Boards of Contract Appeals (ASBCA,
CBCA, PSBCA, and GAOCAB)
Jurisdiction/Standing/Timeliness/Contract
Disputes Act (CDA) Issues
In
Quimba
Software, the ASBCA dismissed an appeal as untimely
after determining that receipt of a Contracting Officer's
decision by email does not extend the 90-day period for
filing an appeal.
In
USCS
Chemical Chartering, the CBCA held that the
successor-in-interest of a bankrupt firm lacked standing
to prosecute a claim because the bankrupt firm failed to
list the claim in its schedule of assets.
In
Dr.
Lewis J. Goldfine, the CBCA dismissed (for lack of
CDA jurisdiction) a claim for money damages that had not
first been submitted to the Contracting Officer for a
decision and a claim for cancellation of a BPA (because a
BPA is not a contract) even though the BPA repeatedly
referred to itself as a contract: "The fact that the BPA which
SSA issued to Dr. Goldfine calls itself a contract brings to mind a quotation attributed to
President Lincoln: 'If you call a tail a leg, how many legs does a dog have? Four. Calling
a tail a leg doesn’t make it a leg.' "
In
The
Boeing Co., the ASBCA dismissed a government claim against
the contractor (for increased costs allegedly incurred by the
Government as a result of a voluntary change in the
contractor's accounting system) because the Contracting
Officer's decision asserting the government claim was not
issued within the CDA's six-year statute of limitations (41 U.S.C. §
7103(a)(4)(A), formerly 605(a)). The ASBCA (i) examined
whether any of several recent appeals court (including Supreme
Court) decisions had changed the conclusion that the CDA's is
a jurisdictional statute of limitations and (ii) concluded
they had not.
In
Whiteriver
Construction, Inc., the CBCA held that a letter
submitted to Contracting Officer labeled as "final
certified claim" and including a CDA certification
(submitted to correct a prior letter that did not include
a certification) constituted a CDA claim.
In
ACR
Machine, Inc. , the ASBCA held that a contractor's
email to the Contracting Officer requesting an extension of 120
days to a purchase order was a " request for an adjustment in contract terms"
under the definition of a "claim" in the
"Disputes" clause (FAR 52-233.1) and, thus,
was a claim under the CDA.
In General
Dynamics Ordnance and Tactical Systems, Inc. (a
dispute involving unanticipated costs associated with the
Government's allegedly inadequate estimates concerning
ammunition quantities required by the contract), the ASBCA
held that the Government's willful failure to comply with
the Board's orders to turn over documents to the
contractor during discovery merited the sanction of an adverse inference that
the documents, i f disclosed, would have shown that there was relevant
information available to the Government that it failed to consider when developing the estimates
in question, thereby causing the estimates to be inadequately or negligently
prepared.
In
Side
Bar and Assocs., the CBCA held that the Contracting
Officer's belated issuance of a decision on a a claim that
already had been properly appealed to the Board from a deemed
denial could not affect the Board's jurisdiction over the
entire appeal.
In Muhtesem
Co., the ASBCA granted the Government's motion to dismiss
(for lack of jurisdiction) the following elements of damages
claimed to result from Government's late final payment under a
contract: interest on borrowing; loss of reputation; and loss
of anticipatory profits on other business opportunities.
In
JRS
Management, the CBCA dismissed an appeal for lack of
jurisdiction (no contract) because the contractor had
responded to a government order for services by announcing
it was substituting a different individual from the one
specified in the order, thus making a counteroffer the
Government then rejected.
In
Bannum,
Inc., the CBCA dismissed an appeal involving a claim
barred by the CDA's six-year statute of limitations
because it was filed more than six years after it
originally accrued. Subsequently, however, the Board
granted in part a motion
for reconsideration because the contractor had
complained of many acts by the Government that occurred
more recently than six years in the past.
In
SWR,
Inc., the ASBCA denied the Government's motion to
dismiss a claim for lack of jurisdiction and held that the
contractor took sufficient steps under 11 U.S.C. 1123 to
preserve its claim in bankruptcy by adequately disclosing
the claim in its reorganization plan and disclosure
statement.
In
APS
Denver, LLC, the Board denied the Government's motion
to dismiss for lack of CDA jurisdiction because the fact
that the real estate tax assessment in dispute was under
appeal to the taxing authority (and, therefore, ultimately
might be reduced) did not change fact that the contractor had
claimed a definite amount as a sum certain in its claim.
In
A-1
Horton's Moving Service, Inc., the ASBCA denied the
Government's motion to dismiss for lack of CDA jurisdiction
and held that a claim for breach of a transportation
services contract when no services have been provided (as
opposed to a claim for monies due once services under such an
agreement have been provided) is governed by the CDA rather
than section 3726 of the Transportation Act.
In
Ironhorse
Ltd., the ASBCA held that a reminder letter sent by the
contractor three months after its submission of the original
REAs to the Contracting Officer converted those REAs into
claims filed within the CDA's six-year statute of limitations.
In
Triad
Mechanical, Inc., the ASBCA dismissed an appeal for lack
of CDA jurisdiction because (i) the contractor's termination
for convenience settlement proposal was not a claim despite
the fact that contractor had labeled it as such, and
(ii) a government request for additional documentation before
completing its audit of the proposal did not signify an
impasse over it.
In
CPR
Restoration, LLC, the CBCA dismissed an appeal for lack of
jurisdiction because the appellant did not have a contract
with the agency and appeared to have been only a
subcontractor, with no right of direct appeal.
In CACI,
International, Inc., the ASBCA held it had jurisdiction
over the contractor's appeal from a government finding of
noncompliance with CAS 403 even though there was no allegation
of a monetary impact due to the alleged noncompliance.
In Waterstone
Environmental Hydrology and Engineering, Inc., the ASBCA
dismissed an appeal not filed at the Board within 90 days of
receipt of the Contracting Officer's decision (the contractor,
without the assistance of counsel, had initially appealed to
the wrong forum).
The CBCA
dismissed an appeal by
URS
Energy & Construction., Inc., for lack of jurisdiction
because its attempt at the required CDA claim certification
was defective in so many respects that it could not be cured.
In Caddell
Construction Co., the ASBCA held it had CDA jurisdiction
over a contractor's claim for a mistake in bid allegedly induced by the contracting agency's'
"confusion" in failing to designate clearly the applicable Davis-Bacon Ac t wage determination rate for structural
ironworkers on a building construction task order.
In NOVA
Technology Corp., the ASBCA Board held it lacked CDA
jurisdiction over a dispute involving a cooperative agreement
that did not meet the FAR definition of a contract.
In Intermark
Managed Services, Inc., the ASBCA denied the Government's motions
to dismiss and held that the Board had jurisdiction where a
joint venture became the prime contractor under a modified
contract and the joint venture member who filed the appeal was
authorized by the relevant joint venture documents to do so on
behalf of the joint venture. The Board also held that a claim
was properly certified where the contractor submitted an
affidavit to the Board stating that the original claim was
certified and, prior to the appeal, the Contracting Officer
had repeatedly referred to it (in writing) as the
"certified claim." (Thus, the Contracting Officer's
subsequent statements on appeal (to the effect that those
prior references were a matter of form and that she first
noticed after the appeal was filed that the claim package in
the Government's Rule 4 file did not include a certification)
were unavailing.)
In Parsons
Evergreene L.L.C., the ASBCA dismissed an appeal for lack of
jurisdiction because the Government's letter merely notifying
the contractor that the Government intended to assess
liquidated damages (absent (i) an actual assessment of
damages, (ii) a notice of the contractor's appeal rights,
(iii) a statement that the letter was a final decision) was
not an appealable final decision.
In TMS
Envirocon, Inc., the ASBCA dismissed most of the contractor's claims for failure to comply with
the CDA's six-year statute of limitations and denied a claim for REA preparation costs because
the costs were incurred
in anticipation of litigation, not negotiations, and were unreasonably
high compared to the claimed amounts. Subsequently, the Board affirmed
the decision on reconsideration.
In Eastern
New Mexico University -- Roswell, the ASBCA held that a contract for providing training
classes was neither an ID/IQ nor a requirements contract and,
therefore, dismissed the contractor's claim for an alleged
shortfall in expected students, but held that there was a
possibility the contractor could recover for claims involving
extra work, even if the Board was not quite sure what to call
the contract.
In Hedgecock
Electric, Inc., the ASBCA held, inter alia, that seemingly
broad release language in bilateral modifications did not
operate as an accord and satisfaction of the contractor's
delay claims where the Contracting Officer had indicated such
claims would not be considered until the end of the contract.
In a
couple of similar cases involving the same contractor, e.g.,
DODS,
Inc., the ASBCA held that, because a firm had not
undertaken any substantial performance of a unilateral purchase order
(which is an offer) before the delivery date passed, the offer lapsed before
a contract was ever formed.
In
ePlus
Technology, Inc. the CBCA denied the Government's motion
to dismiss an appeal for lack of jurisdiction and held that a
submission labeled both as a termination for
convenience settlement proposal and a claim, which had been
properly certified and which included a request for a
Contracting Officer's decision, was a CDA claim that could be
appealed as deemed denied after the Contracting Officer failed
to respond to it for six months.
In Daniel S. Sinclair,
et al., the ASBCA held (i) it lacked CDA
jurisdiction over claims for "a minimum of" a stated
amount because there was no sum certain being claimed.
In
Omni
Pinnacle, L.L.C., the CBCA denied the Government's
motion to dismiss an appeal involving a cooperative
agreement for lack of CDA jurisdiction because the
contractor's allegation that Government's actions under
the agreement created an implied-in-fact procurement
contract were sufficient to give the contractor an
opportunity to conduct discovery to try to prove that
allegation.
In ERKA
Construction Co., the ASBCA dismissed one count of the
complaint for lack of CDA jurisdiction because the prior
letter to the Contracting Officer on which it was based did
not request a decision and was not certified.
In
GTSI
Corp., the CBCA held it lacked jurisdiction over the
portion of an appeal involving the GSA under a GSA FSS
contract where only the actions of the ordering agency (and
not the terms of FSS contract) were involved in the underlying
claim.
In
Jacob
Construction LLC, the CBCA dismissed an appeal as untimely
filed where there was no evidence the Contracting Officer had
extended the period for appeal by reconsidering her original
decision, even though the Contracting Officer was considering
other claims related to the same contract.
In
Eagle
Peak Rock & Paving, Inc., the CBCA dismissed a direct
subcontractor appeal (brought under a third party beneficiary
theory) for lack of CDA jurisdiction because the subcontractor
had no privity of contract with the Government and the third
party beneficiary arguments would apply only to appeals in the
Court of Federal Claims pursuant to Tucker Act.
In Green
Dream Group, the ASBCA (i) denied the Government's motion
to dismiss appeals for lack of jurisdiction, and (ii) held
that even though the contractor had changed its name and then
changed its address in a Baghdad war zone because of an
explosion, it was the same entity that had been awarded the
original contract.
In
Cecelia
Sutton, the CBCA dismissed an appeal for failure to
prosecute after the appellant failed to respond to and comply
with the Board's initial scheduling order and several
subsequent orders.
In EJB
Facilities Services, the ASBCA denied the Government's
motion to dismiss the appeal for lack of CDA jurisdiction
based on the Government's allegation that the person who
submitted the claim was a former government employee who,
prior to his retirement, had participated personally and
substantially in the solicitation leading to the award of the
contract at issue and, therefore, had allegedly violated 18
U.S.C. 207(a)(1) in communicating the claim to the Government.
In
KK&L
Administration, Inc., the CBCA dismissed an appeal for
lack of jurisdiction because it was the subcontractor,
purporting to be prime's representative, that filed the
notice of appeal. It did not help matters that a letter
purportedly authorizing the sub to file the appeal
included the docket number of the appeal but was dated
three months before the appeal was actually filed.
In
Jane
Mobley Assocs., the CBCA held that a claim that the
Government had breached the covenant of good faith and
fair dealing by issuing a modification that unilaterally
changed the contract's payment practices did not not
require an allegation of bad faith on the part of the
Government. The CBCA applied the same principle in Sigma
Services, Inc.
In Tri-County
Contractors, Inc., the ASBCA held that, especially in
the context of earlier communications on the same subject, a
request for equitable adjustment addressed to the Contracting
Officer and seeking a "written response" (which was
accompanied by a CDA certification) satisfied the requirements
for a CDA claim.
Changes/Constructive Changes/Contract
Interpretation/Breach/Authority
In
Singleton
Enterprises, the CBCA denied a post-award unilateral
mistake-in-bid claim due to a lack of evidence in two
areas: (i) what the bid would have been absent the
alleged mistake; and (ii) that government knew, or should
have known, of the mistake prior to award.
In
Rafael
Portillo, the CBCA held that the Government complied
with an unambiguous lease provision that permitted it to
terminate a lease with 60-days advance notice.
In
Distributed
Solutions, the ASBCA initially granted partial summary
judgment to the Government (because its interpretation of
disputed language in a contract modification was the only
reasonable one and was not in conflict with any other
contractual language) but subsequently vacated its
earlier
decision in order to allow further discovery on issues of
contract interpretation.
In
Sharp
Electronics Corp. , the CBCA held that a purchase
order provision establishing a cancellation charge if the
Government did not extend a 48-month, lease-to-own term
beyond the first 12-month period was valid and enforceable
against the Government.
In
Hillcrest
Aircraft Co., the CBCA denied the contractor's claim
for reimbursement of federal excise taxes in a contract
containing the unique commercial item tax clause at FAR 52.212-4(k)).
In
TKC
Aerospace, Inc., the CBCA interpreted the contract as
making the contractor responsible for the costs of
repairing corrosion in an aircraft it was leasing to the
Government and for the costs of "downtime"
during such repairs.
In
Southern
Defense Systems, Inc., the ASBCA held that the contractor
was not entitled to receive the same (higher) pass-through
mark-up on a particular delivery order as stated in the basic
contract (rather than the lower rate negotiated for the
delivery order) because the contractor did not demonstrate
there was a patent or latent ambiguity, a violation of the
FAR, a mistake, or bad faith, coercion, or misrepresentation
by the Government.
In
Hartman
Walsh Painting Co., the ASBCA denied the contractor's
claim for extra work on a painting contract and held that the
Government's approval of one of the contractor's submittals
did not preclude the Government from later enforcing
compliance with specification.
In
M.E.S.,
Inc., the ASBCA decided several claims by a construction
contractor for alleged changes and compensable delays
(including claims for extended field and home office
overheads) opposed by various government defenses, including
the sovereign acts doctrine, concurrent delays, and lack of
proof of quantum.
In
denying
Veleta
Corp.'s claim under the "Changes" clause,
the CBCA held that the contractor failed to present any
evidence of either (i) work beyond that required by the
specifications specs or (ii) increased costs caused by this
allegedly extra work.
In
Walsh/Davis
Joint Venture, the CBCA held that an unambiguous sentence
in various contract modifications barred the contractor from
passing through its construction subcontractor's subsequent
claims for cumulative labor inefficiencies.
In
Weigel Hochdrucktechnik
GmbH & Co. KG, which involved a contract performed in
Spain, the ASBCA (i) held that the Government had failed to
prove that the water testing it required the contractor to
perform was required by either the contract or Spanish law and
(ii) denied the contractor's claim for waterproofing certain
containers because the Government merely acquiesced in
contractor's (ultimately unsuccessful) suggested method for
doing so, without waiving the contract requirement that they
be waterproof.
In
Valley
Apparel, LLC, the ASBCA denied an appeal because one
statement in a footnote to a solicitation for an indefinite
quantity contract to supply parkas regarding the percentage of
each size parka the Government "anticipated"
ordering was not a guarantee that the Government would order
those percentages, especially when read in connection with
numerous other solicitation provisions indicating the amounts
to be ordered were uncertain.
In
Top
Painting Co., the ASBCA granted the Government's motion
for summary judgment and rejected the contractor's claim for
Differing Site Conditions because (i) the contractor had
failed to conduct a pre-award site visit; (ii) the conditions
encountered by the contractor were visible (neither subsurface
nor latent); and (iii) the contract required the contractor to
deal with conditions of that type.
The ASBCA
denied an appeal by Hartman
Walsh Painting Co. because, in connection with its
misrepresentation claim, the contractor failed to prove that
the Government made an erroneous representation of material
fact.
In
Sharon
Roedel, the PSBCA, in a rare result, held that (i) an
enforceable oral agreement for a six-month contract without
the right of termination had come into existence (despite
denials from the Postal Service), and (ii) the Postal Service
had breached the contract by terminating it within a week of
its inception, entitling the contractor to the wages and
profit she would have earned in the full term.
In
UniTech
Services Group, Inc., the ASBCA denied the contractor's
claim for decommissioning costs, sometimes referred to as unamortized and stranded
costs, arising from the closing of the contractor's
longstanding nuclear laundry facility in Hawaii, finding there
was no evidence of an implied-in-fact contract, especially
where there was an express contract covering the same subject
area, and concluding there was no basis under that
express contract for recovery on theories of failure to
disclose superior knowledge, breach of the covenant of good
faith and fair dealing, or equitable estoppel.
In Cubic
Transportation Systems, Inc., the ASBCA held that both the
"Pricing of Adjustments" and "No Waiver of
Sovereign Immunity" clauses in a contract between a private
firm and the Washington Metropolitan Area Transit Authority
precluded the recovery of interest on late payments.
In International
Oil Trading Co., the ASBCA held, inter alia, that the
Government's inspection method did not substantially comply
with requirement of the "Quantity Determination"
clause of a fuel delivery contract, and the Government could
not present extrinsic evidence to interpret that unambiguous
requirement.
In Strand
Hunt Construction, Inc., the ASBCA held that (i) high temperatures
encountered by a contractor in a building were contemplated by
the specifications and, therefore, were neither a constructive
change nor a Type I Differing Site Condition, and (ii) an
interpretation never advanced by the contractor before appeal
(and then not raised until the very last opportunity during
the appeal) was not entitled to any weight.
The
CBCA granted the contractor's appeal in
Red
Gold, Inc., because the contractor successfully
established all the elements for a unilateral mistake-in-bid
claim.
In
GaN
Corp., the ASBCA held that, under the "Payments"
clause of a contract that provided the contractor would be
paid at pre-established, fixed hourly rates for the hours
actually worked by its employees, the fact that the
contractor's salaried employees were not paid extra for
working extra hours was irrelevant.
In Daniel S. Sinclair,
et al., the ASBCA held (i) it lacked CDA
jurisdiction over claims for "a minimum of" a stated
amount because there was no sum certain being claimed, and
(ii) the Government's termination of a lease did not
extinguish its contractual obligation to make specified
improvements, which was the main reason for the lessor to
enter the lease in the first place.
In MCC
Construction Corp., the ASBCA held that the phrase
"subsequent contracting opportunities" in section
713(b) of the Small Business Competitiveness Demonstration Program Act of
1988 means solicitations for a contract rather than requests
for task order proposals.
In
Lear
Siegler Services, Inc., the ASBCA sustained the
contractor's appeal and held that a unilateral modification to
a task order under an Air Force ID/IQ contract for aircraft and depot maintenance
at National Guard aviation facilities was a compensable change
because it increased the agreed maintenance workload beyond
that required by the performance work statement.
In
IAP
World Services, Inc., the CBCA held that, under a
fixed-price contract, the contractor was not entitled to
recover its costs of snow removal in a winter when three times
the normal amount of snow fell. Historical snowfall data in
the solicitation was not a guarantee, and the fact that a
different contracting officer had once paid for such removal
did not establish a course of dealing.
In Teresa
A. McVicker, P.C., the ASBCA held that the Government's
purported partial convenience termination merely ratified the
Government's prior breach of the covenant of good faith and
fair dealing when it induced the contractor to enter into the
contract and hire specific employees without disclosing that
the Government intended to bring those employees (and the
associated work) in house as soon as possible. Therefore, the
contractor was entitled to breach damages in the form of lost
profits for the base contract year.
In
Primetech,
the CBCA granted the Government's motion to dismiss an appeal
with prejudice because (i) the Government had fulfilled the
requirement in a bilateral settlement agreement (to make a
specified payment to the contractor), and (ii) extrinsic
evidence would not be admitted to vary the terms of the
agreement to require (as the contractor contended) that the
Government should also expunge references to the contractor's
default termination from government records.
In NDG
Constructors, the ASBCA held that a construction
contractor failed to prove it encountered Type I Differing
Site Conditions in the form of (i) a different soil profile,
(ii) soil with different characteristics, or (iii) increased soil moisture conditions.
In
Amin
Farnam, the CBCA summarily denied an appeal involving a
claim for the cost of repairs to a vehicle bought at an
"as is" auction.
Subsequently, the Board
affirmed
its decision, despite conceding it initially had gotten
the facts wrong.
In
Airclaims,
Inc., the CBCA held that a contract was plain and
unambiguous and did not require the Government to compensate
the contractor for its employees' time spent in airplane
travel.
In APAC
Southeast, Inc., the ASBCA granted the Government's motion
for summary judgment because FAR 52.217-8 ("Option to
Extend Services") permits the Government to extend
a contract up to six months beyond its normal term,
including options, under to FAR 52.217-9 ("Option to
Extend the Term of the Contract").
In
MJL
Enterprises, Inc., the CBCA denied the Government's motion
for summary judgment in part because disputed issues of fact
remained as to whether the general release language in various
bilateral amendments covered the claims at issue before the
Board.
In
R.L.
McDonnell Construction, the ASBCA denied a construction
contractor's claim for extra costs because (i) the SOW was not
ambiguous; (ii) there was no Differing Site Condition; (iii)
the drawings were not defective; and (iv) the Government did
not fail to cooperate; (v) but, rather, the contractor had
made an unreasonable assumption in bidding the job without
checking with the Government.
In
Sigma
Services, Inc., the CBCA held that a claim that the
Government breached the implied covenant of good faith and
fair dealing does not require a showing of bad faith by the
Government.
In
Donald
P. Wood, the CBCA denied a claim for partial refund of the
purchase price paid for goods in an online auction because the
claimant failed to prove the items he received had been
misdescribed and failed to comply with the contract
requirements for making such claims.
In BAE
Systems San Francisco Ship Repair, the ASBCA held that the
Government did not breach its duty to cooperate with the
contractor by taking too long to approve a request made by the
contractor because the contractor did not inform the
Government of the significance or urgency of the request.
In
Lacey
Newday Consulting LLC, the CBCA denied the contractor's
claim that a mistake in bid justified a higher price for
ground beef because, under the RFQ, the contractor
accepted the Government's "offer" (purchase order)
by delivering in accordance with the terms of the purchase
order.
Terminations/Liquidated Damages
In
Lan-Cay,
Inc., the ASBCA upheld a termination for default,
rejecting the contractor's contentions that the Government
had (i) wrongfully withheld progress payments and (ii)
audited and inspected the contractor's work excessively.
In
Delta
Industries, Inc., the ASBCA held that a purchase order
was an offer that lapsed when Delta failed to deliver
within the required time.
In
Singleton
Enterprises, the Board upheld a default termination
after a contract had been reinstated following an
earlier default because there was no reasonable prospect
the contractor could meet newly agreed upon completion
date and because the contractor had not shown performance
was impossible due to an allegedly defective spec.
The
CBCA upheld the default termination of a roadway
vegetation maintenance contract held by
D&M
Grading, Inc., because the conditions encountered by
contractor (which it claimed excused its failure to
complete the work) did not amount to either a Type I or
Type II Differing Site Condition.
In
Laura
K. McNew, the PSBCA held that although a mail deliverer's
act of taking, and using, a discount coupon from undeliverable
mail addressed to a former resident only as
"Occupant" breached the contract and was an event of
default, the default was excused by the fact that this was a
common practice of employees of the post office in question.
(When I was a kid, the "everybody else is doing it"
excuse never worked with my parents.)
In Harold
N. Colerick, the PSBCA held that the Postal Service had
properly terminated contract under its "notice
termination" clause (which contemplated no-cost
terminations) and that the contractor was not entitled to
convenience termination costs because the contract did not
contain a termination for convenience clause, even though the
Postal Service had muddied the water by repeatedly referring
to such a clause in its communications with the contractor.
In
Singleton
Enterprises, the CBCA upheld the Contracting Officer's
decision to deny various elements of a convenience termination
claim for lack of proof, tardiness in providing notice to the
Government, and performance in spite of the lack of a notice
to proceed with the contract work.
In Charles
Mullens, the ASBCA held there was no basis for the
contractor's challenge to its termination where the contract
included a "no fault" termination clause.
In
Steelform,
Inc., the ASBCA granted the Government's motion for
summary judgment as to the propriety of a default termination
because bilateral mods acted as an accord and satisfaction,
preventing the contractor from relying on delays occurring
prior to the mods as excuses for its nonperformance.
In
Jerome
T. Dunbar, the CBCA upheld the default termination of a
sales contracts resulting from an online auction (as well as
an assessment of liquidated damages) after the buyer failed to
pick up the items he had won at auction by the extended
deadline for doing so.
In Hanley
Industries, Inc., the ASBCA denied the Government's motion
for summary judgment upholding a default termination based on
the contractor's alleged failure to comply with a contract
provision requiring timely notice of a vendor change because
"contractual notice provisions will not be mechanically
applied."
In BYA
International, LLC, the ASBCA denied the contractor's
motion for summary judgment to overturn a default termination
based on an alleged government waiver because the question
whether the forbearance period preceding the termination was
reasonable was a fact issue still to be resolved.
Delay
In
Versar,
Inc., the ASBCA denied both parties' delay claims against
the other because neither party presented evidence (i)
concerning concurrent delay or (ii) segregating its own and
its opponent's delays.
In
Paradigm II, LLC, d/b/a JB Carpet &
Upholstery Care, the ASBCA denied a contractor's claims
for anticipated profits and unabsorbed overhead after the
Government failed to order as much work as the contractor had
anticipated, noting that, during the alleged period of delay
(i) the contractor could not prove it was ready, willing, and
able to perform because it had declined several delivery
orders; and (ii) the contractor had only one permanent
employee (its managing member) and, therefore, did not pay
employees to stand by.
In ECC,
International, the ASBCA denied all delay claims by a
construction contractor for various constructive changes,
including defective government-furnished property,
interference with performance, and acceleration, most of which
boiled down to the contractor's belief that the Government's
representatives had been too strict in enforcing the
contract's requirements.
Costs and Cost
Accounting Standards (CAS)
In
J.F.
Taylor, Inc., the ASBCA determined that the executive
compensation paid by a contractor was reasonable because
the DCAA's method for challenging that compensation
suffered from unrebutted statistical flaws.
In
Space
Gateway Support, LLC, the ASBCA held that (i) the costs of
accrued sick leave hours paid to employees in cash at the termination of
their employment in accordance with the terms of
applicable collective bargaining agreements were allowable
fringe benefits under FAR 31.205-6, and (ii) the
Government's contrary interpretation of the contract would
have required a deviation from the FAR that the agency had
not obtained.
In
Metron,
Inc., after an extensive, fact-based analysis, the ASBCA
held that a contractor's executive compensation costs were
reasonable and allowable.
In Inframat
Corp., the ASBCA held held that, under FAR
42.709-5(c)(1), (2), the contractor was not
entitled to a waiver of the penalties for unallowable costs
included in its final indirect cost proposals because, inter
alia, the contractor:
failed to exercise due care
because its system support broke down for failure to make yearly maintenance payments,
its [software accounting] system crashed, it lost cost information, its bookkeeper could not make timely
cost entries, and its inexperienced controller included expressly unallowable costs in its
2004 final indirect cost rate proposal on the misunderstanding that DCAA later would tell
him what costs were not acceptable. . . .
In
URS
Energy & Construction, Inc., the CBCA denied the
Government's motion for reconsideration (based on sovereign
immunity and Anti-Deficiency Act arguments) of the Board's prior
decision finding the contractor entitled to recover the
amount paid to a surety under a supersedeas bond.
In
Shaw
Areva Mox Services, LLC, the CBCA denied the Government's
motion for summary relief because the Board was not bound by
the Contracting Officer's prior determination that the costs
at issue were not allowable.
In
Thomas
Associates, Inc., the ASBCA upheld the ACO's
determination that five indirect cost items (membership in
a hunting club, costs of a jazz ensemble, gifts of flowers
to employees on various special occasions, an
expensive Christmas party that included significant costs
for alcohol, and certain rental costs) were expressly
unallowable under FAR 31.205 and that the contractor was
not entitled to a waiver of the penalties for unallowable
costs under FAR FAR 42.709-5.
Quantum
The
CBCA did not buy
National
Fruit Product Co.'s arguments that its late deliveries
were excused by a stinkbug outbreak, but concluded the
Government had vastly overstated the amount of liquidated
damages that were due. The contractor and the Government each
interpreted the liquidated damages provision in an equally
preposterous manner: the contractor claimed only $33.53 were
due, and the Government had assessed more than $500,000. The
Board concluded that the proper interpretation of the clause
resulted in an assessment of $9,650.
Discovery/Evidence/Procedure
In
Parsons-UXB,
Joint Venture, the ASBCA granted the contractor's
motion to exclude an export report and testimony based on
that report because nothing in the proffered evidence
required expert testimony: "[The proffered] opinion is not based upon any
'scientific, technical, or other specialized knowledge' and does not
'help the trier of fact.' None of the facts described by
[the proffered expert] require any expertise to decide them. All of them
are within our competence to determine as the trier of fact. Accordingly, his opinion
about them is of no help. Additionally, [the proffered
expert's] opinion of the meaning of the word
'foreseeable' relates to an issue of l aw, and in particular attempts to interpret
specialized legal terminology."
In
General
Dynamics Ordnance and Tactical Systems, Inc. (a
dispute involving unanticipated costs associated with the
Government's allegedly inadequate estimates concerning
ammunition quantities required by the contract), the ASBCA
held that the Government's willful failure to comply with
the Board's orders to turn over documents to the
contractor during discovery merited the sanction of an adverse inference that
the documents, i f disclosed, would have shown that there was relevant
information available to the Government that it failed to consider when developing the estimates
in question, thereby causing the estimates to be inadequately or negligently
prepared.
In
Lawrence
Jackson, the CBCA dismissed an appeal (with prejudice) for
failure to prosecute after the appellant repeatedly ignored
the Board's orders to file a Complaint or to designate its
notice of appeal as its Complaint.
In
Utility
Construction Co., the ASBCA denied the Government's motion
to dismiss an appeal for failure to prosecute based on the
appellant's litigation delays. The Board noted that the
appellant had not refused to proceed and that the appellant's
attorney indicated it was not receiving payments from the
contractor.
In
Power
Wire Constructors, the CBCA denied the contractor's motion
for reconsideration in part because the contractor asserted as
fact a position directly contradictory to the one it had taken
in the
original
litigation).
In
The
Public Warehousing Co., the ASBCA ruled on several
discovery motions in a board case where there were concurrent
district court civil and criminal fraud proceedings involving
the same contractor and the same contract, but distinct
issues. One motion was the Government's (unsuccessful) motion
to dismiss the appeal after it discovered the contractor was
live-streaming the Contracting Officer's deposition to defense
counsel in the criminal proceeding.
Equal Access to Justice Act
In
Maggie's
Landscaping, Inc., the ASBCA denied an EAJA application,
in part because the Government's litigation position, though
incorrect, was substantially justified and also because it was
the Board, on its own initiative, which had to search the
record to come up with evidence to support one of the
contractor's original claims.
Court of Federal
Claims
Contract Disputes
Act (CDA) / Tucker Act / Jurisdiction / Standing
In
SUFI
Network Services, the court denied the Government's motion
to dismiss a complaint in a direct appeal to the court from
the Government's failure to issue a decision on the
contractor's claim for attorneys' fees submitted after a prior
successful ASBCA case on the merits (despite the fact that the
1979 version of the "Disputes" clause in this
non-appropriated fund contract only provided for an appeal to
the ASBCA) because the Government breached the
"Disputes" clause by failing to issue a decision on
the contractor's claim within a reasonable time--meaning the
clause was no longer controlling on this issue.
In
Travelers
Casualty & Security Co. of America, the court held that, given the Anti-Assignment Act, a
general liability insurer (as opposed to a surety)
does not have standing to sue Government for breach of
contract to recover amounts it paid to its insured, even
under a theory of equitable subrogation.
In
Simulation
Technology, a CDA jurisdictional decision, the court
dismissed an excusable delay claim that was not
sufficiently similar to the claim that had been previously
presented to the Contracting Officer to have put him on
notice of it.
In Century
Exploration New Orleans, Inc., And Champion Exploration, LLC,
the court discussed (at length) the evolution of the case law
on the subject before concluding that the contractor was not
prohibited from asserting a Fifth Amendment
"Takings" claim and a breach of contract claim as
alternative theories in the same Complaint.
In
L-3
Services, Inc., Aerospace Electronics Division, the court
noted it lacked jurisdiction over claims under maritime
contracts and that allegations of violations of the FAR and
the Antideficiency Act were not sufficient to establish
jurisdiction.
In
Township
of Saddle Brook, the court dismissed a claim based on an
implied-in-fact contract (because the allegations in the
complaint were not adequate to establish either the mutual
intent to contract or an exchange of consideration) and held
there is no jurisdiction in the court over claims for
promissory estoppel.
In
Raytheon
Co., the court held that the CDA's
six-year statute of limitations barred a Contracting Officer's
decision on a government claim issued ten years after
the advance agreement on allowable costs that the decision
purported to challenge and that (i) the continuing
claims doctrine, (ii) equitable tolling under the FAR
"Credits" clause, and (iii) the accrual suspension
doctrine did not apply in this situation. The Government's
claim had been based on an audit conducted after the
expiration of the six-year period, apparently motivated by
criticism of the original audit conducted within that
period. Subsequently, the
Government argued unsuccessfully that the court should
reconsider its earlier
decision because the statute of limitations on the
Government's claim could not begin to run until it completed
its audit. In this case, the court concluded the Government
had enough information to know of its claim even before it
began the audit.
In
Bell
Heery/A Joint Venture, the court dismissed the counts in the
complaint requesting a "review" of the Contracting
Officer's denial of the contractor's claims (because the CDA
only authorizes suits directly on the underlying claims).
In
Atkins
North America, Inc., the court (i) rejected the
plaintiff's contention that the Contracting Officer's decision
(which had been drafted by others) did not reflect her
independent judgment on a government claim and (ii) held that
it was sufficient that the Contracting Officer familiarized
herself with the facts and conclusions contained in the draft decision and
adopted them as her own.
In
Uniglobe
General Trading & Contracting Co, W.L.L., the court held it lacked CDA jurisdiction over a
contractor's suit filed more than four years after the
contractor received
the Contracting Officer's decision and more than two years
after the the Government had terminated post-decision
discussions concerning the claim.
In
Extreme
Coatings, Inc., the court stayed the
proceedings to permit Contracting Officer time to decide
claims submitted by the contractor to the Contracting Officer
after the contractor had filed this suit based on the
Contracting Officer's denials of other, related claims. The
court reasoned that the two sets of claims were not so
closely tied that the suit on the earlier claims had divested
the Contracting Officer of the power to decide the second set
of claims.
In
Union
Pacific Railroad Co., the court dismissed a case pursuant
to the Tucker Act's statute of limitations because it was
filed more than six years after the date it accrued.
In
Kenney
Orthopedic, LLC, the court held that, although it had
Tucker Act jurisdiction over the plaintiff's claim for
misrepresentation in the inducement to enter a
settlement agreement with the VA, the claim must be dismissed
for failure to state with sufficient particularity the alleged
facts of the what, when, where, and how of the
misrepresentation under Rule 9(b).
In
Hartford
Fire Insurance Co., the court denied the
Government's Rule 12(b)(6) motion to dismiss for failure to
state a claim upon which relief may be granted where the
plaintiff had alleged that it was entitled to funds due a
contractor on one contract as damages for a sum the Government
had wrongfully paid to the contractor on another where the
plaintiff, as equitable subrogee, was the performance bond
surety on both contracts (under the "two contract"
theory recognized in Transamerica Insurance Co. v. United
States, 989 F.2d 1188 (1993).
In
Kenney
Orthopedic, LLC, the court held that,
although it had Tucker Act jurisdiction over the plaintiff's
claim for misrepresentation in the inducement to enter a
settlement agreement with the VA, the claim must be dismissed
for failure to state with sufficient particularity the alleged
facts of the what, when, where, and how of the
misrepresentation under Rule 9(b).
In
K-Con
Building Systems, Inc., the court held
that: (i) even though a contractor's letter to the Contracting
Officer requesting remission of previously-assessed liquidated
damages for allegedly late performance contained almost no
specifics concerning the basis of the request, it was,
nevertheless, a valid CDA claim when read in the context of
the contractor's earlier letters to the Contracting Officer
requesting time extensions for excusable delays; (ii) the
current suit divested the Contracting Officer of authority to
issue a decision on a portion of a subsequent claim that was
already encompassed by this suit; (iii) the liquidated damages
rate used in contract was unobjectionable; (iv) releases
in various contract modifications precluded the
contractor from seeking further excusable delays based on
inclement weather (hurricanes); and (v) the contractor was not
entitled to recover on a claim for excusable delay because the
contractor had not gone through the proper steps to obtain the
Contracting Officer's approval for a change in its
construction sequence.
In
Ground
Improvement Techniques, Inc., the court held it lacked
jurisdiction because there was no privity of contract between
the plaintiff/subcontractor and United States.
In
Tidewater
Contractors, Inc., the court held it lacked CDA
jurisdiction because (i) no final decision had been issued at
time the Complaint had been filed; (ii) no final decision
could be implied because nothing the Government had done had
determined liability or damages related to the contractor's
claim; and (iii) no constructive termination for default had
occurred.
Changes/Breach/Contract
Interpretation/Defective Specs/Authority
In
Pew
Forest Products, the plaintiff argued (unsuccessfully, in
both cases) that (i) its timber logging contracts came into
existence at the time bids were opened and its bid was
declared to be the best bid (as opposed to when the Government
later signed the contracts), and (ii) its logging operations
were compensably delayed by contingencies that the
solicitation and contract documents clearly stated might
occur.
In
System
Planning Corp., the court denied a contractor's claim
because the option clause containing the language on which the
claim was based was never exercised.
In
Bell
Heery/A Joint Venture, after dismissing the counts in the
complaint requesting a "review" of the Contracting
Officer's denial of the contractor's claims (because the CDA
only authorizes suits directly on the underlying claims), the
court held that the actions of state
officials hindering the performance of a federal construction
contract could not be attributed to actual or implied
breaches, changes, or cardinal changes of the contract by the
Federal Government because the contract allocated the risk of
such actions to the contractor through the "Permits and
Responsibilities" clause.
In
Overseas
Lease Group, Inc., the court held that
the Government breached a contract for leased vehicles by
failing to compensate the lessor for damage to returned
vehicles and by forcing the lessor to accept short term leases
that did not comply with minimum contract term.
In
BPLW
Architects & Engineers. Inc., although the court
found that the architect breached the contract by
negligently failing to provide underfloor piping and civil site grading
designs that complied with the contract's requirements and the applicable standard of care,
the Government failed to prove that the negligent designs
caused the vast majority of the costs claimed by the
Government for its alleged damages.
In Lublin
Corp., the court denied a
subcontractor's claim that its prime contractor had terminated
it because the Government allegedly had leaked information to
the prime that the subcontractor had disclosed to the
Government in confidence:
Plaintiff attempts to pile a Pelion of conjecture upon an Ossa of speculation in relying on
a single, lonesome fact - the timing of its termination - to prove that HUD officials breached an
alleged confidentiality agreement. But like the Greeks of old, whose stone pile atop Mt.
Olympus failed to reach the heavens, plaintiff’s efforts fall far short of its goal, dashed, inter
alia, by evidence proving that [the prime's] decision to terminate Lublin predated Lublin’s meeting
with HUD.
In
SUFI
Network Services, Inc., the court, performing a
Wunderlich Act review of a prior ASBCA
decision in a non-CDA case involving a nonappropriated
fund activity and a contract to provide telephone services
in guest lodging rooms on U. S. Air Force bases in Germany
increased the award to the contractor for various breaches
and extra work from the approximately $4.6 million
previously awarded to it by the ASBCA to more than $118.7
million.
In
P&K
Contracting, Inc., the court held that a contractor
was not entitled to the extra costs of providing a
contractually compliant HVAC system and rejected the
contractor's allegations of (among others) mistake,
defective specifications, equitable estoppel, superior
knowledge as excuses
for its
original proposal of a non-compliant system.
In
denying a motion for summary judgment in Alpena
Marc, LLC, a case
involving a dispute over the proper interpretation of the
term "base year" in a real property lease for
purposes of determining the responsibility for future tax
adjustments, the court noted that
the issue did not fit neatly within doctrine of patent
ambiguity and that "the parties’ cribbed formulation of
these doctrines [ambiguity and mistake] hamstrings not
only resolution on summary judgment, but also an appropriate
resolution of a bizarre contractual impasse that the rules of contract interpretation may not
resolve satisfactorily to either party."
Terminations
In
Philip
Emiabata d/b/a/ NOVA EXPRESS, the court held that the
Government properly terminated a Postal Services contract for
default after the contractor failed to provide the Contracting
Officer with proof that it had obtained the contractually-required liability insurance
that would enable it to begin performance.
In
5860
Chicago Ridge, LLC, the court (i) upheld
the Government's default termination of a building lease due
to numerous, longstanding water leak problems even though the
Government failed to strictly comply with lease's cure period
requirements because the contractor indicated it could not
have fixed all the leaks within the full cure period, but (ii)
denied the Government's claims for relocation costs (because
the Government failed to meet its burden of proof to show
which of those costs were necessary) and excess reprocurement
costs of substitute rental space (because the Government's
witness failed to compare the relocated space with the
original space to establish they were similar).
In
M.E.S.,
Inc., the court held it lacked subject matter and ancillary jurisdiction over a bonding
company's claims in intervention that: (a) the
plaintiff/defaulted contractor should be required (i) to pay
the bonding company any recovery by plaintiff to the extent of
the bonding company's bond losses and (ii) to pay into
court any remaining balance on plaintiff's affirmative recovery
to be held for the benefit of the bonding company as a set-off against any
potential award in a separate federal district court lawsuit
between the bonding company and the Government (over the
bonding company's refusal to be responsible for the excess
reprocurement costs during the contractor's challenge to the
underlying default termination at the PSBCA); and (b) the
court should issue a declaratory judgment that the claims alleged against
the bonding company by the Government in the district court
suit with respect to the alleged excess reprocurement costs are subject to setoff to the extent of any
affirmative recovery by the contractor in the Court of Federal
Claims action. Secondly, the court held that the CDA's
statute of limitations with regard for claims for excess
reprocurement costs begins to run when the Government pays the
reprocurement contractor, not when the original default
termination is issued. Third, the court held that, in this
case, the Government, nevertheless, lost its right to claim
excess reprocurement costs under the CDA because it
unreasonably delayed the reprocurement for four years as part
of a litigation strategy, when the delay increased the costs
of reprocurement.
Costs;
Quantum; Cost Accounting Standards (CAS)
In
Kellogg
Brown & Root Services, Inc., the court analyzed the
contractor's burden of proving the reasonableness of its
claimed costs in connection with a contract to provide dining
facility services to troops in Iraq, in a situation that was
further complicated by the fact that two of the contractor's
managerial employees accepted kickbacks from a subcontractor,
which, in turn, resulted in government counterclaims for (i)
violations of Anti-Kickback Act and (ii) common law fraud
(with the court ultimately deciding that the contractor was
liable only for the return of the amount of the kickbacks
accepted by those employees).
In Sugar
Hill, LLC V. United States, the court held that the lessor
had not proved it was damaged by the Government's alleged
failure to properly restore a trailer park at the conclusion
of a post-Katrina lease for mobile home trailer pads because
the contractor did not present credible evidence that the park
had diminished in value.
In
SUFI
Network Services, Inc., the court held
that a contractor on a NAFI contract could recover its
attorneys' contingent fees incurred before the appeal of its
claim to the ASBCA.
In
its opinion on the merits (following trial) in the Raytheon
post-1995 CAS 413 segment-closing adjustment case, the
court held that: (i) the parties did not intend the
waiver language (which was taken from FAR 42.1204(i)) in the novation agreement
relating to individual segment closings to bar Raytheon's CAS
413 claim because the waiver language was contract-specific
whereas the CAS 413 claims were not; (ii) Raytheon’s reliance on the
"last place worked" methodology to determine the share of pension assets attributable to the AIS segment was
compliant with CAS 413-50(c)(12); (iii) linear interpolation was a reasonable method for
Raytheon to utilize in estimating pension plan assets, and it
complied with CAS 413-50(c)(12)(iii)’s requirement to utilize the market value of the assets
as of the date of the segment closing; (iv) Raytheon's use of a one-hundred percent retirement
assumption with regard to the retirement of retirement-eligible plan participants in preparing its segment closing
calculations for all of the plans in dispute in the AIS segment
was also reasonable and CAS-compliant; (v) Raytheon reasonably followed
the illustration in CAS 413-60(c)(9) and utilized sales data as a proxy for
pension cost data when performing its CAS 413 government share calculations, where a reasonable
search for historical data was performed, and actual pension cost data could not be
located; (vi) the court lacked jurisdiction over the
Government's equitable adjustment claim, as well as a set-off
claim it first raised during the trial; (vii) Raytheon’s Optical segment closing adjustment calculation
did not comply with the CAS requirements (found in CAS 413-50(c)(12)(ii) and CAS 413-50(c)(5))
for allocating assets from a single composite pension plan to the Optical
segment; and (viii) PWF was not a "segment" within the meaning of CAS 413-30(a)(19),
and, therefore, its sale did not trigger the need for a segment closing
adjustment.
In
Nycal
Offshore Development Corp., following an earlier decision
establishing that the Government had breached an oil and gas
lease, the court held that the contractor
was not entitled to lost profit expectancy damages because of
an intervening cause--the contractor would not have been able
to obtain the necessary air pollution permits to proceed with
drilling.
In Kellogg
Brown & Root Services, Inc., the court addressed the reasonableness of subcontractor costs
related to a cost reimbursable prime contract for the
provision of dining facility services in wartime in Iraq and
discussed the standards the contractor had to meet to
establish the reasonableness of its methods for pricing
changes to those subcontracts during times of rapid troop
buildups beyond the levels contemplated by the original
subcontracts.
Discovery,
Evidence, Procedure
In
Structural
Concepts, the court denied cross motions
for partial summary judgment as to the propriety of government
counterclaims for liquidated damages because such damages
cannot not be quantified until after resolution of delay
claims that have been reserved by the parties for trial on the
merits.
In
K-Con
Building Systems, Inc., the court imposed both monetary and evidentiary sanctions on the
Government because (i) it failed to produce a set of relevant
documents during discovery, and (ii) one of its witnesses
destroyed the documents after their existence became known but
before the plaintiff could examine them.
In
Sikorsky
Aircraft Corp., the court denied the Government's
motion to strike a set of emails from the record because
the Government had waited too long after it had produced
the documents during discovery to assert the deliberative
process privilege.
Fraud
In
Railway
Logistics International, the court denied the contractor's
$6 million in breach claims (on a contract worth less than
$2.5 million) and granted the Government's counterclaims for
forfeiture under a special plea in fraud based on a contractor
spreadsheet concerning the claim quantum revealed during
discovery. The court left little doubt how it felt about the
spreadsheet and the contractor's claim in general:
Railway
Logistics could not support its claim because of fraud and misrepresentation of fact.
Every item on the spreadsheet that served as plaintiff’s support for its claim was overstated or
imaginary. Contents of the spreadsheet alone provide clear and convincing evidence that RLI
practiced fraud "against the United States in the proof, statement, establishment, or
allowance" of its claim. 28 U.S.C. § 2514.
Trial of this case revealed that defendant’s business relationship with RLI had no redeeming
aspect; it caused a grievous waste of limited resources and hindered the Government’s rebuilding
efforts in Iraq. RLI was in obvious breach of both contracts, yet defendant terminated them for
convenience of the Government. This would have allowed plaintiff to walk away with little or no
cost to itself, yet it sued the Government for millions of dollars on a specious claim, thereby creating
still more waste of valuable time and resources.
The Government limited its counterclaims to the most obvious and outrageously inflated
fraudulent claims. Given that restraint, the category of claims that RLI could not support because
of "misrepresentation of fact or fraud by the
contractor" totaled $1,175,160. See 41 U.S.C. § 7103(c)(2).
. . .
Any amount of RLI’s claim that might have been valid, or could have remained after
applying statutory penalties would be forfeited pursuant to the special plea in fraud. 28 U.S.C. §
2514. Statements contained in the spreadsheet alone support a finding, by clear and convincing
evidence, that plaintiff attempted to practice a fraud
"against the United States in the proof, statement, establishment, or
allowance" of its claims.
In
Grand
Acadian, Inc., the court denied all of the contractor's
various claims for government damage to leased property, but
also held that the Government had not established that the
contractor had the required mental state to support the
Government's counterclaims for fraud under the FCA, the FFCA or the
antifraud provision of the CDA , i.e.,
"knowing" submission of fraudulent claims.
The
court's decision in Veridyne
Corp. is a fascinating story of a joint scheme by the
contractor and the procuring agency to avoid competition
requirements on an 8(a) contract extension (by vastly
understating its anticipated cost), which eventually collapsed
due to the accounting constraints of funding limitations. The
court refused to declare the extension mod void ab initio
because the agency was in on the deception, but the contractor
was, nevertheless, liable on the Government's counterclaims
for forfeiture, fraud, and CDA antifraud provisions because
the contractor manipulated certain invoices in order to get
around the ever-increasing problem of funding
limitations. In a
later decision in the Veridyne
case, the court granted a portion of the Government's claim
for its costs of reviewing the unsupported portions of the
contractor's CDA claim pursuant to the anti-fraud provisions
of the CDA ( 41 U.S.C. 7103(c)(2)).
EAJA
In Watterson
Construction Co., the court denied the
plaintiff's EAJA application because it found that the
Government's litigation position was substantially justified.
Court of Appeals for
the Federal Circuit
Jurisdiction/Standing/Res
Judicata
In
The
Minesen Co. v. McHugh, the CAFC enforced a provision in the
"Disputes" clause of a NAFI contract that stated the
ASBCA's decision on any appeal would be final and
unreviewable.
In
Parsons
Global Services, Inc., the CAFC affirmed an ASBCA decision dismissing an
appeal for lack of CDA jurisdiction because a prime
contractor's request for payment of its subcontractor's
overhead and G&A costs (at a rate specified in the
subcontract) submitted by the prime two years after a
termination for convenience was "routine" and,
therefore, not a claim within the meaning of the CDA.
FloorPro,
Inc., was a small subcontractor on a
government contract, and it completed its modest work scope
satisfactorily. The prime and the Government then entered a
bilateral modification providing that the payment for
FloorPro's work would be made out in a hard copy check jointly
to the prime and sub to ensure FloorPro received the funds.
The Government's paying office promptly ignored the mod and
sent the funds electronically to the prime, which did not pay
the sub. FloorPro sought relief from the Government's
Contracting Officer and when that was denied, appealed at the
ASBCA, which eventually (four years later) found in FloorPro's
favor on a third party beneficiary theory. The Government
appealed, and (two years later) the CAFC reversed on the
grounds that the CDA did not provide the boards with such
jurisdiction, but noted in dicta that the Tucker Act's grant
of jurisdiction to the Court of Federal Claims was broader, so
FloorPro promptly filed suit in that court, which eventually also
held in its favor. Now, the CAFC reverses that decision, too,
on the grounds that FloorPro did not file suit at the CoFC
until more than six years after the Government had made the
erroneous payment.
In
Bowers
Investment Co., LLC, the CAFC affirmed the CoFC's dismissal of a contractor's claims
for unpaid rent because they were based on the same
transactional facts as, and therefore were precluded by,
claims involved in a prior, unappealed, decision by the CBCA.
In
Peter
C. Nwogu, dba Environmental Safety Consultants, Inc.,
a decision labeled as nonprecedential, the CAFC
held, among other things, that the CDA gives the Court of
Federal Claims Tucker Act jurisdiction to enforce a
monetary judgment rendered by the ASBCA.
Contract
Interpretation/Changes/Authority/Breach
In
Englewood
Terrace Limited Partnership, a
nonprecedential decision, the CAFC remanded
the case to the CoFC for a recalculation of a lost profit
award following a breach because the lower court had not
subtracted the costs saved by reason of the breach.
In Scott
Timber Co., the CAFC reversed the prior decisions by CoFC in
favor of a timber sales contractor (see prior decisions
on liability
and quantum)
and held that (i) the Government could not have breached the covenant of good faith and fair dealing by
failing to disclose information to the contractor prior to
award because the covenant does not exist until the contract
is signed; and (ii) the Government did not unreasonably
lengthen contract suspensions by unduly delaying its actions
during the suspensions because the suspensions were not
"specifically targeted" at delaying Scott's
contracts and did not reappropriate any benefit guaranteed by the contracts, since the contracts contained
no guarantee that performance would not be interrupted.
In a
decision it labeled as nonprecedential, the CAFC reversed the prior decision by the
CBCA and held that the lessor, KD1
Development, Inc., rather than the lessee (GSA), was
entitled to recover on its monetary claims because an
ambiguity in a lease agreement as to whether operating costs
were included in the base rental rate was a latent ambiguity
that could not be resolved one way or the other by resort to
extrinsic evidence (which pointed in both directions) and,
therefore, must be construed against the Government.
Costs/CAS
In
The
DIRECTV Group, the CAFC affirmed the Court of Federal Claims' decision
concerning the appropriate segment closing adjustments
under CAS 413 when the sale of two segments involved the
transfer of defined benefit pension plans.
In
Tip
Top Construction, Inc. v. Donahoe, the CAFC reversed the PSBCA's prior
decision and held that consultant and attorney costs were
recoverable because they were reasonable contract
administration costs incurred in connection with negotiating
the quantum of a change rather than for the prosecution of a
CDA claim.
In
Chu
v. The Boeing Co., a decision it labels as
nonprecedential, the CAFC affirmed (for the most part) a
prior set of CBCA decisions (including this
most recent one) regarding the allowability of defense
costs. The court held that, although the Board
incorrectly determined that it did not have the power to
apportion the costs of litigation in cases with mixed
results, there was no need to remand the case because
apportionment would not have been appropriate in this
case.
This
website links to resources on the web concerning
government contracting. It is not intended to provide
legal advice. Moreover, I do not vouch for the
completeness, currency, or accuracy of the sites to which
it links. If you have comments, suggestions for new links,
or corrections, please email me.
|