Boards of Contract Appeals (ASBCA,
CBCA, PSBCA, and GAOCAB)
Jurisdiction/Standing/Timeliness/Contract
Disputes Act (CDA) Issues
In
Jane Mobley Assocs., the CBCA held that various defenses
asserted by a contractor in its complaint in response to the
Government's claim to recover an alleged overpayment were not
CDA claims and, therefore, were not required to be submitted
to the Contracting Officer before being asserted at the
Board.
In
Reliable Contracting Group, LLC, the CBCA denied a
contractor's claim for certain extra costs. The Federal Circuit
reversed and remanded, instructing the Board
to consider an additional issue. While the Board was preparing its
decision on remand, the parties engaged in settlement
discussions and arrived at a "handshake" settlement that would
have resulted in the contractor receiving some, but not all, of
its originally claimed amount. Before the parties signed the
final settlement agreement or notified the Board of it, however,
the Board issued its
decision on remand, again denying the contractor's claim
(basically saying the record was inadequate for it to consider
the additional issue identified by the court). The contractor then
moved the Board to vacate its decision so that the parties could
implement their settlement agreement. During a
conference call concerning that motion, the Government stated
that it would implement the settlement if the Board vacated its
decision, but the Board issued
a decision refusing to do so. The Board conceded that its
latest decision will likely result in another appeal to
the Federal Circuit.
In
Aetna Government Health Plans,
the ASBCA refused to dismiss a timely appeal from a deemed
denial because the Contracting Officer had failed to issue a
decision within 60 days of the submission of a certified claim
and had failed to specify a non-contingent date by which a
decision could be expected.
In
HK&S Construction Holding Corp., the ASBCA held that, in
deciding whether an appeal was timely filed and absent any
indication in either of the two copies of the Contracting
Officer's decision sent to the contractor as to which of of them
was supposed to start the appeal clock running, the
contractor was entitled to use the date of the copy that it
received last.
In
Bushra Co., the ASBCA dismissed an appeal filed more than 90
days after the contractor's receipt of a notice of termination,
even though the notice merely referred the contractor to the
applicable FAR provisions rather than directly stating its
appeal rights, because the contractor did not allege any
prejudice from the defect in the termination notice.
Subsequently, the Board
denied the contractor's motion for reconsideration.
However, in
Access Personnel Services, Inc., the ASBCA denied the
Government's motion to dismiss an appeal as untimely
because the contractor showed detrimental reliance on the
absence of notice of its appeal rights in the Contracting
Officer's decision.
In
Mansoor International Development Services, the ASBCA
dismissed (as untimely) appeals filed more than 12 months
after the contractor's receipt of the Contracting
Officer's decisions that had failed to notify the
contractor of its appeal rights because the record showed
the contractor had received notice of its appeal rights by
other means and was aware of them and, thus, could not
show prejudice from the defects in the decisions.
In
Suffolk Construction Co., the CBCA denied the
Government's motion to dismiss (as untimely) an appeal
filed with the Board more than 90 days after the
Contracting Officer's decision on the original claim
because the contractor had brought a timely action on the
claim in the Court of Federal Claims, and that court, on
the basis of an unopposed motion supported by good cause,
had then transferred the action to the Board pursuant to
41 U.S.C. § 7107(d).
In
Public Warehousing Co., K.S.C., the ASBCA: (i) held that the
Government's liability for Prompt Payment Act penalties accrues,
for each invoice separately, when the Government pays the
invoice without paying any required Prompt Payment
interest; and then (ii) denied the Government motion for summary
judgment based on the contractor's alleged violation of the
six-year limitations period for presenting its claim because the
Government had not alleged when each invoice was paid, and,
therefore, the claim accrual date could not be ascertained.
In
John Lewinger, as Receiver for Corban ABQ V, LLC, the
CBCA allowed an appeal to proceed to develop the factual record
as to whether the Government had waived the contractor's clear
violations of the Anti-Assignment statutes.
In
Jonathan Noeldner, the CBCA held that, despite
confusion caused by multiple transmissions of notices of
appeal by different means, a notice of appeal (i) that
referred to all of the claims being appealed and (ii) that
was postmarked within 90 days of the Contracting Officer's
decision, was timely.
In
ThinkGlobal Inc., the CBCA, inter alia, dismissed:
(i) a claim for the Government's alleged failure to provide
required information on one contract because the claim accrued
when the information was due at contract award, which was more
than six years before the claim was filed; (ii) a claim for
unfair competition from the Government because the contract did
not give the contractor the right to operate on the disputed
program; and (iii) a claim based on the Government's delays in
responding to an FOIA request because the claim involved a
statutory, rather than a contract, right. The Board, however,
denied the Government's motion to dismiss a claim for damages
solely because a no-cost contract was involved. Subsequently,
the CBCA
partially granted the contractor's motion for
reconsideration with respect to six-year limitations
issue
In
Jonathan Noeldner, the CBCA dismissed an appeal because the
contractor had failed to file a claim with the Contracting
Officer within the time limit established by a timber sales
contract.
In
Military Aircraft Parts, the ASBCA dismissed an appeal
as untimely, holding that the notice of appeal rights in a
decision by a Contracting Officer need not inform a contractor
that, if it chooses to appeal to the Court of Federal Claims,
the company cannot be represented by non-attorney appearing
pro se. (Here, the contractor discovered this CoFC rule only
after his 90-day time limit for appealing to the Board had
passed.)
In
The Adamant Group for Contracting and General Trading,
the ASBCA dismissed an appeal as time-barred because the
contractor failed to follow-up with any inquiries on an
unpaid invoice until more than nine years had
passed.
In
Ralph Muhammad, the CBCA dismissed appeal with
prejudice as moot without the pro se contractor's
consent because the parties had signed a bilateral
modification giving the contractor its requested relief.
In
Agbayani Construction Corp., the CBCA held that an appeal
filed prior to the Contracting Officer's issuance of a decision
was premature.
In
Ahtna Environmental, Inc., the CBCA refused to
penalize the contractor pursuant to an unusual and onerous
Federal Highway Administration contract clause purportedly
barring claims not specifically identified by the
contractor in executing a final payment voucher prepared
by the Government because (i) the contractor adequately
notified the Government of its REA before the voucher was
due, and (ii) the Contracting Officer continued to
evaluate the REA thereafter.
In
URS Federal Support Services, Inc., the ASBCA
dismissed (as moot) an appeal from a Contracting Officer's
decision that was subsequently withdrawn. Similarly, in
BAE Systems Tactical Vehicle Systems LP, the Board
dismissed (as moot) an appeal from a decision alleging a
government claim for defective pricing, which the
Contracting Officer had rescinded.
In
SFM Constructors, Inc., the CBCA denied the
Government's motion to dismiss an appeal because, although
the cover letter to the contractor's claim stated the
contractor was seeking "at least" a specified amount, the
actual certified claim stated a sum certain.
Jurisdiction
In
Shafi Nasimi Construction and Logistics Co., the
ASBCA held that, absent any allegation from the contractor
of prejudice or detrimental reliance, the
Contracting Officer's default termination letter, which
notified the contractor of its right to appeal but not the
time limits for such appeals, was valid and started the
90-day appeal clock running. The Board then dismissed the
appeal as untimely because the Government's communications
with the contractor during the appeal period could not
reasonably be considered as a reconsideration of the
Contracting Officer's decision. I am a little
uncomfortable with this position--isn't the contractor's
failure to appeal within 90 days, itself, evidence of
detrimental reliance on the Contracting Officer's failure
to notify it that there was any time limit for an appeal??
In
Strobe Data, Inc., the ASBCA dismissed an appeal for
lack of jurisdiction because a claim for a "minimum" of,
and "likely more" than, a stated amount was not for a sum
certain.
In
Patrick M. Murray,
the PSBCA dismissed an appeal because the underlying claim did not state
a sum certain,
and, in one of its filings, the contractor wrote: "[r]egarding a total amount claimed, I would not know how to figure out
how much damages I may be entitled to . . . ."
In
Pacific Coast Community Services, Inc., the CBCA
dismissed an appeal for lack of CDA jurisdiction because the
underlying claim failed to state a sum certain. Subsequently,
the Board
denied the contractor's motion for reconsideration.
In
DekaTron Corp., the CBCA denied the Government's
motion to dismiss an appeal for lack of CDA jurisdiction
because, contrary to Government's allegations, the
contractor's original claim was for a sum certain, the
amount requested had not changed on appeal, and the
contractor's allegation that its claim was based on a
contract with the Government was all that was required to
survive a motion to dismiss (arguments concerning the
Government's contention that there was no contract would
not be considered until a hearing on the merits).
in Military
Aircraft Parts, the ASBCA held that a termination for
convenience belatedly issued after the
contractor already had submitted a breach claim based on a
prior (erroneously issued) cancellation, did not deprive
the Board of jurisdiction over an appeal involving the
alleged breach.
In
Shavers-Whittle Construction, LLC, the ASBCA held it lacked
jurisdiction over a direct appeal by a subcontractor, especially
where the letter that the subcontractor contended was its claim
did not include a sum certain and was not certified and where
the subcontractor requested a form of relief (to have the prime
contract voided) beyond the Board's jurisdiction.
In
Global Engineering & Construction, LLC, the ASBCA held
it lacked CDA jurisdiction over an appeal because: (i) the
contractor's letters to the Government did not amount to a
claim, especially where the amount at issue exceeded
$100,000 but had not been certified; and (ii) the
Government's message to the contractor did not contain
sufficient indicia of finality to constitute a government
claim.
In
AeroVironment, Inc., the ASBCA held it lacked
jurisdiction over proposed amendments to the Government's
answers in an appeal because the amendments were actually
new claims first raised by the Government's trial attorney
that were beyond the scope of the Contracting Officer's
original decision.
In
Moss Card Consulting, Inc., the CBCA dismissed an appeal for
lack of CDA jurisdiction because the contractor had not
submitted a claim to the Contracting Officer. In
Richter Developments, Ltd., the CBCA dismissed another
appeal for lack of CDA jurisdiction because the contractor had
failed to certify a claim that exceeded $100,000.
In
Optimum Services, Inc., the CBCA held that the GAO's
conclusion in a bid protest under its CICA jurisdiction that the
procuring agency had acted reasonably in terminating a contract
for convenience was not res judicata with regard to the
Board's ability to decide a CDA claim challenging the propriety
of that termination.
In
Afghan Active Group (AAG), the ASBCA held that a
contractor's emails to the Contracting Officer evidencing a
desire to "appeal" the Contracting Officer's decision were
sufficient to establish jurisdiction at the Board, even absent a
direct appeal to the Board and any statement in those emails
that the Board was where the contractor wanted its appeal filed
because the Contracting Officer's decision had not advised the
contractor of its option of filing suit at the Court of Federal
Claims.
In
Military Aircraft Parts, the ASBCA held that: (i) it lacked
jurisdiction over the contractor's claim that a contract
termination was a breach because the appeal had not been filed
within 90 days of the contractor's receipt of the termination
decision; (ii) because the cancellation of individual purchase
orders orders issued under that contract was not a government
claim, the Board did have jurisdiction over subsequent
contractor claims challenging those cancellations; but (iii)
those claims lacked merit because the contractor had not
delivered the required first article items on time.
Subsequently, the contractor's motion for reconsideration
was
denied
In
Leviathan Corp., the ASBCA held it had jurisdiction over a
contractor's appeal, which was based on a written settlement
offer (made and signed by a DCMA Contracting Officer in the form
of a proposed contract modification), which the contractor had
accepted by signing it, despite the fact that the original
contracting entity (Iraq's CPA) was not one over which the Board
normally has jurisdiction.
In
Military Aircraft Parts, the ASBCA held it lacked
jurisdiction over a contractor's breach claims that
implicitly were challenges to default terminations the
contractor had not timely appealed. Subsequently, the
Board
denied the contractor's motion for reconsideration.
In
Maersk Line, Limited, the ASBCA denied: (i) the Government's
motion to dismiss for lack of jurisdiction (because the claim
presented by the contractor to the Board was based on the same
operative facts as the claim originally submitted to the
Contracting Officer); and (ii) cross motions for summary
judgment (because of disputed material facts and the
advisability of hearing extrinsic evidence as to an issue of
contract interpretation).
In
Bluegrass Contracting Corp., the CBCA held that a notice of
appeal with a Postal Service postmark within the 90-day limit
was timely filed.
In
Bass Transportation Services, LLC, the CBCA dismissed
an appeal of the denial of a contractor's certified claim
for lack of jurisdiction because, although that appeal was
timely filed, the contractor had failed to timely appeal
the prior default termination, the overturning of which
would be a prerequisite to considering the current appeal.
In
ABB Enterprise Software , Inc., the ASBCA rejected the
Government's argument to interpret the phrase "related to"
narrowly and held it had CDA jurisdiction over a dispute
involving a license agreement accompanying software that
the Government was acquiring under a contract covered by
the CDA because the license agreement was "related to,"
i.e. connected with, the performance of the covered
contract.
In
Government Services Corp., the ASBCA held it had
jurisdiction over a contractor's claim for "$100,000"
because it was stated as a sum certain even though, in
response to the Contracting Officer's query regarding
how that amount was calculated, the contractor had stated
it was a "good faith estimate . . . derived by a simple
mathematical formula of estimating the future expense,
both administrative and legal, that is expected to be
required to counter the apparent bad faith libelous
actions of" the Government's representatives.
In
Black Tiger Co., because the appellant alleged the
existence of a contract and provided some evidence of it,
the ASBCA refused to dismiss an appeal based on the
Government's contention that it could find no evidence of
the contract in its records.
In
GSC Construction, Inc., the ASBCA held that although
the DOL had exclusive jurisdiction to decide whether a
contractor violated a contract's labor provisions, the
Board has jurisdiction to decide whether a termination
based on alleged violations of those provisions was
justified.
In
Panjshir Kandahur Construction Co., the ASBCA
dismissed an appeal for lack of jurisdiction because the
contractor had previously filed only a routine invoice
rather than a claim with the Contracting Officer.
In
Academy Partners, Inc., dba Academy Technology, the CBCA
held that the contractor's mere allegation of
the existence of an implied-in-fact
contract for continued performance after the base period of an order
had
ended was sufficient to survive the Government's motion to dismiss for lack of
jurisdiction.
The ASBCA dismissed an appeal by
Arab Shah Construction Co. because there was no
evidence a claim in any form had been filed with the
Contracting Officer.
The ASBCA dismissed another appeal because
Great America Construction Co. had signed a contract
mod releasing all claims in return for a settlement
payment.
In
Suzan Co., the ASBCA dismissed an appeal for lack of
jurisdiction because, despite several orders from the
Board to do so, the contractor never provided any evidence
to the Board that it had certified its original claim
prior to the time the Contracting Officer had issued a
decision on it. An appeal by
Stobil Enterprise at the CBCA suffered from the same
defect and suffered the same fate. Subsequently, the Board
denied the contractor's motion for reconsideration.
In
RECO Rishad Engineering Construction ORG, the ASBCA
dismissed an appeal because the claim certification
included only the typed name of a company official and was
not signed. Similarly, in
ABS Development Corp., the Board dismissed an appeal
because merely typing the name of an alleged claim
certifier in a different font, even a cursive font, does
not result in signature that can be authenticated.
In
Amaratek, the ASBCA dismissed an appeal challenging
the Government's in-sourcing decision because it was
essentially a bid protest over which the Board lacks
jurisdiction.
The ASBCA dismissed an appeal by
Fahim Noori Construction Co. because the contractor's
only submission to the Contracting Officer was a routine
request for payment in the form of an invoice,
rather than a claim. In
Mustafa Kamosh Group, the CBCA dismissed an appeal for lack
of jurisdiction because the contractor had not submitted a claim
to the Contracting Officer.
The ASBCA dismissed an appeal by
KBAJ Enterprises, LLC t/d/b/a Home Again because
the essence of the appeal was a monetary dispute, and the
contractor had not submitted a monetary claim in a sum
certain to the Contracting Officer.
In
Colonna's Shipyard, Inc., the ASBCA held that,
although it lacked jurisdiction over (a) the contractor's
claim that its due process rights were violated by the
Government's failure to permit the contractor to review
and respond to negative comments in a CPAR before it was
published and (b) the contractor's request for injunctive
relief or specific performance, the Board did have
jurisdiction over other contract disputes involving
alleged improprieties in the CPAR.
In
Creative Times Dayschool, Inc., the contractor had
initially submitted a document to the Contracting Officer
that qualified as a CDA claim, but then down-converted it
into an REA (so that the ASBCA lacked jurisdiction over a
suit based on the Contracting Officer's response to the
REA), and still later, reconverted it into a CDA
claim, giving the Board jurisdiction over the Contracting
Officer's subsequent denial of that claim. The fact that
the submission was initially a claim submitted in
anticipation of litigation, rather than an REA, however,
precluded the contractor from recovering its professional
consulting fees incurred in preparing it.
In
Strawberry Hill, LLC, the CBCA dismissed an appeal
because: (i) no contract existed absent the Contracting
Officer's signature; and (ii) the contractor's self-styled
"amended" claim presented on appeal was actually a new
claim for greater than $100,000 that had not been
presented to the Contracting Officer. Similarly, in
Excel Link Construction Co., the ASBCA dismissed an
appeal challenging a firm's designation as "Not Eligible
for Installation Access" in a vendor vetting program
because there was no contract between the firm and the
Government and no prior claim to the Contracting Officer.
In both
Genuine Construction Co. and
Washington Star Construction Co., the ASBCA dismissed
an appeal because the contractor had not submitted a claim
to the Contracting Officer. Similarly, in
Sauer Inc., the ASBCA struck a claim from the
Complaint because it had not been previously submitted to
the Contracting Officer.
The ASBCA dismissed an appeal by
KBAJ Enterprises, LLC t/d/b/a Home Again because the
contractor's alleged claim letter was not sent to the
Contracting Officer and did not request a decision by the
Contracting Officer.
In
B3 Solutions LLC, the ASBCA dismissed a direct appeal
by a second-tier subcontractor to an 8(a) contractor for
lack of jurisdiction because there was no privity of
contract with the Government.
In
CB&I Areva Mox Services, LLC, even though the
contractor sought the same relief (increase in fee
percentage) on appeal as it had in its original claim to
the Contracting Officer, the CBCA dismissed the appeal for
lack of jurisdiction because the contractor's contention
on appeal that the Contracting Officer failed to negotiate
the fee in good faith would require the Board to examine
different operative facts than the original claim, which
relied on the assertion that the Government had breached a
specific contract clause.
In
Angela M. Stine, the PSBCA dismissed an appeal
involving a monetary claim that had not been presented to
the Contracting Officer for a decision and requesting
relief the Board lacked jurisdiction to provide, i.e.,
renewal of a contract.
Changes/Constructive Changes/Contract
Interpretation/Breach/Authority
In In
R.A. Glancy & Sons, Inc., the CBCA held that the
contractor could recover for some extra work directed by
government employees who lacked the authority to give such
directions because the Contracting Officer knew or should
have known what was happening, but simply stood by and let
it continue
In
VEER Right Management Group, Inc., the PSBCA held that
a contractor's unreasonable delay in submitting its
subcontractor's invoice to the Government breached the
contract and left the contractor liable for payment.
In
Andy Phillips, the ASBCA denied various breach claims
because: (i) there was a lack of proof; (ii) the
contract made the contractor responsible for the costs of the alleged issue;
(iii) an isolated event did not rise to the level of a breach; (iv) an
allegation of damages phrased as "[e]stimate loss of sales at 30%" did
not meet the CDA requirement to state the claim as a sum certain; and (v)
allegations that the Government failed to appoint a COR and
invalidly extended the contract were not CDA claims because they did not
include a demand for money or any other relief.
In
The Life Eye Co., the ASBCA denied the claim primarily because the contractor submitted
inadequate, inconsistent documentation, including some with forged
signatures, to support it.
In
Edinburgh International, a case involving contract
interpretation, the ASBCA held that a fixed-price task order,
which did not cover billeting services, did not shift the risk
to (or impose an obligation on) the Government to pay for
unexpected costs of billeting security personnel.
In
Relyant, LLC, the ASBCA held that the interpretation that
the contract allowed the parties to agree on lower prices for
individual delivery orders than those stated in the price
schedules of the overarching contract was the only reasonable
reading of the contract documents as a whole and was consistent
with the parties' actions before the dispute arose.
In
Vistas Construction of Illinois, Inc., a case
involving a post-Katrina construction contract to enlarge a
levee, the ASBCA held, inter alia, that: (i) the
contractor was not entitled to the retroactive use of a
value-added base for calculating G&A when the contractor's
normal approach for all other situations was a total cost input;
(ii) the contractor failed to present sufficient, relevant,
non-contradictory evidence to support its calculation of the
profit it alleged it was owed for changed work; (iii) the
Government was not obligated to pay PPA interest for alleged
delays in payment on disputed amounts in excess of the
original contract price; (iv) several other claims by the
contractor were not adequately supported with evidence, e.g.,
some of its claims for its costs of responding to a DCAA audit
report.
In
Magwood Services, Inc., the CBCA: (i) denied a delay claim
under the "Suspension of Work" clause because the Government's
actions were not the "sole proximate cause" of the delay; and
(ii) upheld the Contracting Officer's withholding of funds
pursuant to "Inspection of Construction" clause for retesting
and rework of work originally provided by the contractor.
In
G2G, LLC, the CBCA held that: (i) an 8(a) contractor
was not entitled to monetary damages for the Government's
decision not to exercise its option to extend the term of
a contract (even if the Government had failed to comply
with certain procedural requirements of the 8(a) program);
and (ii) the Board lacks CDA jurisdiction to compel
specific performance of a contract.
In
SupplyCore, Inc., the ASBCA held that the Government had not
breached a duty of good faith and fair dealing toward the
contractor by allegedly delaying its notice to the contractor
that an option would not be exercised because the contract did
not require any earlier notice from the Government.
In
Jane Mobley Assocs, Inc., a decision based on principles of
contract interpretation, the CBCA held that a bilateral task
order modification clearly established that the modification
work was to be based on labor-hour billing as opposed to the
firm, fixed-price measure under the basic task order, especially
in light of both: (i) the contractor's conduct in changing its
accounting methods to comport with the labor-hour billing system
after the mod was issued, and (ii) the contractor's failure to
inquire about a patent ambiguity between the terms of the
modification and an interpretative statement made by the
Contracting Officer.
In
ERKA Construction Co. Ltd.,
the ASBCA held that, even absent proof that the contractor's
owners or upper management knew of the theft, the contractor was
responsible for the actions of its employees who stole fuel,
especially when it is likely that its project managers were
aware of the situation.
In
Systems Management and Research Technologies Corp., a case
involving contract
interpretation and the parol evidence rule, the CBCA held that a
contract was an unusual hybrid calling for (i) T&M payments of
hourly rates loaded only with G&A and overhead and (ii) a
separate, pre-established "fixed fee" in addition to the T&M
payments.
In
Matheson Postal Services, Inc., the PSBCA held that: (i) a
bilateral amendment (negotiated under the "Changes" clause and
revising rates as a result of service reductions) precluded the
contractor's subsequent claims that the reductions constituted
partial contract terminations; and (ii) a single instance in
which the Postal Service had handled the issue differently on
another contract was not sufficient to create a "course of
dealing" on which the contractor was entitled to rely.
In
River Ridge Development Authority, the ASBCA found broad
authority in a master lease agreement and an O&M plan for the
lessee of an Army ammunition plant to offset some of its
insurance costs against the annual fair market rental for the
property.
In
Lee's Ford Dock, Inc., the ASBCA held that: (i) the
contractor had not established the elements for reformation
based on either mistake or misrepresentation; and (ii) the
contractor's argument that the Government had breached the
agreement relied on an unreasonable interpretation of a clear
provision in the agreement.
In
Americom Government Services, Inc., the CBCA discussed the
requirements for the Government to be found to have ratified an
otherwise unauthorized contractual commitment and held that the
requirements for ratification were met in this case.
Subsequently, the Government's motion for reconsideration
was
denied.
In
Rodriguez Construction LLC, a case involving competing
claims by the Government and the contractor on a contract for
renovation work on a retention pond, the CBCA determined (i) the
extent and quantum of a deductive change and (ii) the date of
substantial completion for purposes of computing the number of
days of liquidated damages the Government was entitled to assess
for late completion.
Over a dissent, the CBCA held in
José
Gustavo Zeno that a broadly worded, general release of all
the contractor's claims (which closely followed a default
termination and was supported by consideration) did not preclude
the contractor from challenging the termination because it did
not specifically waive his right to challenge a government
claim.
In
AutoFlex, Inc., the CBCA held that the agency had fulfilled
bilateral agreement for a 12-month vehicle lease at a stated
monthly price and was not obligated beyond that term or price.
In
CAE USA, Inc., the CBCA rejected all the legal theories advanced by
the contractor to support its contention that its IDIQ contract
required the Government to permit it to retain (for the duration of the
contract) government-furnished
equipment relating to an aircraft program the Government had canceled
after contract award.
In
Asheville Jet Charter and Management, Inc., the CBCA held over for further proceedings
the question of whether the departure of the contractor's key employees
constituted a "strike" excusing its default under the
contract's commercial items
contract terms and conditions.
In
Marine Metal, Inc., the CBCA held that, because both the
solicitation and the contract for the sale of a ship contained
clear "as is/where is" condition clauses, the contractor was
precluded from recovering on a claim of an alleged
misdescription of the ship's weight.
In
Military Aircraft Parts, the ASBCA held that the
contractor was entitled to the full contract price for a
purchase order as damages for the Government's improper
rejection of the First Article, which would have been
acceptable but for damage to the item caused by the
Government's inspection.
In
Mach I AREP Carlyle Center, LLC, the ASBCA reaffirmed
the principle that "by law, no lease can compel the
[Government] to exercise option years that were not yet
funded at the time the lease was entered" and held that
the Government was not liable for the failure to exercise
the remaining option years on a building lease that was
terminated early in one option year due to a lack of
funding brought about by a government shutdown over a
budget dispute and, subsequently, was not reinstated.
In
BMC Contracting, LLC, the CBCA held that clear government
disclaimers in a timber sales solicitation and contract placed
all the risks as to the quality and quantity of available timber
on the contractor and precluded the contractor's claims for
negligent estimates or alleged government misrepresentations.
In
SecTek, Inc., the CBCA held that the contractor was not
entitled to a Service Contract Act price adjustment for higher
wages it paid its employees beginning with the first day of the first
option year pursuant to a new collective bargaining
agreement because those wages were not incorporated in a
wage determination applicable to the contract as of that
date. However, the CBCA subsequently granted the
contractor's
motion for reconsideration and dismissed the
appeal as one involving a dispute within the exclusive
jurisdiction of the Labor Department.
In
ASW Assocs., the CBCA dismissed the portion of the
appeal related to the contractor's contention that
the agency had interfered with or hindered the
contractor’s performance because the contractor failed to
provide any evidence to support that assertion despite
numerous requests during discovery.
In
CACI International, Inc. & CACI Technologies, Inc., a
decision involving contract interpretation, the ASBCA held
that the hazardous pay supplement of 35% of the
contractor's "basic compensation" rate applied to all
hours worked by the contractor's employees, including
overtime work.
In
King Aerospace, Inc., the ASBCA held that (in an
aircraft maintenance contract), the contractor was
entitled to recover its extra costs incurred because (i)
the condition of the government-furnished aircraft was
inferior to that represented in the contract, and (ii) the
government-furnished property listed in the contract was
often not delivered in a serviceable condition or in a
timely manner.
In
Financial & Realty Services, LLC,
the CBCA dismissed the contractor's claim and held that, in
a fixed-price task order to provide an individual to
perform property management services, the fact that the
employee left to work for the Government does not entitle
the contractor to payment for the months during which no
replacement was performing the required services.
In
Bullseye International SDVOB, Inc., the CBCA found no
basis for the contractor's claim that it was entitled to
recover merchant transaction fees incurred because the
agency had allegedly used government purchase cards in
amounts, and at intervals, that violated agency
regulations.
In
Douglas P. Fleming, LLC, the CBCA expressed its displeasure
with (a) the contractor's failure to track its actual costs of
allegedly extra work it knew at the time of performance would be
the subject of a dispute and (b) its reliance on unpersuasive
testimony that was often at odds with the sparse contemporaneous
record, and held, inter alia: (i) the jury verdict
method would be used to calculate a recovery where the
contractor's evidence was insufficient; (ii) the contractor's
claim for costs associated with responding to a cure notice must
be denied because the cure notice was justified by the
contractor's statements and actions threatening anticipatory
repudiation; (iii) claims for excess painting costs were not
justified because, under the rules of contract interpretation,
the contract required the contractor to paint all of the
disputed area for the contract price; (iv) a clear release in a
supplemental agreement precluded a subsequent claim for the
costs of administrative time incurred prior to a notice to
proceed; and (v) the contractor failed to present evidence that
it had performed extra touch-up painting work.
The
ASBCA sustained an appeal by
HCS, Inc. because the Government failed to present evidence
in support of its post-contract, unilateral 50% price reduction
for deleted work as a result of an earlier unilateral change
order.
In
Ft. McCoy Shipping & Services, the ASBCA denied claims for
various categories of costs because (i) the contract made the
contractor responsible for them, (ii) the contract contained no
provision for their recovery, (ii) they constituted ordinary
business expenses, or (iv) the contractor incurred them as a
volunteer after the contract had ended.
In
Bryant Commercial Postal, LLC, the PSBCA held that the
Postal Service, as the lessee, was responsible for the
costs of removing trash and graffiti from a building it
continued to pay rent on, but had abandoned.
In
Attenuation Environmental Co., the CBCA rejected all
the contractor's theories of recovery for lost profits
after the Government declined to exercise an option
because the Government had ordered (more than) the minimum
quantity under an IDIQ contract, which was all it was
required to do.
In
Native American Construction Services, LLC, the CBCA
denied a claim for breach of contract because the
contractor had not presented any evidence that would
permit the CBCA to determine the amount, if any, of
increased costs associated with the alleged breach.
Subsequently, the Board
denied the contractor's request for reconsideration
because it sought relief on a basis that was inconsistent
with the issue that had been originally litigated.
In
E Industry, Inc., the CBCA held that the purchaser's
failure to inspect the merchandise prior to bidding in an
online auction did not preclude its subsequent claim for
misdescription of the items in the auction.
In
Sylvan B. Orr., the CBCA, inter alia: (i) dismissed
the contractor's claim that it should have been offered work
under a BPA because the BPA did not commit the Government to
order any work; (ii) held that the contractor's signature
on a general release accompanying final payment on an order
barred the contractor's subsequent claim for actions that
occurred prior to the execution of the release; (iii) concluded
that the contractor had failed to prove it signed the release
under duress; (iv) dismissed a claim based on minor procedural
missteps by the Government in issuing a CPAR; and (v) held that
the contractor's challenge to the specifics in a CPAR was moot
because the Government, recognizing the contractor had not had
an opportunity to comment on the CPAR, never utilized (or acted
on) it for any purpose.
In
Ensign-Bickford Aerospace & Defense Co., the ASBCA
held that: (i) the Government had failed to meet its
burden to prove by a preponderance of the evidence that
its rejection of production lots was proper; and (ii) the
characteristics of an approved First Article do not
change, or make more stringent, the contract requirements
for subsequent production lots.
In
Creative Times Dayschool, Inc., the ASBCA held that
the contractor failed to offer adequate proof for any of
its contentions that: (i) the Government required paving
work beyond the original contract specifications; (ii) the
roofing specification was defective; (iii) the Government
unreasonably delayed roofing work; and (iv) the
Government changed the requirements regarding the fall
prevention system or the size of the mandatory management
team. However, the ASBCA held that the contractor was
entitled to remission of liquidated damages for the period
of time it took the parties to agree on a solution to a
problem that arose during construction.
In
Grunley Construction Co., on cross motions for summary
judgment on numerous issues, the CBCA held, inter alia,
that the Government was responsible for the contractor's
(and its subcontractor's) excess costs incurred because of
the Government's erroneous insistence (initially
supported, but ultimately rejected, by the DOL) that the
subcontractor was paying certain workers less than the
rates required by the Davis-Bacon Act.
In
R & G Food Services, Inc., the CBCA held that the
Government had not breached a mobile food service
company's contract after two fires merged into one by (i)
releasing the company from further work, and (ii)
consolidating service with another contractor that had
been working at one of the two fires before they merged.
In
Sea Shepherd Conservation Society, the CBCA denied an
auction winner's claim that, because the agency had
allowed another firm (which ultimately had been determined
to be ineligible) to bid in an auction, the winning bidder
was forced to bid higher for an item that it would have
had that other bidder not been permitted to participate.
The CBCA reasoned that the agency had followed all
applicable auction rules.
Partially granting cross motions for summary judgment, the
CBCA held in
Grunley Construction Co. that: (i) the Government was
liable for excess costs resulting from its requirement
that the contractor classify and pay workers in a higher
wage rate category than was required by the contract; and
(ii) for a differing site conditions claim, clause GSAM
552.243-71 allowed the contractor to recover a maximum
commission of 10%, and no overhead, on work performed by
its subcontractor.
In
Missouri Department of Social Services, the ASBCA held
that, under FAR 52.249-2(l), the contractor was entitled
to an equitable adjustment for its increased costs of
performing the remaining work, which were caused by the
Government's partial termination for convenience of a
requirements contract.
In
Tetra Tech Facilities Construction, LLC, the ASBCA
held that the contractor had established that the
unsuitable (saturated) subsurface soil it had encountered
during construction constituted a Differing Site
Condition.
The ASBCA denied an appeal by
ABC Data Entry Systems, Inc. because, as a matter of
law, the Government has no liability for a negligent
estimate of work on an indefinite-quantity contract.
In
Smart Way Transportation Services, the ASBCA rejected
the contractor's various theories of recovery because the Government had
satisfied its obligations by permitting the contractor to
invoice for the minimum guaranteed order quantity during the
base period under an ID/IQ contract. Subsequently, the
contractor's motion for reconsideration was
denied.
In a lengthy opinion concerning a delay and disruption
claim that was larger than the basic contract price and
was based primarily on alleged differing site conditions,
the CBCA denied the appeal by
Choctaw Transportation Co. for a host of reasons,
including, inter alia: (i) the absence of support
in the contract for the contractor's interpretation, (ii)
the contractor's failure to timely notify the Contracting
Officer of either changes or differing site conditions,
(iii) the fact that the contractor should have known of
the disputed conditions at the site from its pre-bid
investigations, (iv) questions concerning the credibility
of the contractor's testimony concerning its original plan
for performing the work, and (v) deficiencies in the
contractor's expert's legal analysis and his methods for
calculating the quantum of delays and impacts.
In
Akal Security, Inc., the CBCA denied the contractor's
claim for reimbursement of its liabilities to employees
under California law for providing insufficient wages and
benefits because: (i) the contract obligated the
contractor to comply with all laws; (ii) the Government
was not required to research those laws for the
contractor; and (iii) the Government did not interfere
with contractor's ability to comply with California laws.
In
1201 Eye Street, N.W. Assocs., LLC, the CBCA granted the
contractor's claim because: (i) the plain language of the
original lease between the contractor and the GSA established
the method of calculating yearly operating cost adjustments, and
the lease extension executed by the parties explicitly indicated
the original lease provisions would continue to govern; and (ii)
the Government's interpretation was contradicted by the prior
course of dealing between parties before dispute arose.
In
Ricoh USA, Inc., the ASBCA denied the contractor's
claim for the Government's use of fewer leased copiers
than the contractor had expected because the contract was
a requirements contract that clearly contemplated the
number of units might be reduced without any penalty, and
the executed contract did not include extraneous language
concerning, e.g., termination fees, that the
contractor had submitted in unsolicited parts of its
proposal.
In
MBD Maintenance, LLC, the PSBCA held that a release signed
by the contractor after the contractor was aware of the facts
giving rise to a mistake in bid claim barred that claim.
Terminations/Liquidated
Damages/Government Claims
In
Brent Packer and Myrna Palasi, the CBCA held: (i) it
lacked jurisdiction over appeals from terminations of BPAs
absent any allegation of mutuality of obligation because BPAs
are not contracts; (ii) the Board had jurisdiction over
appeals from terminations of individual call orders
issued under the BPAs because those call orders were
contracts; (iii) the termination of a commercial items
contract for alleged failure to comply with contract terms
requires a cure notice and an opportunity to cure; and (iv)
terminations based on alleged conflicts of interest made
without a prior cure notice were invalid.
In
Stop & Mail Etc., Inc., the PSBCA held that, although
the Postal Service had legitimate concerns with the contractor's
performance, it had failed to establish how a termination upon
only one day's notice was necessary to protect the Postal
Service's interests, which was the standard required by the
termination clause in the contract.
In
Olbeter Enterprises, Inc., the PSBCA held that the Postal
Service was not entitled to recoup payments it had made to a
contractor under a fixed-price contract for mail delivery
services between two facilities after the Postal Service closed
one of the facilities but inexplicably failed to terminate the
contract.
In
Highland Al Hujaz Co., Ltd, the ASBCA: (i) upheld a
termination for default issued immediately after the
contractor anticipatorily repudiated a material,
non-severable requirement of a contract by "positively,
definitely, unconditionally, and unequivocally refus[ing]
to continue providing temporary power without additional
fuel payments by the [G]overnment"; and (ii) held that the
Government's justifiable withholding of progress
payments was not an excuse for the contractor's refusal to
perform.
In
Derrick V. Greene, the PSBCA upheld default terminations
because the mail delivery contractor had refused to communicate
with Postal Service employees concerning various performance
issues and then, after he was denied access to the loading docks
as a result of those communication issues, failed to hire
substitute drivers, which resulted in a failure of performance
over an extended period of time.
In
Joseph Sottolano, the ASBCA upheld the termination for cause
of the United States Military Academy's head baseball coach for,
inter alia, having sexual relations with a female
staff assistant in his office during working hours.
In
Marshall's Electric, Inc., the ASBCA rejected all the
contractor's excuses and upheld a default termination based on
the contractor's failure to obtain the required bonding for the
project.
In
Third Coast Fresh Distribution, L.L.C., the ASBCA upheld a termination
for cause of a contract set-aside for small businesses after the SBA
determined the contractor was not small because it was not compliant
with the requirements of the nonmanufacturer rule.
In
Military Aircraft Parts, the ASBCA held that: (i) it lacked
jurisdiction over the contractor's claim that a contract
termination was a breach because the appeal had not been filed
within 90 days of the contractor's receipt of the termination
decision; (ii) because the cancellation of individual purchase
orders orders issued under that contract was not a government
claim, the Board did have jurisdiction over subsequent
contractor claims challenging those cancellations; but (iii)
those claims lacked merit because the contractor had not
delivered the required first article items on time.
In
Quality Trust Inc., the ASBCA upheld a default termination
based upon the contractor's failure to obtain the required
performance and payment bonds. Subsequently, the Board
denied the contractor's motion for reconsideration.
In
Universal Home Health and Industrial Supplies, Inc., the
CBCA: (i) dismissed the contractor's original appeals
from terminations for default as moot because the Government had
converted them to terminations for convenience; and (ii) denied
a
subsequently-filed appeal that the original terminations were made in bad
faith, because the Government had a reasonable basis to terminate and
the contractor had not responded adequately to the Government's request
for assurances. Subsequently, the Board
denied the contractor's motion for reconsideration.
The ASBCA upheld a partial default termination in
Lean Construction and Engineering Co. because the
contractor failed to complete the construction work
despite two extensions to the contract schedule and
several notices from the Government detailing the problems
with the work.
In
Rhodes Research, the ASBCA held that, in light of the
scant documentation submitted by the contractor to support
its convenience termination settlement proposal, the
Contracting Officer had fairly determined the percentage
of completion of the contract and the amount due the
contractor pursuant to FAR 52.212-4. Subsequently,
the contractor's motion for reconsideration was
denied.
In
Precision Standard, Inc., which involves the principle
of the contractor's duty to proceed pending the resolution
of a dispute, the ASBCA held that a default termination
was justified by the contractor's refusal to perform in
accordance with the Contracting Officer's directions and
to properly respond to cure notices after the Government
insisted on the use of what the contractor believed was
the incorrect welding standard, especially where (prior to
the termination) the contractor had not alleged that the
Government's action was a breach.
In
Puget Sound Environmental Corp., the ASBCA held that
the Government had not acted in bad faith in terminating a
purchase order for convenience and declining to exercise
additional options after the DOL made a preliminary
determination that the contractor failed to pay wages in
accordance with the Service Contract Act.
In
Bryan Concrete & Excavation, Inc., the CBCA denied an
appeal from a default termination because the contract
obtained by the contractor's false certification that it
was an eligible SDVOSB was void ab initio.
Subsequently, the Board (i) held it had jurisdiction over
the contractor's motion for reconsideration even though an
appeal to the CAFC was pending and (ii)
denied that motion.
In
Avant Assessment, LLC, the ASBCA converted a default
termination to one for convenience because the Government:
(i) failed to present any evidence of the existence of the
delivery schedule it claimed the contractor had not met;
and (ii) failed to show the contractor had delivered fewer
than the required number of items because the parties had
agreed to reduce the number of required items to only the
number the Government found acceptable.
In
DCX-CHOL Enterprises, Inc., the ASBCA denied the
contractor's motion for summary judgment to overturn a default
termination because the contractor failed to present evidence
for either of the two elements required by the so-called
DeVito rule to establish that the Government had waived the
contract delivery date.
In
Deas Construction, Inc., the ASBCA held that: (i)
interpreted as a whole, the contract required the
contractor to fabricate and provide a fully functional ISO
Stand and that the Government had not withheld superior
knowledge that the contractor's price was too low; and
(ii) after it terminated the contract for convenience
because the contractor was unable to complete the work,
the Government correctly determined that the contractor
had performed only 10% of the work and, therefore, was
limited to that percentage of the contract price.
In the consolidated appeals of
Cook Mail Carriers, Inc. and Patricia J. Sasnett, the PSBCA,
inter alia, upheld the termination of two contracts under
the Termination with Notice clause because, even though the
Contracting Officer was mistaken about why changes in
mail routes were needed, he had a right to terminate on 60 days
notice with or without cause, and he would still have
terminated the contracts and consolidated the routes if he had
known the correct facts, so he did not act in bad faith.
In
William Finley, although the PSBCA held it had jurisdiction
over an appeal involving a monetary claim that the Postal
Service declined to renew a contract due to racial
discrimination, the Board granted summary judgment in favor of
the Government because there was no evidence (beyond the
contractor's speculations) that the Postal Service abused its
discretion or acted in bad faith or from discriminatory motives
in declining to renew a contract so that mail routes could be
consolidated.
Costs, Defective
Pricing, and Cost
Accounting Standards (CAS)
In
Rex Systems Inc., the ASBCA discussed the proper analysis of
recoverable convenience termination costs under FAR
52.213-4(f) (the termination clause for simplified acquisitions
for other than commercial items), which permits recovery of a
percentage of the contract price reflecting the percentage of
the work performed prior to the notice of termination, plus
reasonable charges that have resulted from the termination.
In
Exelis, Inc., the ASBCA (i) dismissed the Government's CAS 404
claim because a building lease is not a tangible asset, which is
the type of asset covered by CAS 404, but (ii) permitted the
Government to proceed with its claim that the contractor's
alleged mischaracterization of lease expenses violated FAR
principles of allowable costs. Subsequently, the Board
denied the Government's motion for reconsideration.
In
Raytheon Co., Space & Airborne Systems, the ASBCA held that
the Contracting Officer had violated FAR § 30.602 and abused her
discretion by making a government claim for increased costs
associated with a change in cost accounting practices without
considering the materiality of the cost impacts associated with
the change pursuant to the criteria in 48 C.F.R. § 9903.305.
In
Alaska Aerospace Corp., the ASBCA denied the Government's
claim for recoupment of pension contributions because the
Government neglected to present any evidence that it
reimbursed the contractor for any of those costs.
In
Mission Support Alliance, LLC, the CBCA denied the
contractor's claim for the costs of purchasing SAFETY Act
insurance because: (i) the contractor failed to comply
with the contract requirement to notify the Contracting
Officer of the proposed purchase and obtain his prior
consent; and (ii) the Contracting Officer's determination
that the costs were neither "reasonable" (because the
contractor had incurred them without seeking the required
approval) nor "ordinary" (because the contract did not
require them and other similarly situated contractors did
not incur them) was supported in the record.
Delay/Eichleay
In
KBJ, Inc.,
the ASBCA held that, although a release in a modification barred
the contractor's subsequent claims for compensation and time due
to delays occasioned by encountering asbestos, the contractor
was entitled to 109 days of Eichleay overhead because the
Government's suspension of work resulted in a delay to the
critical path, which, in turn, resulted in the contractor's
standby costs in a situation where any contractor delays were
not on the critical path.
In
Air Services, Inc., the ASBCA awarded a contractor its delay
costs caused by the Government's "indecision and confusion" over
a project requirement.
In
Regency Construction, Inc., the CBCA held that a
contractor could recover some of its claimed costs
associated with delays in its subcontractor's access to
the work site caused by the presence of another contractor
because the Government had affirmatively warranted that
the other contractor would have vacated the site by the
date when the subcontractor was to begin work.
In
Contrack International, Inc., the ASBCA held that,
accepting the Government's contentions as true for
purposes of the contractor's summary judgment motion, the
contractor was not entitled to delay damages for a third
party's (the Afghan National Army's) delay in moving
vehicles off the contractor's worksite.
In a lengthy opinion concerning a delay and disruption
claim that was larger than the basic contract price and
was based primarily on alleged differing site conditions,
the CBCA denied the appeal by
Choctaw Transportation Co. for a host of reasons,
including, inter alia: (i) the absence of support
in the contract for the contractor's interpretation, (ii)
the contractor's failure to timely notify the Contracting
Officer of either changes or differing site conditions,
(iii) the fact that the contractor should have known of
the disputed conditions at the site from its pre-bid
investigations, (iv) questions concerning the credibility
of the contractor's testimony concerning its original plan
for performing the work, and (v) deficiencies in the
contractor's expert's legal analysis and his methods for
calculating the quantum of delays and impacts.
Quantum
In
BAE Systems San Francisco Ship Repair, the ASBCA held,
inter alia, that: (i) neither the Government's estimate nor
what similar work had cost other contractors would adequately
measure what the contractor should recover for its costs of
performing extra work unilaterally directed by the Government;
(ii) the contractor's accounting system was adequate to capture
its costs for the extra work; (iii) the contractor was obligated
to suspend work on the original contract items only after it had
received a written, unilateral order from the Contracting
Officer directing it to perform the changed work; (iv) the
contractor's hourly rate for the changed work was not limited by
a contract clause establishing the rate to be utilized in
"negotiating" changes because there were no such negotiations;
(v) the contract did not prohibit the contractor from recovering
overtime for performing the changed work; and (vi) a DCAA audit
report, while accepted as evidence, was not dispositive on the
issue of quantum--the responsibility for making that
determination remained with the Board.
In another
In
BAE Systems San Francisco Ship Repair decision, which involved
determining the appropriate equitable adjustment for extra work
in a vessel overhaul contract, the ASBCA held, inter alia,
that: (i) the contractor's advances to its subcontractor to
perform extra work and its agreement to pursue additional costs
on behalf of that sub were sufficient to satisfy the
requirements of the Severin doctrine; (ii) although the
contractor's initial claim submission was based on
estimates, its accounting system was adequate to
substantiate the actual costs incurred for the extra work;
(iii) the Contracting Officer was on notice from the
contractor's submissions that the contractor would require
overtime to perform the changed work and, having failed to
object, was bound by that interpretation; and (iv) the
Contracting Officer's "benefit of the bargain" approach
for determining the amount of the equitable adjustment was
inappropriate in this situation where the Board had
accepted the contractor's calculation of its actual costs.
In
Tucci and Sons, Inc., the CBCA addressed the proper
way to calculate extra costs under the "Differing Site
Conditions" clause and held that the fact that the
contractor's costs of performance were less than its bid
estimate was irrelevant in determining its excess costs
attributable to a differing site condition.
In
JDL Castle Corp., the CBCA denied the contractor's claims
because the contractor had not provided evidence of damages
caused by the Government's alleged delays, and because it was
implicitly seeking compensation for lost (i.e., delayed
commencement of) rental payments, which are not compensable
costs of performance.
In
PJB Jackson-American, LLC, the CBCA held that loss of
expectancy damages (i.e., the gross rent of the lease had
it been performed minus necessary expenses and then mitigated by
what the contractor would recover through a replacement lessee)
rather than damages based on the diminution in the future
sale value of the leased premises.
In
GSC Construction, Inc. decision, the ASBCA denied the
contractor's motion for summary judgment as to
quantum because the contractor's motion lacked proof.
In
Optimum Services, Inc., after the parties were unable
to agree on quantum, the ASBCA used the Measured Mile
Method to determine the amount owed to the contractor for
a differing site condition on a dredging contract.
Discovery/Procedure/Motion
Practice
In
Mission Support Alliance, LLC, the CBCA denied the
contractor's motion to strike the Government's Answer as
nonresponsive because (i) only notice pleading is
required, (ii) discovery is used to flesh out the parties'
positions, and (iii) the Contracting Officer's original
decision disallowing certain contractor costs contained a
detailed explanation of the Government's position.
n
JR Services, LLC, the CBCA found the Government's
one-page general denial in response to a 383-paragraph
Complaint in an appeal from a default termination to be
inadequate and ordered the Government to file responses to
the detailed factual allegations in the Complaint.
In
P.J. Dick Inc., the CBCA denied the Government's motion for
partial summary judgment that two specifications were not
defective (the contractor had alleged that they were)
because, although the two specification requirements at
issue were clear and unambiguous, material questions
remained as to why the contractor had not inquired
concerning a patent ambiguity before bidding and whether
it was possible to comply with both specifications.
In
Ralph Muhammad, the CBCA directed the Government to file the
Complaint in an appeal from a default termination that did not
provide the contractor with sufficient information as to the
reason for the termination.
In
Raytheon Co., the ASBCA denied the contractor's motion
to strike certain testimony at the hearing that allegedly
conflicted with a prior interrogatory answer by the
Government because the fact that the answer was
inadvertently incomplete did not make it a binding
admission and did not merit the sanction requested by the
contractor.
The ASBCA dismissed two appeals for failure to prosecute
after the contractors failed to respond to orders to propose a
schedule for further proceedings at the Board:
Ahjar Shat Alarab Albidhaa Co. and
Suodor Al-Khair Co - SAKCO for General Trading. In
Tokyo Co., the ASBCA dismissed an appeal for failure to
prosecute after the contractor failed to explain its contention
that its lack of communication with the Board was due to its
inability to access its yahoo.com email account for five months.
In
Elite Quality Services, LLC, the CBCA dismissed an appeal
for failure to prosecute after the contractor ignored
repeated orders to respond to the Government's dispositive
motion.
In
Kellogg Brown & Root Services, Inc., which involved the
analysis of the date when a claim accrues, the ASBCA denied the
contractor's motion for summary judgment alleging that the
Government's nonmonetary and monetary claims were filed more
than six years after the Government should have known of its
claims.
In
BAE Systems Tactical Vehicle Systems LP,
the ASBCA denied the
Government's motion to stay proceedings on an appeal from
the Government's TINA claim pending resolution of the
Government's FCA suit on the same dispute in District
Court. Similarly, in
Kellogg Brown & Root Services, Inc.,
the ASBCA denied the Government's motion to suspend or
dismiss (for an indefinite duration) appeals from the
denial of the contractor's claim for certain subcontractor
costs pending an FCA suit by the Government in District
Court. Subsequently, the Board
denied the Government's motion for reconsideration.
In
Sylvan B. Orr, the CBCA held it would not recognize a
non-attorney family member of a pro se non-attorney
appellant as the appellant's legal representative for
purposes of pursuing an appeal.
In
Crane & Co., the CBCA denied the contractor's motion
to amend its complaint to add two new claims for a
constructive change and ambiguity-of-specifications
because those new claims: (i) had never been presented to
the Contracting Officer for a decision, and (ii) had
accrued more than six years prior to the date the
contractor had submitted its only other claim to the
Contracting Officer. Coming at the issue from the opposite
direction, in
Optimus Technology, Inc., the CBCA denied the
Government's motion to amend its answer to include a
counterclaim that (i) did not relate to the invoices at
issue in the contractor's claim and appeal, and (ii)
had not been communicated to the contractor in a proper
Contracting Officer's decision that notified the
contractor of its appeal rights.
In
Public Warehousing Co., K.S.C., the ASBCA granted the
Government's motion to amend its Answer to add the
affirmative defenses of fraud in the inducement, first
material breach, the sovereign acts doctrine, the
political question doctrine, assumption of the risk, and
failure to mitigate, after finding that (i) the Government
did not unduly delay seeking to amend the Answer and (ii)
the contractor had not been prejudiced.
In
Perry Bartsch Jr. Construction Co., the CBCA denied
the Government's motion for summary judgment because of
ambiguities in (and unresolved factual issues concerning
scope of) the release language in a bilateral
modification.
In
Hawk Contracting Group, LLC, the CBCA denied the
contractor's request that the Board order the Contracting
Officer to issue a decision earlier than the date he had
previously identified for the expected decision, but, given the
agency's protracted delays in addressing the claim, the Board
indicated the contractor could treat any failure to meet the
predicted date as a deemed denial.
Finding that the Government's delay in disclosing its
affirmative defense of equitable estoppel was not done in
bad faith, the ASBCA allowed the Government to amend its
answer to include that defense in
ABB Enterprise Software, Inc. f/k/a Ventyx.
In
Public Warehousing Co., K.S.C., the ASBCA granted the
Government's motion to stay an appeal pending the
Government's criminal case against the contractor in the
Northern District of Georgia that involved many of the
same issues and factual allegations.
In
554 Bloomfield, LLC, the ASBCA denied the contractor's
tardy request to reinstate an oft-delayed appeal to the
Board's docket because the contractor offered no excuse
for its untimely request. Subsequently, the Board
denied the contractor's request for reconsideration.
Equal Access to Justice Act / Prompt
Payment Act
In
Comter Systems, Inc., the CBCA denied an application for an
EAJA recovery because, after the agency had paid the contractor
without the need for a decision by the Board, the contractor had
voluntarily withdrawn its appeal.
In
Avant Assessment, LLC, the ASBCA held the contractor
was entitled to an EAJA recovery after obtaining a summary
judgment converting a termination for cause to one for
convenience in an appeal that was factually distinct from
two other, still-pending, appeals that were consolidated
with it for purposes of judicial economy.
In
Tech Projects, LLC, the ASBCA denied the contractor's
request for an EAJA recovery (after the Contracting
Officer had amended his decision to concede quantum, and
the Board had dismissed the original appeal) because the
contractor was not a "prevailing party" that had obtained
either a decision or a consent judgment from the Board.
Subsequently, the Board
denied the contractor's motion for reconsideration.
In Impact
Assocs., Inc.,
the CBCA (i) reduced the contractor's EAJA claimed
recovery by the amount the contractor had spent on
proceedings at the ASBCA, which ultimately decided it
lacked jurisdiction, before proceedings were held at the
CBCA; but (ii) declined to reduce the EAJA recovery on the
basis that the contractor had recovered only a portion of
its claimed costs before the CBCA.
In
Systems Management and Research Technologies Corp.,
the CBCA allowed an EAJA recovery when the agency did not
dispute either the entitlement to, or the claimed quantum
of, the EAJA request.
In
Seven Seas Shipchandlers LLC, the ASBCA denied a
Prompt Payment Act interest claim because the payment
delays resulted from a dispute that had been litigated at
the ASBCA and that fell under the exception in the statute
for "a dispute between the head of an agency and a
business concern over the amount of payment or compliance
with the contract."
Court of Federal
Claims
Contract Disputes
Act (CDA) / Tucker Act / Jurisdiction / Standing
In
Nexagen Networks, Inc.,, a case involving both contract
claims and bid protest allegations, the court
held that: (i) it lacked jurisdiction over a CDA claim because
the plaintiff had not submitted a certified claim to the
Contracting Officer until after it had commenced its action in
court; (ii) under FASA, the court lacked jurisdiction over the
plaintiff's complaint against agency's corrective action in
cancelling the plaintiff's task order award; and (iii) the
plaintiff's challenge to a termination for default was moot
because the agency already had converted it to a termination for
convenience.
In
Nova Group/Tutor-Saliba, a Joint Venture, the court refused to dismiss a suit due to the plaintiff's
alleged failure to comply with the 20-day written notice
requirement regarding constructive changes in a construction
contract because the contractor demonstrated that the Government
had actual knowledge of the facts giving rise to the changes
claims.
In
Sheridan Transportation Systems, Inc., a decision labeled as
nonprecedential, the CAFC
held it lacked jurisdiction over an appeal from a CBCA decision
concerning a dispute arising under the Transportation Act (31
U.S.C. 3726) rather than the CDA.
In
Nova Group/Tutor-Saliba, a Joint Venture, the court
(i) denied the contractor's unopposed motion to transfer
its case to the ASBCA for consolidation with another
appeal involving the same contract because the case would
be time-barred there and involves wholly different facts,
but (ii) granted the contractor's alternative motion to
transfer the ASBCA appeal to the court.
In
DekaTron Corp., the court held that, although there
would be a difficult burden of proof, the contractor's
allegations of bad faith and a lack of independent
judgment underlying the Contracting Officer's decision not
to exercise an option were sufficient to withstand the
Government's motion to dismiss the suit.
In
Baistar Mechanical, Inc., the court: (i) held it lacked
jurisdiction over a contractor's quantum meruit claim;
(ii) dismissed claims for extra work based on directions
received from the Contracting Officer's technical representative
(because the contract specifically stated only the Contracting
Officer had the authority to order changed work), except claims
for allegedly emergency work requirements, which might
constitute an exception to the general rule; (iii) dismissed
claims related to the Government's alleged failure to order
certain work because the contract did not contain minimum order
requirements or require the Government to order the disputed
work; and (iv) refused to dismiss other claims based on a
contract ambiguity where the contractor had alleged a course of
dealing supporting its interpretation.
In
Federal Contracting, Inc. d/b/a Bryan Construction, Inc.,
the court held that: (i) especially because they did not include
a sum certain regarding alleged breaches of contract, a
contractor's responses to the Government's cure notice and the
Government's notice of termination did not constitute CDA
claims, and the default termination, itself, was not a decision
on those alleged claims; but (ii) the contractor's written
request that the Contracting Officer formally withdraw an
unsatisfactory performance evaluation and the Contracting
Officer's subsequent denial of that request constituted a CDA
claim and a decision on that claim.
in
Bryndon Fisher, the court refused to dismiss a suit claiming
that a software glitch in the Government's PACER system
overcharges users for copies of certain HTML-formatted
documents.
In
Claude Mayo Construction Co., which involved a dispute
over the propriety of a default termination, the court dismissed: (i) counts of the
complaint alleging (a) interference with the contractor's
ability to secure other contracts and (b) unjust
enrichment, because they were outside the court's
jurisdiction, and (ii) another count alleging breach of
contract because the contractor had not first submitted a
CDA claim for breach to the Contracting Officer.
In
California Department of Water Resources, the court held that certain agreements for the operation
and maintenance of water storage facilities in California were
not contracts within the coverage of the CDA and, therefore,
dismissed the plaintiff's claims for breach of contract.
In
Rocky Mountain Helium LLC, which involved a non-CDA
contract dispute, the CAFC: (i) affirmed the CoFC's
holding that a suit challenging the 2004 termination of a
helium extraction contract was untimely under the six-year
limitations period of 28 U.S.C. 2501; and (ii) reversed
the CoFC's holding that a subsequent Settlement Agreement
between the parties was not "money-mandating" under the
Tucker Act and, therefore, that the CoFC lacked
jurisdiction over a claim for the breach of it. The
appeals court reasoned in part as follows: "Where there is
a breach of a government contract, 'as with private
agreements, there is a presumption in the civil context
that a damages remedy will be available upon the breach of
an agreement."
The court dismissed a suit by
Zafer Taahhut Insaat ve Ticaret, A.S. because the
contractor had not requested a Contracting Officer's
decision on its underlying REA.
In
ASI Constructors, Inc., the Government whiffed on all its
efforts to have the contractor's claims dismissed summarily, and
the Court of Federal Claims held that: (i) it had jurisdiction
over issues that were clearly described in the legal memorandum
that formed part of the claim originally submitted to the
Contracting Officer for decision; (ii) the contractor's
differing site conditions claim involved questions of fact
regarding the contract as a whole and was not subject to summary
dismissal for failure to state a claim; and (ii) the
contractor's claims based on superior knowledge, breach of
the duty of good faith and fair dealing, and misrepresentation
all were sufficient to withstand motions to dismiss.
Changes/Breach/Contract
Interpretation/Defective Specs/Authority
In
Ameriserv Trust and Financial Services Co., the court held
that the Government had breached the express warranties in a
subordination agreement.
In
Northwest Title Agency, Inc., the court dismissed a
breach-of-contract action based on the allegedly improper
disallowance of closing fees because the contract
unambiguously prohibited such fees in the situation
involved in this dispute.
In
Evie's Catering, Inc., the court held that
an amount stated in a task order to supply meals was,
unambiguously, only an estimate and not a guaranteed price.
In a decision that
may herald another one with
far-reaching implications, the court indicated
in
Tabetha Jennings that boilerplate clauses in standard Postal
Service daily mail transportation services contracts likely are
not supported by consideration and are unenforceable because
they impose on contractors an open-ended and burdensome
financial obligation in order to dispute Postal Service
decisions concerning the contract.
In
Pioneer Reserve, LLC, the court held that, although the
plaintiff had established the Government had breached the
contract, it failed to prove any damages resulting from the
breach.
In
Certified Construction Co. of Kentucky, LLC, the court
held that two disputed contracts were requirements
contracts, in part because, although standing alone, the
contract note quoted below could be read as either the
contractor or the Government advocated, by taking
into consideration the contracts as whole, the italicized
(by me) portion of the note should be read to modify
all four items in the list that precedes
it (as the contractor contended), rather than just the
immediately preceding phrase (as the Government had
contended): "[The Government reserves the right to]
perform the work included in this contract with in-house
personnel, Job Order contracting, troop labor, or by
another contract where concrete placement, asphalt
surface treatment, or pavement marking is incidental to
other work.”
In
Financial & Realty Services, LLC, the court held that
the plaintiff's failure to provide a project manager to
perform the contract services for a period of time after
its original project manager resigned in mid-performance
was not excused by the time required for the Government to
screen the new candidate the contractor offered to fill
the vacant position, and thus the Government's failure to
pay for work during that time period was not a breach of
contract.
In
Meridian Engineering Co., the court held
that, because the Government's actions, including suspending the
work, were addressable under the Suspension of Work and Changes
clauses, the contractor was entitled only to an equitable
adjustment, not breach damages, and the court then made
extensive factual findings and legal conclusions concerning
various specific elements of the claimed equitable adjustment,
e.g., home office overhead, interest, and tool costs.
Terminations
In
Securiforce International America, LLC, the court held that, although a partial termination for convenience
was improper because the Contracting Officer testified she had
not exercised her own independent judgment in issuing it, the
contractor had not established that the termination for
convenience or any other alleged government actions or breaches
excused its subsequent failures to perform or invalidated the
subsequent default termination of the contract.
In
Boarhog LLC, the court held that the
agency's convenience termination of the plaintiff's contract (as
part of corrective action in response to an agency-level bid
protest by another firm) did not constitute a breach, and, even
if it had, the contractor could
not show any compensable damages because the termination had
occurred before it had performed any work or incurred any costs.
All this was especially true because, as a result of the
contractor's protest against the cancellation, the agency had
subsequently taken additional corrective action and awarded it a
second contract that was identical to the original award.
Discovery,
Evidence, Procedure
In
Northrop Grumman Systems Corp., although (at least for the
time being) the court denied the plaintiff's
motion for sanctions for spoliation based on the Postal
Service's tardy imposition of a litigation hold preserving
documents for possible litigation after the contractor's
submission of a comprehensive REA, the court did impose
sanctions on the Postal Service (preclusion of the use of
certain documents and reimbursement of a portion of the
plaintiff's attorneys' fees) as a result of the Postal Service's
unreasonable delays in the production of documents.
In
Securiforce International America, LLC, the court
denied the contractor's motions for sanctions as a result
of the Government's alleged failures to provide adequate
discovery responses.
In
Tender Years Learning Corp., the court of
denied the Gvernment's motion to dismiss (and overruled its
objections) and allowed the contractor: (i) to amend its
Complaint to eliminate bid protest allegations and allege only
implied-in-fact contract damages; and (ii) to bifurcate the
issues of entitlement and quantum.
EAJA
In its latest win in this
decade-plus long case,
SUFI Network Services, Inc. convinced the court that it was entitled to its attorneys fees at full law
firm rates because its position was substantially justified and
there were special circumstances entitling it to an upward
adjustment of EAJA's statutory cap on hourly rate.
In
The Meyer Group, Ltd., the court denied the contractor's
EAJA application because: (i) the Government's position in the
underlying litigation was substantially justified given the lack
of precedent on an unusual issue and the contractor's overly
aggressive interpretation of the underlying agreement; and (ii)
special circumstances rendered an EAJA award unjust because the
case did not involve any public policy issues or any
violations by the Government of a law or regulation, but rather
the consequences of unfortunate Government missteps in entering
a disadvantageous contract drafted by the plaintiff.
Court of Appeals for
the Federal Circuit
Jurisdiction/Standing/Res
Judicata
In
Guardian Angels Medical Service
Dogs, Inc., the CAFC (i)
reversed the CoFC's prior decision that
an appeal from a default termination was untimely and (ii)
held that the Contracting Officer's request for additional
information from the contractor after the contractor had
requested reconsideration of the Contracting Officer's
prior decision terminating a contract for default meant
the original decision was not final and did not become so
(and, therefore did not start the appeal clock running)
until the Contracting Officer subsequently informed the
contractor she would not reconsider her decision after
all.
In what was probably the final chapter in the
SUFI Network Services, Inc., dispute, the CAFC held that the Government had no right to
appeal an ASBCA decision that the contractor had accepted in a
case (one of the last) governed by the Wunderlich Act,
rather than the CDA.
In
Kellogg Brown & Root Services, Inc., an important decision
concerning the CDA's six-year limitations period for submission
of a claim, the CAFC
reversed the ASBCA and held that a contractor's claim sponsoring
its subcontractor's termination claim did not "accrue"
until it had developed sufficiently to be presented in a sum
certain and, therefore, was not barred by the limitations
period, even though the claim was not submitted to the
Government until long after the termination, following a lengthy
set of disputes between the sub and the prime and a false start
in which the contractor had forwarded one iteration of the claim
to the Government without certifying it.
In
Sheridan Transportation Systems, Inc., a decision
labeled as nonprecedential, the CAFC held it lacked
jurisdiction over an appeal from a CBCA decision
concerning a dispute arising under the Transportation Act
(31 U.S.C. 3726) rather than the CDA.
In
Pacific Gas and Electric Co.,
et al., the
CAFC affirmed the CoFC's dismissal of
a breach of contract suit because the plaintiffs did not have
privity of contract with the Government and, therefore, lacked
standing.
Changes/Breach/Contract
Interpretation
In
System Fuels, Inc., et al., the CAFC reversed the CoFC and
held that the plaintiff-contractors were entitled to recover
their costs of loading spent nuclear fuel into storage casks as
one element of damages for the Government's partial breach of
its spent nuclear fuel contracts.
In
DG21, LLC, the CAFC
affirmed the ASBCA's prior decision denying a contractor's claim
because the contractor, in agreeing to pay the prevailing rate
for fuel in a fixed-price contract, had assumed the risk of
rising fuel prices, and those rising prices were not a change to
the contract.
In
Northrop Grumman Computing Systems, Inc., the CAFC affirmed the CoFC's decision
that the contractor had failed to establish any damages as a
result of the Government's alleged breach of a delivery order (i.e.,
allegedly failing to use its best efforts to secure funding for
the option years) because, without notice to the Government, the
contractor had assigned all its rights under the order to a
third party in exchange for a payment that equaled the
contractor's expected profit from the full term of the order,
including options.
In
Zafer Taahhut Insaat ve Ticaret A.S., the CAFC
affirmed the prior
CoFC decision and held that: (i) there was no evidence
the Government had denied the contractor's request for a
time extension, which was a required element of the
contractor's constructive acceleration claim; and (ii) the
contractor failed to establish that the Government's
negotiations with Pakistan to re-open one contract route
amounted to fault on the part of the Government
establishing a constructive change.
Fraud
In
Laguna Construction Co., the CAFC affirmed the ASBCA's
prior decision, holding that the contractor's Chief
Operating Officer's guilty plea for accepting kickbacks
from subcontractors demonstrated a prior material breach
of the "Allowable Cost and Payment" clause of the contract
at issue and was a valid defense to the contractor's claim
for costs disapproved by a DCAA audit.
Discovery, Evidence, Procedure
The CAFC's decision in
Western States Federal Contracting, LLC (albeit
nonprecedential) raises may be problematic. At the time (April 29,
2013) the contractor originally appealed to the CBCA from a
deemed denial of its claim, it was not in good standing in its
state of incorporation (Delaware), which is a requirement for
maintaining an appeal. Although the Board gave it numerous
chances to correct the problem, it did not do so until sometime
after the CBCA
published a decision dismissing the case on February 11,
2014. The contractor appealed to the CAFC from the CBCA's
dismissal, and then (at the Government's request) the court
vacated the Board's original dismissal so that the Board could
consider two specific issues (one having to do with whether the
company should have been permitted to proceed as an
unincorporated association). As instructed, the CBCA
reviewed those two issues and, once again,
dismissed the contractor's case. The contractor again
appealed the dismissal to the CAFC. Now, the CAFC reverses again
because the company is finally in good standing with the state
and the CBCA's second decision was not entitled to rely on the
company's lack of good standing at the time of the original
dismissal because the court previously had vacated the
Board's original decision, rendering it a nullity.
This
website links to resources on the web concerning
government contracting. It is not intended to provide
legal advice. Moreover, I do not vouch for the
completeness, currency, or accuracy of the sites to which
it links. If you have comments, suggestions for links,
or corrections, please
email me.
|