes, the interim rule amending the
FAR to implement a section of the Duncan Hunter National Defense Authorization
Act for Fiscal Year 2009 that addresses the use and management of cost-reimbursement
contracts, including ensuring that a properly certified and
trained Contracting Officer's Representative (COR) be
appointed to assist the Contracting Officer in the
administration of such contracts, unless agency procedures
require the Contracting Officer to perform all such duties. FAR
Case 2007-012 ("Requirements for Acquisitions
Pursuant to Multiple-award Contracts"): Effective April
2, a final rule adopts, with changes, the interim rule
amending the FAR to implement a section of the Duncan Hunter National Defense Authorization
Act for Fiscal Year 2009 to enhance competition in the purchase of supplies
and services by all executive agencies under multiple-award contracts.
Specifically, the threshold amount in FAR 8.405-3(a)(7)(v) is
changed to read $103 million, and the following language has
been added as FAR 8.405-3(c)(3): "‘The ordering activity is responsible for
considering the level of effort and the mix of labor proposed to perform a
specific task being ordered, and for determining that the total price is
reasonable through appropriate analysis techniques, and documenting the file
accordingly."
FAR
Case 2011-004 ("Socioeconomic Program
Parity"): Effective April 2, a final rule adopts, with
changes, the interim rule amending the FAR to implement a section of the Small
Business Jobs Act of 2010 that clarifies that there is no order of
precedence among the small business socioeconomic contracting
programs and that contracting officers may exercise discretion when determining whether
an acquisition will be restricted to small businesses participating in the 8(a)
Business Development Program (8(a)), Historically Underutilized Business
Zones (HUBZone) Program, Service-Disabled Veteran-Owned Small Business (SDVOSB) Program, or the
WOSB Program.
FAR
Case 2012-002 ("Trade Agreements
Thresholds"): Effective today, a final rule amends the
FAR to incorporate adjusted thresholds for application of the World Trade
Organization Government Procurement Agreement and the Free Trade
Agreements, as determined by the United States Trade Representative.
FAR
Case 2011-030 ("New Designated Country
(Armenia) and Other Trade Agreements Updates"): Effective
today, a final rule amends the FAR (i) to add Armenia as a designated country,
due to the accession of Armenia to membership in the World Trade
Organization Government Procurement Agreement and (ii) to
update the lists of countries that are parties to the Agreement on Trade in Civil
Aircraft.
FAR
Case 2010-009 ("Government Property"): Effective
April 2, a final rule amends the FAR to clarify requirements
concerning reporting, reutilization, and disposal of
government property, by, inter alia, (i) adding a definition of
"surplus property" at FAR 2.101; (ii) defining
"loss of Government property" at FAR 45.101; (iii)
using the term "loss" consistently in lieu of
"loss, damage, destruction, or theft"; (iv)
clarifying, and distinguished among, the responsibilities and authorities of
the contracting officer, property administrator, plant clearance officer,
and contractor; (v) reorganized and clarifying procedures and responsibilities for
disposal of government property (see FAR subpart 45.6); and
(vi) clarifying and updating the government property clause at FAR
52.245–1 to conform with revisions to FAR part 45.
The
Department of Energy has extended (to March 16) the period for
providing comments
in response to its proposed rule to revise existing regulations covering contractor legal
management requirements and make conforming amendments to the Department of Energy Acquisition
Regulation (DEAR) (76 FR 81408).
The Court
of Federal Claims published two decisions concerning
government motions to dismiss various aspects of claims for
alleged government breaches of a settlement agreement (Kenney
Orthopedic) and non-disclosure and CRADA agreements (Demodulation,
Inc.).
|
| February
29 |
In Muhtesem
Co., the ASBCA granted the Government's motion to dismiss
(for lack of jurisdiction) the following elements of damages
claimed to result from Government's late final payment under a
contract: interest on borrowing; loss of reputation; and loss
of anticipatory profits on other business opportunities.
In Southern
Defense Systems, Inc., the ASBCA held that the contractor
was not entitled to receive the same (higher) pass-through
mark-up on a particular delivery order as stated in the basic
contract (rather than the lower rate negotiated for the
delivery order) because the contractor did not demonstrate
there was a patent or latent ambiguity, a violation of the
FAR, a mistake, or bad faith, coercion, or misrepresentation
by the Government.
In Hartman
Walsh Painting Co., the Board denied the contractor's
claim for extra work on a painting contract and held that the
Government's approval of one of the contractor's submittals
did not preclude the Government from later enforcing
compliance with specification.
|
| February
25 |
The GAO
has published two more decisions sustaining protests.
In
InfraMap
Corp., the GAO held that the agency's estimate of future
underground utility relocation work in a solicitation lacked a
rational basis and likely was significantly understated.
In Wisconsin
Physician Service Insurance Corp. (which was originally
decided in May 2009), the GAO found flaws in the cost realism,
technical, and past performance evaluations, as well as a lack
of meaningful discussions regarding the protester's past
performance.
|
| February
24 |
In
Furniture
by Thurston, the Court of Federal Claims held that,
although the protester demonstrated that the winning offer
failed to comply with a material requirement of the
solicitation, the protester's remedy was limited to the
recovery of bid and proposal costs because the contract at
issue already had been substantially performed. (The court
also held that the protester's reorganization in bankruptcy
did not affect its standing to protest.)
In
Side
Bar and Assocs., the CBCA held that the Contracting
Officer's belated issuance of a decision on a a claim that
already had been properly appealed to the Board from a deemed
denial could not affect the Board's jurisdiction over the
entire appeal.
In Lawrence
Jackson, the CBCA dismissed an appeal (with prejudice) for
failure to prosecute after the appellant repeatedly ignored
the Board's orders to file a Complaint or to designate its
notice of appeal as its Complaint.
DFARS
Case 2011-D033: DoD is adopting as final, without change,
an interim rule amending the DFARS (i) to implement those sections of
the National Defense Authorization Acts for Fiscal Years 2010 and 2011,
providing increased authorities to reduce or deny award fees to companies
found to jeopardize the health or safety of Government
personnel and (ii) to modify the requirement that information on the final determination
of award fee be entered into the Federal Awardee Performance and Integrity
Information System (FAPIIS).
DFARS
Case 2009-D038: DoD is adopting as final, with changes, an
interim rule amending the DFARS to improve the effectiveness of DoD oversight of
contractor business systems.
DFARS
Case 2012-D024: DoD is amending the DFARS to extend the date for submittal of
applications under the DoD Mentor-Protégé Pilot Program for new mentor-protégé agreements
to September 30, 2015 and the date mentors may incur costs and/or receive
credit towards fulfilling their small business subcontracting goals through
an approved mentor-protégé agreement to September 30, 2018.
DFARS
Case 2012-D026: DoD is amending the DFARS extend the program period for the DoD
Test Program for Negotiation of Comprehensive Small Business Subcontracting
Plans through December 31, 2014.
DoD's
Per Diem, Travel and Transportation Allowance Committee has
published Civilian Personnel Per Diem
Bulletin Number 280, which lists revisions in the per diem rates
prescribed for U.S. Government employees for official travel in Alaska,
Hawaii, Puerto Rico, the Northern Mariana Islands and Possessions of the
United States.
In
a Memorandum of February 21, 2012, the President has directed
federal agencies to take various steps to increase federal
government procurement of biobased
and sustainable products.
Effective
March 26, the SBA is increasing the small business size standards for 22 industries in
NAICS Sector 48–49, Transportation and
Warehousing, while retaining the current standards for the
remaining 37 industries in that Sector.
SBA
is proposing to increase small business size standards for 28 industries in
NAICS Sector 62, Health Care and Social
Assistance. Comments are due by April 24.
Effective
March 26, the GSA is amending its acquisition regulation (the
GSAR) to modify acquisition-related
thresholds as follows: (i) the GSAR clause at 552.219–71, Notice to
Offerors of Subcontracting Plan Requirements, is revised by removing
"$500,000" and "$1,000,000" and replacing the GSAR text with
"$650,000" and "$1,500,000," respectively;
and (ii) the GSAR clause at 552.219–72, Preparation, Submission,
and Negotiation of Subcontracting Plans, is revised by removing
"$500,000" and "$1,000,000" and replacing the GSAR text with
"$650,000" and "$1,500,000," respectively.
The Department of the
Treasury is proposing to amend its acquisition regulation (DTAR) to implement use of
the Internet
Payment Platform, a centralized electronic invoicing and payment information system, and to
change the definition of bureau to reflect the consolidation on July 21,
2011 of the Office of Thrift Supervision with the Office of the Comptroller of
the Currency. Comments are due by April 23.
|
| February
23 |
The Court
of Federal Claims' latest opinion in the GTA
Containers, Inc., post-award protest replaces its prior
decision but just amplifies on the reasoning in the prior
case and reaches same result in favor of the protester. See
February 7 entry below.
In Diversified
Maintenance Systems, Inc., the court (i) rejected a
contractor's argument that the court had jurisdiction over its
claim for breach of contract monetary damages under 28 U.S.C.
1491(b) (because such bid protest jurisdiction does not cover
claims by contractors involving contract administration after
a contract has been awarded) and then (ii) dismissed the suit
for lack of jurisdiction because the contractor did not
first submit a certified claim to Contracting Officer, as
required by the CDA.
|
| February
22 |
FAR Case
2011-011: A proposed rule would amend the FAR to implement the requirements of the
James Zadroga 9/11 Health and Compensation Act of 2010 regarding the
imposition of a 2 percent tax on certain
foreign procurements. Comments are due by April 23.
In Pacific
Gas & Electric Co., a spent nuclear fuel case, the
Court of Appeals for the Federal Circuit affirmed the damages
award by the Court of Federal Claims in a prior
decision favor of the plaintiff.
|
| February
16 |
Somebody
must have slipped some happy juice into the GAO's punchbowl
because all three of the decisions it published yesterday
sustained protests.
In Standard
Communications, Inc., the GAO found the agency treated the
eventual awardee and the protester differently by permitting
only the former to make material changes in its quotation,
which rendered its technically unacceptable quote acceptable.
In ITT
Systems Corp., the GAO could not locate any explanation in
the record for apparent discrepancies (and the lack of a
logical connection) between the results of the cost and
technical evaluations.
In the
long-delayed, published version of its decision in IBM
Global Business Services, B-404498, .2 (Feb. 23, 2011),
the GAO concluded that the agency had rewarded the awardee's
proposal on the basis of an unstated evaluation criterion and
that the agency had misled offerors by evaluating on basis of
much different quantities than those suggested in the
solicitation.
The SBA's
OHA has published several size decisions.
In Size
Appeal of Nuclear Fuel Services, Inc. , the OHA
reversed the Area Office and held that (i) the "present
effect" rule did not require a finding of affiliation
where discussions between two firms concerning merger or
acquisition had not reached the status of an agreement in
principle at the time of self-certification (although
agreement was reached very shortly thereafter) and (ii) the
NAICS code under which size should have been assessed was the
one the prime contractor had assigned to the RFP in question
rather than the NAICS code for the contested firm's primary
industry.
In Size
Appeal of Tyler Construction Group, the OHA affirmed
the Area Office's dismissal of an untimely protest against a
firm's size status for task order award where the Contracting
Officer had not requested recertification in connection with
the award.
In Size
Appeal of Santa Fe Protective Services, Inc., the OHA
affirmed the Area Office's finding that a firm did not run
afoul of the ostensible subcontractor rule because it would be
providing the large majority of what the Area Office had
determined were the primary requirements of the solicitation,
even though that area of work barely qualified as the primary
requirement.
|
| February
15 |
In TriCenturion,
Inc.; SafeGuard Services, LLC, the GAO concluded that the
cost realism, technical, and past performance evaluations all
were insufficiently documented in the record to uphold the
agency's award decision.
Effective
March 15, USAID is amending the USAID Acquisitions Regulations
(AIDAR) to implement a pilot program for a Partner
Vetting System for USAID assistance and acquisition awards,
the purpose of which is to help ensure that USAID funds and other
resources do not inadvertently benefit individuals or entities that are terrorists,
supporters of terrorists or affiliated with terrorists, while also minimizing the
impact on USAID's programs and its implementing partners.
Effective
February 29, EPA will amend the prescription in the EPAAR for
the work
assignment clause in order to provide clearer and more
detailed instructions for the use of the clause.
|
| February
14 |
The ASBCA
published several decisions, including the following:
In Space
Gateway Support, LLC, the ASBCA held that (i) the costs of
accrued sick leave hours paid to employees in cash at the termination of
their employment in accordance with the terms of applicable
collective bargaining agreements were allowable fringe
benefits under FAR 31.205-6, and (ii) the Government's
contrary interpretation of the contract would have required a
deviation from the FAR that the agency had not obtained.
In ACR
Machine, Inc., the ASBCA held that a contractor's email to
the Contracting Officer requesting an extension of 120 days to
a purchase order was a " request for an adjustment in contract terms"
under the definition of a "claim" in the
"Disputes" clause (FAR 52-233.1) and, thus,
was a claim under the CDA.
In General
Dynamics Ordnance and Tactical Systems, Inc. (a dispute
involving unanticipated costs associated with the Government's
allegedly inadequate estimates concerning ammunition
quantities required by the contract), the ASBCA held that the
Government's willful failure to comply with the Board's orders
to turn over documents to the contractor during discovery
merited the sanction of an adverse inference that the
documents, i f disclosed, would have shown that there was relevant
information available to the Government that it failed to consider when developing the estimates
in question, thereby causing the estimates to be inadequately or negligently
prepared.
|
| February
11 |
The GAO
has adopted the FAR's debarment
and suspension procedures.
The GAO
sustained a protest by MANCON
because the acceptability of the offeror's small business
subcontracting plan should have been a responsibility issue,
not a pass/fail reason for evaluating the proposal as
technically unacceptable.
|
| February
10 |
Effective
March 12, the SBA is (i) increasing 37 small business size
standards for 34 industries and three sub-industries ("exceptions" in SBA’s table of small business size standards) in NAICS
Sector 54 (Professional, Technical, and Scientific
Services), (ii) retaining the current standards for the
remaining industries in NAICS Sector 54, (iii) increasing one
size standard in NAICS Sector 81 (Other Services), and (iv)
removing "Map Drafting" as the "exception"
to NAICS 541340 (Drafting Services).
In Hillcrest
Aircraft Co., the CBCA denied the contractor's claim for
reimbursement of federal excise taxes in a contract containing
the unique commercial item tax clause at FAR 52.212-4(k).
In Whiteriver
Construction, Inc., the CBCA held that a letter submitted
to Contracting Officer labeled as "final certified
claim" and including a CDA certification (submitted to
correct a prior letter that did not include a certification)
constituted a CDA claim even though it did not specifically
request a decision.
In TKC
Aerospace, Inc., the CBCA interpreted the contract as
making the contractor responsible for the costs of repairing
corrosion in an aircraft it was leasing to the Government and
for the costs of "downtime" during such repairs.
|
| February
9 |
In
J.F.
Taylor, Inc., the ASBCA determined that the executive
compensation paid by a contractor was reasonable because the
DCAA's method for challenging that compensation suffered from
unrebutted statistical flaws.
In Lan-Cay,
Inc., the ASBCA upheld a termination for default,
rejecting the contractor's contentions that the Government had
(i) wrongfully withheld progress payments and (ii) audited and
inspected the contractor's work excessively.
|
| February
7 |
In GTA
Containers, Inc., the Court of Federal Claims issued a
permanent injunction against performance of a delivery order
based on the fact that the awardee's submission to the SBA for
purposes of a post-award size determination indicated the
awardee did not really intend to subcontract with a firm it
had identified in its bid as a subcontractor, a representation
the agency's evaluators had relied on in favorably evaluating
the awardee's proposal. Also interesting is the court's
refusal to acquiesce in the corrective action undertaken
voluntarily by the procuring agency during the pendancy of the
protest, i.e., terminating all but what the agency
regarded as the essential portions of the original delivery
order.
In
Size Appeal of
DoverStaffing, Inc., the SBA's OHA affirmed the Area
Office's finding of affiliation under the ostensible
subcontractor rule due to unusual reliance on a subcontractor
because, inter alia, the protested firm intended to
hire its key employees from the sub and relied almost entirely
on the sub's past performance for the past experience part of
the proposal.
|
| February
5 |
In
Sharp
Electronics Corp., the CBCA held that a purchase order
provision establishing a cancellation charge if the Government
did not extend a 48-month, lease-to-own term beyond the first
12-month period was valid and enforceable against the
Government.
|
| February
3 |
In
its latest CRAssociates
decision, the Court of Federal Claims denied the protester's
request for a stay pending its appeal of the court's prior
decision denying the protest (see January 24 entry
below).
In
a final rule effective today, the Department of Commerce's
Bureau of Industry and Security (BIS) has amended the Export
Administration Regulations (EAR) to add a reference to the Iran
Sanctions Act of 1996 (ISA), which states BIS’s licensing policy for export
and reexport transactions that involve persons sanctioned pursuant to certain
enumerated statutes, including its general policy of denying export and
reexport license applications in which a person sanctioned by the State
Department under the ISA is a party to the transaction.
|
| February
1 |
In an
interesting reverse twist on the typical mistake-in-bid case,
the Court of Federal Claims held, in the Virgin
Islands Paving bid protest, that the agency lacked a
rational, post-award, basis to reject the awardee's bid (and
then award to the second-low bidder) on the basis of
"mistakes" in the awardee's bid after the agency
originally had determined (preaward) that neither the
awardee's nor the second-low bidder's bids were mistaken, in
part because they were comparable to one another.
DoD's
e Per Diem, Travel and Transportation Allowance Committee has
published Civilian Personnel Per Diem
Bulletin Number 279, which lists revisions in the per diem rates
prescribed for U.S. Government employees for official travel in Alaska,
Hawaii, Puerto Rico, the Northern Mariana Islands and Possessions of the
United States.
|
| January
29 |
DFARS
2010-D011: DoD is publishing a final rule, effective
January 30, requiring "major contractors" (i.e.,
those whose covered segments allocated a total of more than $11,000,000 in IR&D/Bid and Proposal
(B&P) costs to covered contracts during the preceding fiscal year)
to report IR&D projects to the Defense Technical Information
Center (DTIC) using the DTIC’s on-line input form and instructions at
this site.
DFARS
2011-D057: Another final rule, also effective January 30,
amends the DFARS to add Armenia as a World Trade Organization Government
Procurement Agreement country and a designated country, due to the accession of Armenia to
membership in the World Trade Organization Government Procurement
Agreement.
DFARS
Case 2012-D005: DoD is amending the DFARS to to incorporate adjusted
thresholds for application of the World Trade Organization Government
Procurement Agreement and the Free Trade Agreements, as determined by the
United States Trade Representative. Additionally, this rule includes
language in prescriptions for use of contract clauses intended to clarify their
applicability to commercial items.
DFARS
Case 2011-D045: DoD proposes to amend the FAR to provide detailed guidance and
instructions on the use of the performance-based payments analysis
tool. Comments are due by March 30.
DFARS
Case 2011-D052: DoD is proposing to amend the FAR to update the form used by contractors to
request shipping instructions and the associated contract clause and clause
prescription to cover both commercial and Government bills of lading, and to
relocate the coverage within the DFARS. Comments are due by
March 30.
|
| January
28 |
In The
DIRECTV Group, the Court of Appeals for the Federal
Circuit affirmed the Court of Federal Claims' decision
concerning the appropriate segment closing adjustments under
CAS 413 when the sale of two segments involved the transfer of
defined benefit pension plans.
In Travelers
Casualty & Security Co. of America, the Court of
Federal Claims held that, given the Anti-Assignment Act, a
general liability insurer (as opposed to a surety) does
not have standing to sue Government for breach of contract to
recover amounts it paid to its insured, even under a theory of
equitable subrogation.
In
Simulation
Technology, a CDA jurisdictional decision, the court
dismissed an excusable delay claim that was not sufficiently
similar to the claim that had been previously presented to the
Contracting Officer to have put him on notice of it.
In
Parsons-UXB,
Joint Venture, the ASBCA granted the contractor's motion
to exclude an export report and testimony based on that report
because nothing in the proffered evidence required expert
testimony: "[The proffered] opinion is not based upon any
'scientific, technical, or other specialized knowledge' and does not
'help the trier of fact.' None of the facts described by [the
proffered expert] require any expertise to decide them. All of them
are within our competence to determine as the trier of fact.
Accordingly, his opinion about them is of no help. Additionally,
[the proffered expert's] opinion of the meaning of the word
'foreseeable' relates to an issue of law, and in particular attempts to interpret
specialized legal terminology."
In Singleton
Enterprises, the CBCA denied a post-award unilateral
mistake-in-bid claim due to a lack of evidence in two
areas: (i) what the bid would have been absent the
alleged mistake; and (ii) that government knew, or should have
known, of the mistake prior to award.
In Rafael
Portillo, the CBCA held that the Government complied with
an unambiguous lease provision that permitted it to terminate
a lease with 60-days advance notice.
In Dr.
Lewis J. Goldfine , the CBCA dismissed (for lack of CDA
jurisdiction) a claim for money damages that had not first
been submitted to the Contracting Officer for a decision and a
claim for cancellation of a BPA (because a BPA is not a
contract) even though the BPA repeatedly referred to itself as
a contract: "The fact that the BPA which SSA issued to Dr. Goldfine calls itself a contract brings to mind a quotation attributed to
President Lincoln: 'If you call a tail a leg, how many legs does a dog have? Four. Calling
a tail a leg doesn’t make it a leg.' "
The SBA's
OHA has published several decisions--
In Matter
of Major Contracting Services, the OHA affirmed the
dismissal of an untimely protest of a firm's SDVOSB status
because the time period to protest started from the day notice
was received by email at 4:43 p.m., which was prior to the 5
p.m. close of business.
In Size
Appeal of Trident3, LLC, the OHA overturned
the Area Office's size determination because an 8(a) firm's
joint venture agreement was approved prior to the award of an
8(a) contract and Area Office lacked the authority to review
the underlying, approved mentor-protégé agreement in context
of an 8(a) procurement.
In SP
Technologies, LLC, the OHA overturned the Area
Office's finding of affiliation through identify of interest
because there was a clear fracture between the allegedly
affiliated firms, and the individual with the alleged identity
of interest was only a minority shareholder who did not
control the allegedly related firm.
In Alutiiq
Diversified Services, LLC, the OHA held that, where the
parties to an approved mentor-protégé agreement also had an approved
JV agreement for a particular procurement, the Area Office's decision
that it did not have the authority to examine whether the members of
the joint venture had formed too many such ventures together over the
years was correct (because the SBA already had determined that the JV
was approved for this particular procurement).
|
| January
27 |
The GAO
published two decisions sustaining protests.
In SeKON
Enterprise, Inc.; Signature Consulting Group, the GAO
found a lack of meaningful discussions because, based on
an incomplete analysis of the protester's proposal, the agency
misled the protester during discussions by directing it to
increase its proposed staffing (and thus its costs).
In The
Argos Group, a protest against the terms of a
solicitation, the GAO held that the GSA improperly failed to
include the 10 percent price evaluation preference for HUBZone
small business concerns mandated by the Historically Underutilized Business Zone Act of 1997, 15 U.S.C. § 657a(b)(3)(B),
because the statute applies "in any case in which a contract is to be awarded on the basis of full and open
competition," and (i) the lease that will result from this procurement is a
contract; (ii) the agency is using full and open competition to award the contract; and
(iii) there is no language in the statute suggesting that an exception is applicable for GSA lease
procurements.
|
| January
26 |
In
The
Boeing Co., the ASBCA dismissed a government claim against
the contractor (for increased costs allegedly incurred by the
Government as a result of a voluntary change in the
contractor's accounting system) because the Contracting
Officer's decision asserting the government claim was not
issued within the CDA's six-year statute of limitations (41 U.S.C. §
7103(a)(4)(A), formerly 605(a)). The ASBCA (i) examined
whether any of several recent appeals court (including Supreme
Court) decisions had changed the conclusion that the CDA's is
a jurisdictional statute of limitations and (ii) concluded
they had not.
In Distributed
Solutions, the ASBCA engaged in a good analysis of a
contract interpretation issue and granted partial summary
judgment to the Government because its interpretation of
disputed language in a contract modification was the only
reasonable one and was not in conflict with any other
contractual language.
I've
cleaned up a bunch of broken links on the Statutes
page.
|
| January
25 |
In
Structural
Concepts, the Court of Federal Claims denied cross motions
for partial summary judgment as to the propriety of government
counterclaims for liquidated damages because such damages
cannot not be quantified until after resolution of delay
claims that have been reserved by the parties for trial on the
merits.
In Century
Exploration New Orleans, Inc., And Champion Exploration, LLC,
the court discussed (at length) the evolution of the case law
on the subject before concluding that the contractor was not
prohibited from asserting a Fifth Amendment
"Takings" claim and a breach of contract claim as
alternative theories in the same Complaint.
In South
Fuels, a spent nuclear fuel case, the Court of Appeals for
the Federal Circuit (a) affirmed (i) the CoFC's denial of a claim for
the cost of borrowed funds and (ii) the CoFC's causation analysis and revised
award of nominal damages; and (b) reversed the CoFC's denial of overhead
costs.
|
| January
24 |
In CRAssociates,
the Court of Federal Claims denied a protest asserting
multiple grounds allegedly showing that the agency's second
evaluation after a prior successful bid protest was a mere
pretext to justify re-award to the original awardee:
In seeking to overturn this award, plaintiff attempts to pile a Pelion of conjecture upon
an Ossa of speculation, literally raising dozens of alleged errors in contending that, from the
outset, the Army intended to make a second award to Spectrum. But reminiscent of the Greeks
of old, whose stone pile atop Mt. Olympus failed to reach the heavens, plaintiff ultimately fails
to convince this court that the second set of evaluations performed by the Army was a pretext for
giving the contract to its competitor.
In URS
Federal Services, the court (i) denied the Government's
request to reconsider a prior
decision declaring an agency override of an automatic stay
to have been improvidently issued and (ii) concluded that the
court is not required to use the four-factor test for
injunctive relief when analyzing the merits of an automatic
override for purposes of issuing a declaratory judgment.
In
Ceradyne,
an unsuccessful protest, the court held that the Government's
decision to modify one awardee's contract to add items that
were supposed to have been produced by another contractor that
had defaulted on its companion contract (i) was a type of
modification contemplated by the original solicitation, (ii)
was within the scope of the awardee's contract and (iii) was
not an improper sole source award in violation of CICA. The
court also held that the plaintiff's complaint about the
Government's alleged failure to conduct a proper
responsibility determination should be dismissed as moot
because the same claim was previously settled as part
of a prior GAO bid protest.
In
SUFI
Network Services, the court denied the Government's motion
to dismiss a complaint in a direct appeal to the court from
the Government's failure to issue a decision on the
contractor's claim for attorneys' fees submitted after a prior
successful ASBCA case on the merits (despite the fact that the
1979 version of the "Disputes" clause in this
non-appropriated fund contract only provided for an appeal to
the ASBCA) because the Government breached the
"Disputes" clause by failing to issue a decision on
the contractor's claim within a reasonable time--meaning the
clause was no longer controlling on this issue. I'm not sure I
agree with the reasoning here; perhaps there is a way to reach
the same conclusion that is more compelling.
In
Railway
Logistics International, the court denied the contractor's
$6 million in breach claims (on a contract worth less than
$2.5 million) and granted the Government's counterclaims for
forfeiture under a special plea in fraud based on a contractor
spreadsheet concerning the claim quantum revealed during
discovery. The court left little doubt how it felt about the
spreadsheet and the contractor's claim in general:
RailwayLogistics could not support its claim because of fraud and misrepresentation of fact.
Every item on the spreadsheet that served as plaintiff’s support for its claim was overstated or
imaginary. Contents of the spreadsheet alone provide clear and convincing evidence that RLI
practiced fraud "against the United States in the proof, statement, establishment, or
allowance" of its claim. 28 U.S.C. § 2514.
Trial of this case revealed that defendant’s business relationship with RLI had no redeeming
aspect; it caused a grievous waste of limited resources and hindered the Government’s rebuilding
efforts in Iraq. RLI was in obvious breach of both contracts, yet defendant terminated them for
convenience of the Government. This would have allowed plaintiff to walk away with little or no
cost to itself, yet it sued the Government for millions of dollars on a specious claim, thereby creating
still more waste of valuable time and resources.
The Government limited its counterclaims to the most obvious and outrageously inflated
fraudulent claims. Given that restraint, the category of claims that RLI could not support because
of "misrepresentation of fact or fraud by the
contractor" totaled $1,175,160. See 41 U.S.C. § 7103(c)(2).
. . .
Any amount of RLI’s claim that might have been valid, or could have remained after
applying statutory penalties would be forfeited pursuant to the special plea in fraud. 28 U.S.C. §
2514. Statements contained in the spreadsheet alone support a finding, by clear and convincing
evidence, that plaintiff attempted to practice a fraud
"against the United States in the proof, statement, establishment, or
allowance" of its claims.
In Philip
Emiabata d/b/a/ NOVA EXPRESS, the court held that the
Government properly terminated a Postal Services contract for
default after the contractor failed to provide the Contracting
Officer with proof that it had obtained the contractually-required liability insurance
that would enable it to begin performance.
|
| January
19 |
DFARS
Case 2011-D034: DoD has adopted as final, without change,
an interim rule amending the DFARS to establish a pilot
program to assess the feasibility of acquiring military-purpose
nondevelopmental items using streamlined procedures.
DFARS
Case 2011-D040: DoD proposes to amend the DFARS to update text addressing the definition of
cost or pricing data to make it consistent with the FAR.
Comments are due by March 19.
DFARS
Case 2011-D054: DoD proposes to amend the DFARS to update DoD’s voucher processing
procedures and better accommodate the use of Wide Area WorkFlow.
Comments are due by March 19.
DFARS
Case 2012-D002: DoD proposes to amend the DFARS to establish an
order for application of contract modifications to resolve any potential
conflicts that may arise from multiple modifications with the same effective
date. Comments are due by March 19.
In Size
Appeal of Excalibur Laundries, Inc., the SBA's OHA held that the Area Office was not
required to consider a specific allegation of affiliation
first raised after the deadline for filing a size protest in a
negotiated procurement had passed.
In Size
Appeal of Rio Vista Management, LLC, the OHA found that the Area Office's size
determination contained multiple errors, including (i)
reliance on circumstances occurring more than three years
before the date of the size determination; (ii) finding
affiliation from assistance properly provided under an
approved 8(a) mentor-protégé agreement; (iii) finding a
violation of the newly-organized concern rule when the
protested firm's founder was not in one of proscribed
positions at the predecessor firm; and (iv) finding
affiliation based on an identity of interest between two
individuals when neither of them controlled the allegedly
affiliated firm.
|
| January
14 |
The GAO
sustained a protest by Veterans
Contracting Group after the agency improperly rejected a
bid as nonresponsive for proposing a brand of chiller and
refrigerant that the agency simply did not like, when the
specifications neither prohibited those items nor required a
different brand.
The Court
of Federal Claims denied a protest by Brooks
Range Contract Services, after concluding the plaintiff
lacked standing (i) with respect to an argument it was
required to, but did not, raise in its initial brief and (ii)
because it did not establish it would have had a substantial
chance for award if its protest had been sustained. The court
also rejected the plaintiff's argument that the awardee's
contractor teaming agreement should have been analyzed as a
joint venture (although the court did concede that the
agency's (and the solicitation's) guidance concerning the
requirements for a teaming agreement were far from clear).
Science
Applications International Corp. survived preliminary
motions to dismiss its complaint for lack of standing based
upon the evaluation of its management proposal as unacceptable
(even though the court indicated this argument could be raised
again in motions on the merits for judgment on the
administrative record).
On
a brighter note (at least for protesters), BayFirst
Solutions won its protest at the Court of Federal Claims
because the evaluators (i) irrationally awarded a strength to
the awardee for inadequate resumes while declining to assign a strength to
the protester for resumes that were deemed adequate; (ii)
assessed weaknesses in the protester's Transition Plan that were irrational or not warranted under the
solicitation's evaluation criteria; and (iii) treated offerors
unequally in the Past Performance evaluation.
|
| January
13 |
In USCS
Chemical Chartering, the CBCA held that the
successor-in-interest of a bankrupt firm lacked standing to
prosecute a claim because the bankrupt firm failed to list the
claim in its schedule of assets.
|
| January
12 |
The SBA
has published an interim rule amending its regulations (i) to make them consistent
with the inflationary adjustments that are already codified in the
FAR as they relate to the Women-Owned Small
Business (WOSB) Program and the Simplified Acquisition
Threshold and (ii) to make its WOSB Program protest procedures
consistent with the protest procedures for SBA’s other government
contracting programs. Comments are due by February 13.
FAR Case
2011-024: An extended
comment period (to February 13) now applies to the previously-published,
interim rule that (i) implements section 1331 of the Small Business Jobs Act of
2010 (addressing set-asides of task- and delivery-orders under
multiple-award contracts, partial set-asides under multiple-award
contracts, and the reserving of one or more multiple-award contracts that are
awarded using full and open competition) and (ii) covers the
coordination of the Federal Supply Schedules Program with the
SBA.
FAR Case
2010-016: A correction to the previously-published
rule (see January 1 entry below) concerning the
FAPIIS system notes that there will be a 14-calendar-day
delay in the posting information submitted for the publicly
available segment of FAPIIS.
|
| January
11 |
In Size
Appeal of M1 Support Services, LP, the SBA's OHA affirmed the Area Office's
finding that a firm (i) was not the manufacturer of the
contract items (its proposed subcontractor was) and (ii) was
too large to qualify for the application of the
nonmanufacturer rule.
In Size
Appeal of Technibilt, LTD, the OHA affirmed the Area Office's finding that, under
13 C.F.R. 121.103(c)(2), a contested firm was affiliated
with two firms that each owned approximately 36% of the stock
in the company that controlled the contested firm.
|
| January
8 |
In Matter
of Mission Essentials, LLC, the SBA's OHA held that a protest alleging that the
challenged firm failed to comply with the joint venture
regulations covering SDVOSBs at 13 C.F.R. 125.15(b) was
sufficiently specific and should not have been dismissed.
In Size
Appeal of The Associated Construction Co., the OHA held that the Area Office
properly included a firm's interdivisional labor receipts in
calculating its average annual receipts because the firm's
division was not a separate legal entity and, therefore, not
an affiliate within the meaning of 13 C.F.R. 121.104(a).
|
| January
7 |
The GAO
sustained a protest by W.
B. Construction and Sons because both of the agency's
grounds for rejecting a bid as nonresponsive were improper:
(i) the bidder's failure to provide a price for one of many line items included in
a bid schedule, where the omitted item was divisible from solicitation’s overall requirements,
de minimis as to total cost, and would not affect the competitive standing of the
bidders; and (ii) the bidder's submission of an unbalanced bid
where the agency failed to conduct a FAR 15.404-1(g) risk analysis to determine whether
the unbalanced bid posed an unacceptable risk to the
Government.
|
| January
6 |
The GSA
has has adopted as final, with changes, an interim rule amending
its acquisition regulation (the GSAR) to implement policy and guidelines to
strengthen the security requirements for contracts and orders that include
information technology (IT) supplies, services, and systems,
by adding the following new paragraph (k) to the contract
clause at 48 C.F.R. 552.239-71:
GSA access. The Contractor shall afford
GSA access to the Contractor’s and subcontractors’ facilities, installations,
operations, documentation, databases, IT systems and devices, and personnel used in
performance of the contract, regardless of the location. Access shall be provided to the
extent required, in GSA’s judgment, to conduct an inspection, evaluation,
investigation or audit, including vulnerability testing to safeguard against
threats and hazards to the integrity, availability and confidentiality of GSA data
or to the function of information technology systems operated on behalf of GSA, and to
preserve evidence of computer crime. This information shall be available to GSA
upon request.
|
| January
5 |
Effective
January 20, the EPA is amending its acquisition regulation
(the EPAAR) by revising the contract clause at 48 C.F.R.
1552.211-79 (entitled "Compliance with EPA Policies for
Information Resources Management") to include administrative
changes and to update terminology and Web site links related to EPA policies for
information
resources management.
In
Digitalis
Education Solutions, the Court of Appeals for the Federal
Circuit affirmed a Court of Federal Claims decision that a
company which did not file a statement of capabilities in
response to a published notice of a proposed sole-source award
lacked standing to protest that award. (The court also
discussed, with something less than its most trenchant
reasoning, the possibility that a firm might be able to
protest that the time period an agency allowed for such
submissions was too short.)
|
| January
4 |
In Quimba
Software , the ASBCA dismissed an appeal as untimely after
determining that receipt of a Contracting Officer's decision
by email does not extend the 90-day period for filing an
appeal.
In Akal
Security, an unsuccessful post-award protest, the Court of
Federal Claims held that: (i) an awardee's failure to disclose
a government investigation regarding wage payments that
subsequently ripened into a civil action was not fatal to the
Government's favorable responsibility determination
because the awardee did disclose a related class action
lawsuit and because the size of the undisclosed matter was not
great enough to affect the awardee's overall financial
responsibility; (ii) there was no violation of FAR 15.308
where the SSA simply signed the CO's award recommendation in
the blank beside the word "Approved" because there
was no evidence in the record that the SSA did not exercise
independent judgment in coming to its conclusion; and (iii) an
evaluator's scoring error, even after being corrected, did not
change the ultimate rankings of offerors.
In
URS
Federal Services, the court held that a "best
interests" override of an automatic stay (pending the
resolution of GAO protests) was improvidently issued
because the agency did not consider (i) any alternatives
to the override, such as extending the incumbent's contract
temporarily or (ii) the effect of an override on the integrity
of the procurement system.
In
Timber
Products Co., the court held the Government breached its
implied duties to cooperate with the contractor and not to
hinder its performance by awarding (and later suspending) a
timber sales contract without revealing to the contractor that
the Government's interpretation of the law as permitting it to
forego environmental surveys was unlikely to prevail in a
pending district court suit.
|
| January
1 |
Happy New
Year!
Federal
Acquisition Circular (FAC) 2005-55
is being published and includes the following six items:
FAR
Case 2008-032 ("Preventing Abuse of Interagency
Contracts"): A final rule, effective February 2, adopts
(with changes) the prior interim rule amending FAR Subpart
17.5 to implement a section of the Duncan Hunter National Defense Authorization
Act for Fiscal Year 2009 to prevent abuse of interagency
contracts by: (i) broadening the coverage to address all interagency acquisitions that
result in a contract action (except FSS orders under
$500,000); (ii) requiring agencies to support the decision to use an interagency
acquisition with a determination that such action is the
"best procurement approach"; and (iii) directing that assisted acquisitions
be accompanied by written agreements between the requesting agency and the
servicing agency documenting the roles and responsibilities of the respective
parties.
FAR
Case 2011-021 ("Transition to the System for Award
Management (SAM)"): A final rule, effective February 2,
amends the FAR to update certain definitions and clauses pertaining to three procurement systems
included in the Integrated Acquisition Environment (the CCR database, the Excluded
Parties List System, and the Online Representations and Certifications
Application) which (along with the Disaster Response Registry) will now
be accessed through a single
web site.
FAR
Case 2005-037 ("Brand Name Specifications"): A
final rule, effective February 2, adopts, with changes, a
prior interim rule and amends the FAR to implement three previously
published OMB memoranda on the use of brand-name specifications.
FAR
Case 2009-043 ("Time-and-Materials and Labor-Hour
Contracts for Commercial Items"): A final rule, effective
February 2, will implement various GAO recommendations: (i) to
ensure that time-and-materials and labor-hour contracts are used to acquire
commercial services only when no other contract type is suitable; and
(ii) to instill discipline in the determination of contract type
in order to minimize the risk to the Government.
FAR
Case 2010-016 ("Public Access to the Federal Awardee
Performance and Integrity Information System"): A final
rule, effective January 3, adopts, with changes, the prior
interim rule amending the FAR to implement a section of the Supplemental Appropriations Act,
2010, which requires that the information in the Federal Awardee
Performance and Integrity Information System (FAPIIS), excluding past
performance reviews, be made publicly available.
FAR
Case 2010-005 ("Updated Financial Accounting
Standards Board Accounting References"): A final rule,
effective February 2, amends the FAR to update references to authoritative
accounting standards owing to FASB's Accounting Standards Codification of
GAAP.
|
|