Stan Hinton

Home
Contact Me
 
Current Blog
2023 Blog
Courts
GAO
Boards
SBA
Statutes
Regulations
Directives
Agency Sites
More Agencies
Periodicals
Research
 

Recent Federal Circuit Contract Disputes Decisions (2000-Present)



See also Winstar Decisions

Click on any case name below to link directly to the decision

 

2024

Sage Acquisitions LLC v. Sec'y of HUD, No. 2023-1907 (Oct. 18, 2024) (affirms prior CBCA decision denying relief to asset manager contractor for T for C costs and breach damages under agency's Real Estate Owned ("REO") disposition program because: (i) contracts at issue clearly stated they were IDIQ contracts with a guaranteed minimum, and contract sections referring to "all" work in a geographic area did not mean they were requirements contracts because those sections merely described manner in which work would be performed and would have conflicted with section clearly giving Government right to unilaterally reduce the scope of contractor's geographical region to zero and to utilize other contractors had they been interpreted as requirements contracts; (ii) contract provision stating that task orders would be issued on a yearly basis meant that task orders would be issued once per year, not that each task order must provide for a performance period of 12 months, and even if that were what it meant, Government satisfied IDIQ requirement by ordering the guaranteed minimum; and (iii) the Government did not breach the contract by assigning some asset management work to non-REO alternatives because that was specifically contemplated by the contract and was done for the legitimate business purpose of reducing costs rather than avoiding the Government's responsibilities under this contract)

The Boeing Co. v. United States, No.  2023-1018 (Oct. 4, 2024) (reverses prior CoFC decision; CoFC has jurisdiction over (i) suit challenging Contracting Officer's decision demanding reimbursement for alleged increased costs resulting from changes to contractor's cost accounting practices even if the gravamen of the contractor's complaint was a challenge to the validity of a regulation (in this case FAR § 30.606) because the case is basically a contract dispute governed by the dispute resolution provisions of the CDA and (ii)  contractor's alternative illegal exaction claim pursuant to 28 U.S.C. § 1491(a)(1))

American Medical Equipment, Inc., Servant Health, LLC, Noble Attorney, LLC, Transcendence, Inc. v. United States, Nos. 2022-2193, -2194 (Sep. 30, 2024)  (nonprecedential; affirms prior CoFC decisions upholding default terminations of contracts to deliver nitrile examination gloves (PPE) during COVID because the contractors failed to provide actual evidence of excusable delays, contractor failed to provide documentation that the gloves it tendered were acceptable substitutes for contractually specified items, and the "brand name or equal" solicitation provision only allowed for substitutions in proposals, not after proposals quoting the appropriate gloves had been submitted and accepted; Contracting Officer did not breach duty of good faith and fair dealing by terminating the contracts for default due to lack of timely delivery)

ACLR, LLC v. United States, No. 2023-1190 (Sep. 27, 2024) (nonprecedential; affirms prior CoFC decision denying contractor's claims for breach of contract, breach of the implied covenant of good faith and fair dealing, and recovery of certain termination-for-convenience damages because (i) terminations relating to two audits constituted retroactive, constructive terminations for convenience, consistent with the FAR 52.212-4(l) clause incorporated into the task order and, thereby, into the contract; (ii) contractor presented no evidence in support of its assertion that the Government entered the contract in bad faith with no intention of honoring it; (iii) no breach of implied covenant of good faith and fair dealing because Government did not expand contractor's duties beyond those contained in the contract; (iv) under T for C, contractor was not entitled to recover a contingency fee that was to be based on work that had not progressed to the point that such a fee would have been earned at the time of the termination)

Contrack Watts, Inc.-Uejo Kogyo K.K v. Sec'y of the Army, No. 2023-1373 (Sep. 16, 2024) (nonprecedential; upholds prior ASBCA decision dismissing appeal by joint venture because underlying claim had not been submitted by a party authorized to bind the joint venture)

Petro Mex, LLC v. United States, No. 2023-1848 (Sep. 12, 2024) (nonprecedential; reverses prior CoFC decision that claim was barred by CDA's six-year limitations period because breach of contract claim for wrongful termination could not have accrued until the actual termination)

International Development Solutions, LLC v. Sec'y of State, No. 2022-1922 (June 26, 2024) (affirms prior CBCA decision; no evidence that taxes for which contractor seeks reimbursement were actually assessed against the contractor or paid by it (as opposed to entities higher up in its business structure) or were allocable to the task orders at issue)

MPG West, LLC v. Sec'y of Defense, No. 2023-1430 (May 17, 2024) (nonprecedential; in contract for provision of fresh fruits and vegetables to commissaries in Korea and Japan, affirms ASBCA's findings that contract gave contractor discretion whether to use local sources or to import produce and (if contractor chose to import) it was required to follow applicable regulations; Government was not required to examine possible price consequences of new contract model and did not undertake to do so; DCAA did not act in bad faith in weekly pricing meetings; remands for further proceedings to determine whether requirement to use certain vendor for bagged salads and then refusing to pay its prices (as too high) could be a breach because there was no local sourcing for its products)

Siemens Government Technologies, Inc. v. Sec'y of the Navy, No. 2022-2240 (May 8, 2024) (nonprecedential; affirms prior ASBCA decision; claimed costs were not incurred in connection with actual contract award; rejects argument is that because the Government issued a task order authorizing energy conservation work at some sites, it thereby became liable for the proposal development costs contractor incurred at all of the sites; no claim for breach of implied duty of good faith and fair dealing in absence of contract; no claim based on superior knowledge where claimed actions did not result in contract award)

Jemison & Partners, Inc. v. Sec'y of the Army, No. 2023-1773 (Apr. 16, 2024) (nonprecedential ; affirms prior ASBCA decision that contractor was to be paid for actual quantity of topsoil placed as opposed to lump sum based upon estimate of how much would be required)

BCC-UIProjects-ZAAZTC Team JV v. Sec'y of the Army, No. 2022-2143 (Mar. 27, 2024) (affirms prior ASBCA decision dismissing appeal for lack of jurisdiction because the person who submitted the claims was not authorized to do so on behalf of the contractor)

AVUE Technologies Corp. v. GSA, HHS, No 2022-1784 (Mar. 6, 2024) (reverses and remands prior CBCA decision that it lacked jurisdiction, holding that the plaintiff's allegation that it had a contract with the Government was sufficient to survive a challenge to jurisdiction)

Nauset Constr. Corp. v. Sec'y of the Army, Nos. 2021-2305, 2022-1853 (Mar. 4, 2024) (affirms prior ASBCA decision that (i) contractor was not prejudiced by lack of notice of specific appeal rights notice in Contracting Officer's letter terminating contract for default where the letter directed the contractor to the FAR clause that contained those appeal times and (ii) Government's conduct after issuing default termination did not vitiate it because the contractor could not have reasonably concluded the Contracting Officer was reconsidering the termination decision)

United Communities, LLC v. United States, No. 2022-2074 (Jan. 12, 2024) (affirms prior CoFC decision denying plaintiff's motion for enlargement of time to file late notice of appeal to CAFC because there was no showing of excusable neglect)

2023 

Nova Group/Tutor-Saliba v. United States, No. 2022-1740 (Dec. 11, 2023) (affirms prior CoFC decision that contractor failed to prove existence of either Type 1 or Type 2 differing site condition; CAFC reviews CoFC's application of parol evidence rule de novo as a question of law rather than a rule of evidence; evidence Government submitted related to fully integrated agreement was not introduced to vary that agreement, as would be prohibited by parol evidence rule, but to support its contention that the agreement settled the issue; reference in CoFC footnote to design-build contract was not the basis for its reason or its decision and, therefore, cannot be basis to overturn it)

ECC Int'l Constructors, LLC  v. Sec'y of the Army, No. 2021-2323 (Aug. 22, 2023) (reverses prior ASBCA decision; CDA's sum certain requirement is not a jurisdictional issue; it is a requirement that the Government may forfeit its right to object to if it waits too long to object)

Dept. of Transportation v. Eagle Peak Rock & Paving, Inc., No. 2012-1837 (June 6, 2023) (reverses prior CBCA decision overturning default termination; CBCA focused on whether Contracting Officer had considered required factors in making default decision rather than a de novo review of the propriety of the termination)

Lockheed Martin Aeronautics Co. v. Sec'y of the Air Force, No. 2022-1035 (Apr. 25, 2023) (Contracting Officer's unilateral determination of price of Undefinitized Contract Action is not a government claim under the CDA that can be appealed by the contractor)

Sec'y of Defense v. Raytheon Co, Raytheon Missile Systems No. 2021-2304 (Jan. 3, 2023) (reverses prior ASBCA decision; contractor's incurred-cost submissions accounted only for unallowable costs incurred during regular hours and ignored after-hours lobbying and, therefore, did not accurately reflect the proportion of time that contractor's employees spent on after-hours unallowable lobbying activities)

2022  

E&I Global Energy Services, Inc. v. United States, No. 2022-1472 (Dec. 30, 2022) (reverses prior CoFC determination dismissing claim for improper default termination; contractor should be allowed to develop case that failure of sureties to pay subcontractors necessitated its efforts to do so, which excusably delayed the work; affirms all other holdings by CoFC, including that Government did not breach implied duty of good faith and fair dealing and did not fail to disclose superior knowledge because contractor failed to establish that it was misled as to status of payments to subcontractors)

Carmazzi Global Solutions, Inc. v. Commissioner of Social Security, No. 2021-2035 (Dec. 28, 2022) (no jurisdiction over appeal filed more than 120 days after appellant received a copy of CBCA's decision)

Supreme Foodservice GmbH v. Director of the Defense Logistics Agency, No. 2021-1965 (Dec. 5, 2022) (affirms prior ASBCA decision; Government did not waive its defense (contractor's prior material breach) which barred contractor's claims against Government; without valid underlying contractor claim, contractor cannot recover CDA interest on Government's alleged over-withholding)

Microtechnologies LLC dba MicroTech v. United States Attorney General, No. 2021-2169 (Jul. 28, 2022) (affirms prior CBCA decision that contractor was not entitled to price of software maintenance agreement for option year following T for C because it had purchased three year agreement at beginning of base year without any requirement to do so with no assurance options would be exercised so the cost of the software maintenance contract did not "result" from the termination) 

Zafer Constr.Co. v. United States, No. 2021-1547 (July 18, 2022) (reverses prior CoFC decision (holding that underlying document did not request a Contracting Officer's final decision and, therefore, was not a claim) because document "impliedly" requested final decision)

U.S. Aeroteam, Inc. v. United States, No. 2021-2272 (July 5, 2022) (affirms prior CoFC decision denying claims; no constructive change or cardinal change because Government did not order extra work but merely approved idea contractor had initiated and proposed; lower court's erroneous suggestion that the contractor must show a constructive change order authorized a change in contract price was harmless error because there was no order at all; no commercial impracticability where supplier just raised price of parts and contractor chose a different route rather than to pay that increased price)

GSC Constr., Inc. v. Sec'y of the Army, No. 2021-1803 (May 2, 2022)  (nonprecedential; affirms prior ASBCA decision upholding termination for default because: (i) Government did not breach contract by requiring contractor to remove and replace soil since contract clearly required it to do so; (ii) contractor not entitled to time extension due to Government's review of drawings under allegedly wrong edition of governing specification because contractor had used incorrect edition in accomplishing its work; and (iii) agency had not waived the project's completion date because it specifically and repeatedly reserved its rights to enforce the completion date and contractor missed extended date by which Government had given it a chance to complete project)  

CSI Aviation, Inc. v. DHS, GSA No. 2021-6030 (Apr. 14, 2022) (reverses prior CBCA decision; contract expressly incorporated contractor's standard terms and conditions by reference)

Lebolo-Watts Constructors 01 JV, LLC v. Sec'y of the Army, No. 2021-1749 (Feb. 18, 2022) (nonprecedential; affirms prior ASBCA decision; contract was patently ambiguous as to whether contractor was to furnish circuit breakers (even though they were low cost items they were important to the project) and contractor failed to inquire prior to bidding; subcontractors' pass through delay claims were (i) based on delays associated with circuit breakers, which were attributable to the contractor, not the Government, (ii) concurrent with contractor-caused delays, and/or (iii) waived in a bilateral modification)

Aspen Consulting, LLC v. Sec'y of the Army, No. 2021-1381 (Feb. 9, 2022) (reverses prior ASBCA decision; Government breached contract by making payments to an account other than the one listed in the CCR database, which was the account required by the "Payments" clause (FAR 52.232-33); remands case to ASBCA to decide Government's affirmative defense of payment, i.e., whether the contractor had benefitted from the funds paid to wrong account)  

2021

Tolliver Group, Inc. v. United States, No. 2020-2341 (Dec. 13, 2021) (vacates prior CoFC decision because claim for breach of implied warranty of performance presented by contractor at CoFC was materially different from allowable cost claim it had presented to the Contracting Officer, so CoFC lacked jurisdiction over claim)

JKB Solutions and Services, LLC v. United States, No. 2021-1257 (Nov. 17, 2021) (reverses prior CoFC decision; even though FAR 52.212-4 ("Termination for Convenience") was incorporated by reference in contract, it was inapplicable because it is not applicable to service contracts and, therefore, could not be used as a basis for Government's position that it had constructively terminated the contract for convenience)

Thomas Nussbaum v. United States, No 2020-1170 (Nov. 17, 2021) (nonprecedential; affirms prior COFC decision that suit brought nine years after Contracting Officer's decision on claim was time-barred)

7800 Ricchi LLC v. United States, No. 2021-1704 (Nov. 16, 2021) (nonprecedential; affirms prior CoFC decision that duty of good faith and fair dealing did not attach to "Renewal Options" provision because it expired before the conduct the plaintiff complained of and was not the basis for the parties' discussions concerning a short term lease extension)

Billie O. Stone dba Stobil Enterprise v. Sec'y of the Air Force, No. 2020-1233 (Oct. 19, 2021) (nonprecedential; dismisses appeal of ASBCA's denial of claim and upholding of termination; no jurisdiction over appeal because contractor failed to raise any non-frivolous allegations to support its contention that the Board's decision was fraudulent)

Billie O. Stone dba Stobil Enterprise v. Sec'y of VA, No. 2020-1732 (Oct. 18, 2021) (nonprecedential; affirms CBCA's grant of summary judgment in favor of Government; contractor failed to present evidence of the actual increase of  applicable wages and fringe benefits that it had made to comply with the applicable DOL Labor wage determination, as required by FAR 52.222-43) 

Triple Canopy, Inc. v. Sec'y of the Air Force, No. 2020-2165 (Sep. 29, 2021) (reverses prior BCA decision dismissing claims as time-barred because Board erred in determining date that claims accrued; under FAR 52.229-6 ("Taxes—Foreign Fixed-Price") clause, contractor was required to appeal an assessment before taking further steps, so claim did not accrue when that assessment was initially made)

Starwalker PR LLC v. Sec'y of the Army, Sec'y of Defense, No. 2020-2024 (Sep. 22, 2021) (nonprecedential; affirms concurring opinion in prior ASBCA decision; contract unambiguously required the backhaul (return trip) movement of trucks to be directed by the Government on an Logistics Movement Request (LMR) or Transportation Movement Request (TMR) in order to be compensable)

Coastal Park LLC, Meyer Landau v. United States, No. 2020-1687 (Aug. 18, 2021) (nonprecedential; affirms prior CoFC decision that contractor not entitled to return of deposit after it defaulted on agreement to purchase property from Government)

Catherine Kurkjian v. Secretary of the Army, No. 2020-2201 (Aug. 11, 2021) (nonprecedential; affirms prior ASBCA decision; no error in Board's conclusions that: (i) Government did not terminate base year of contract because it was substantially complete and Government had offered to pay contractor the balance owing; (ii) Government was not required to give contractor cure notice because it had not terminated contract; (iii) Government did not breach contract or act in bad faith by declining to exercise option;  (iv) contractor not entitled to lost profits for unexercised options)

NOAA Maryland, LLC v. GSA, No. 2020-1548 (May 13, 2021) (reverses prior CBCA decision; contract interpretation; reading two successive sentences of lease provision together, second sentence did not exclude a tax from being a reimbursable "real estate tax" whenever it was a "future tax," i.e., a tax imposed after the lease (or its extension) was entered into)

Pacific Coast Community Services, Inc. v. United States, No. 2020-1219 (Apr. 30, 2021) (nonprecedential; affirms prior CoFC decision; contractor was required, but failed, to prove damages as a result of Government's constructive change)

Pacific Coast Community Services, Inc. v. United States, No. 2020-1815 (Apr. 30, 2021) (nonprecedential; affirms prior CoFC decision; contract was for productive hours of work delivered to the Government, which meant that Government could deduct for hours not delivered)

Future Forest, LLC v. Sec'y of Agr., No. 2020-2039 (Apr. 15, 2021) (nonprecedential; affirms prior CBCA decision; Government did not breach implied duty of good faith and fair dealing by failing to order more than the minimum guaranteed quantity in ID/IQ contract)  

Creative Management Services, LLC dba MC-2 v. United States, No. 2020-1449 (Feb. 26, 2021) (affirms prior CoFC decision that suit not brought within 12 months of Contracting Officer's decision on government's claim should be dismissed as time barred; CDA's requirement of a sum certain does not rule out use of qualifying words such as "approximately" so long as the amount of the Government's claim is readily ascertainable by the contractor)

P.K. Management Group, Inc. v. Sec'y of HUD, No. 2020-1260 (Feb. 4, 2021) (affirms prior CBCA decision because contract's plain meaning comports with Board's analysis) 

2020

BGT Holdings LLC v. United States, No. 2020-1084 (Dec. 23, 2020) (affirms portion of the prior CoFC decision dismissing contractor's claim for breach of the duty of good faith and fair dealing, but vacates and remands portions of prior decision that had held that, by agreeing to a nonstandard changes clause unique to the Naval Surface Warfare Warfare Center Carderock Division, the contractor had waived its claims for constructive change through ratification, official change through waiver, and breach for failure to provide an equitable adjustment)

The Boeing Co. v. Secretary of the Air Force (Dec. 2020) (reverses prior ASBCA decision; DFARS 227.7103(f) applies only to markings on technical data that limit the Government's rights)

McLeod Group, LLC v. United States, No. 2020-1389 (Dec. 17, 2020) (nonprecedential; affirms CoFC's prior dismissal of case for lack of jurisdiction because the BPAs at issue were not "contracts" with the United States, lacking mutuality of both intent and consideration)

Kellogg Brown & Root Services, Inc. v Sec'y of the Army, No. 2019-1683 (Sep. 1, 2020) (affirms prior ASBCA decision on narrow basis that contractor did not establish its claimed costs were reasonable; dissent argues case should have been remanded to ASBCA to investigate that issue because it had not been briefing and argued thoroughly either originally or on appeal)

Kiewit Infrastructure West Co. v. United States, No. 2019-2125 (Aug. 26, 2020) (reverses prior CoFC decision; contract interpretation of the phrase "environmental impacts"; contractor reasonably interpreted contract as providing that it would not have to perform wetlands analyses (which is one type of environmental impacts analysis) if it intended to dispose of waste at designated government waste disposal sites)

Agility Public Warehousng Co, K.S.C.P v. United States, Nos. 2019-1886, -1887 (Aug. 12, 2020) (vacates prior CoFC decision in part; to trigger the Debt Collection Act's  (DCA) offset provision, a pre-existing, valid debt must first be owed to the United States; in evaluating validity of offset under DCA part of the analysis involves the validity of the United States’ determination that a pre-exiting debt is owed; Government has independent right to recover overpayments of money appropriated by Congress for a specific purpose even where the United States is acting as contract administrator for the Government of Iraq; CoFC erred in failing to address plaintiff's contention that no underlying overpayment had occurred; Government did not afford contractor all protections afforded by DCA prior to offsetting to recoup alleged overpayment)

The Boeing Co. v. United States, No. 2019-2148 (Aug. 10, 2020) (reverses prior CoFC decision; jurisdiction over illegal exaction claims does not require a money-mandating statute; contractor did not waive claim by failing to raise it prior to award because, at that time, agency could not have resolved objection favorably to contractor and it would not have been ripe for judicial review)

Parsons Evergreene, LLC v. Secretary of the Air Force, Nos. 2019-1931, -1975 (Aug. 7, 2020) (contrary to ASBCA's prior decision, task order for construction of two buildings was not a NAFI contract but was made by the Air Force, and ASBCA, therefore, had CDA jurisdiction over appeal involving the contract; contractor failed to timely appeal Board's decision on its payroll claim; ASBCA correctly concluded contractor had not offered sufficient proof of damages under one theory of recovery, and contractor first raised issue too late in request for ASBCA to reconsider its decision; Board erred in limiting contractor's recovery for equitable adjustment--contractor should be awarded the difference between its actual reasonable costs of changed work and what it would have cost had the work remained unchanged)

United States Army Corps of Engineers v. John C. Grimberg Co., No. 2019-1608 (June 9, 2020) (reverses prior ASBCA decision; contractor not entitled to price adjustment for alleged Type I Differing Site Condition because its interpretation of the contract was found to be unreasonable, even if the ASBCAalso found the Government's interpretation to be even less reasonable) 

Electric Boat Corp. v. Secretary of the Navy, No. 2019-1621 (May 19, 2020) (affirms ASBCA's prior decision that contractor's claim was barred by CDA's six-year limitations period which began to run at the time a change of law (that allegedly increased the contractor's costs of performance) became applicable to the contract, not when the Government, much later, denied the contractor's cost proposal for a price adjustment)

Team Hall Venture, LLC, dba Limeberry Frozen Yogurt v. Army and Air Force Exchange Service, No. 2018-2283 (Mar. 12, 2020) (nonprecedential; affirms prior ASBCA decision because unambiguous general release signed by contractor barred "any" claim "for monetary or other relief to this contract")

2019

DAI Global, LLC fka Development Alternatives, Inc. v. Administrator of the United States Agency for International Development, No. 2019-1330 (Dec. 27, 2019) (reverses prior CBCA decision dismissing appeals for lack of jurisdiction due to allegedly defective, uncorrectable CDA claim certification by prime transmitting properly certified CDA claim by sub;  the two documents together constituted a defective certification which is correctable according to the CDA and the Board's decision to the contrary was based on language in a draft of the statute that had specifically been deleted from the enacted version)

Secretary of Defense v. Northrop Grumman Corp., Nos. 2018-1945, 2018-1990 (Nov. 15, 2019) (denies Government's appeal from prior ASBCA quantum decision because substantial evidence supports ASBCA's conclusion that the Government had suffered no damages from contractor's noncompliance with accrual methodology required by FAR 31.205-6(o) because negative amendment to contractor's PRB plans effectively eliminated the disputed PRB costs from its transition obligation such that those costs were never and will never be charged to the Government)

Guarantee Co. of North America USA v. Ikhana, LLC, No. 2018-1394 (Oct. 29, 2019) (affirms ASBCA decision that surety lacks standing to intervene and replace appellant in Board appeal because the surety could not have brought the original complaint on its own since the appeals were taken before the surety entered into a settlement agreement with the Government)

Raytheon Co. v. Secretary of Defense, No. 18-2371 (Oct. 18, 2019) (affirms prior ASBCA decision that salary costs for lobbying activities are expressly unallowable under FAR § 31.205-22)

Calloway Manor Apartments, Ltd., et al. v. United States, No. 2018-1926 (Oct. 2, 2019) (because Appellants did not expressly or impliedly assign the Government their accrued claims for breach of contract based on the prepayment right, Appellants retain the legal right to pursue those claims and have established standing. We, therefore, reverse the Claims Court’s decision that Appellants lack standing and remand for the court to consider the merits of that claim)

Hejran Hejrat Co. Ltd. v. United States Corps of Engineers, No. 2018-2206 (July 17, 2019) (reverses prior ASBCA decision; contractor's submission to Contracting Officer after a years-long dispute, although styled an "REA," alerted the Contracting Officer to basis and sum certain amount claimed, included a certification (albeit defective), and elicited a "final determination" from the Contracting Officer and, thus, was a "claim" over the appeal of which the Board had jurisdiction)

Bechtel National, Inc. v. United States, No. 2018-2055 (July 16, 2019) (affirms prior CoFC decision holding that CAFC precedent in Geren v. Tecom precluded reimbursement of costs that Bechtel incurred in defending two sexual and racial discrimination and retaliation suits brought by former employees)

Secretary of the Army v. Kellogg Brown & Root Services, Inc., No. 2018-1022 (July 9, 2019) (nonprecedential; affirms ASBCA's decision awarding contractor breach of contract damages in the form of costs for private security forces after Government failed to fulfill its contractual obligations to provide security for contractor's employees in Iraq war zone; Board had jurisdiction over contractor's claim because it was an affirmative defense to Government's prior material breach of the contract in withholding costs incurred by contractor in hiring private security forces; Board properly determined that interest should begin to run from dates contractor submitted properly certified quantum claims to Contracting Officer--no requirement that a contractor must state in a claim the legal theory upon which it ultimately recovers to start the running of interest)

Park Properties Assocs., L.P., Valentine Properties Assocs., L.P. v. United States, Nos. 2017-2279, 2017-2344 (Feb. 19. 2019) (reverses prior CoFC decision; where HUD contracted with state housing authority agency and then, in separate instrument (naming only state agency and landlords as parties), state agency contracted with landlords, HUD was not in privity of contract with landlords and, therefore, CoFC lacked jurisdiction to entertain breach of contract suit by landlords against HUD)

Premier Office Complex of Parma, LLC v. United States, No. 2018-1231 (Feb. 19, 2019) (contract interpretation; affirms prior CoFC decision granting summary judgment in favor of the Government; while provision of basic lease document may be ambiguous, language of Amendment #1 to lease agreement is not and requires Level II Security for the "Project," i.e., the entire project)

St. Bernard Parish Government v. United States, No. 2018-1204 (Feb. 15, 2019) (affirms CoFC's decision that it lacked jurisdiction over breach of contract claim under Cooperative Agreement with Natural Resources Conservation Service, which should have been handled in District Court following exhaustion of administrative remedies in Department of Agriculture)

 

2018

Avant Assessment, LLC v. Secretary of the Army, No. 2018-1235 (Nov. 9, 2018) (affirms ASBCA decision rejecting contractor's appeal, specifically Board's refusal to permit contractor to admit or utilize voluminous, unauthenticated, tardily submitted documents concerning allegedly improper rejections of contract items by Government)

K-Con, Inc. v. Secretary of the Army, No. 2017-2254 (Nov. 5, 2018) (affirms prior ASBCA decision; contractor failed to timely object prior to contracting to patent ambiguity in solicitation concerning whether contracts were construction contracts and, therefore, cannot claim they are not construction contracts; bonding requirements were incorporated in construction contracts under Christian doctrine by operation of law) 

Agility Logistics Services Co. KSC v. Mattis, No. 2015-1555 (Apr. 16, 2018) (affirms ASBCA's prior decision that it lacked CDA jurisdiction over appeals because neither the underlying contract nor the task orders at issue were made by an executive agency of the United States and no subsequent action made the Government a party to either the contract or the task orders; the CAFC has no appellate jurisdiction over ASBCA's determination that its Charter did not provide it with jurisdiction over the appeals)

Meridian Engineering Co. v. United States, No. 2017-1584 (Mar. 20, 2018) (appeal from two prior CoFC decisions: Meridian 1 and Meridian 2; affirms CoFC's prior holdings that: (i) only contractor's breach-of-contract and breach-of-good-faith-and-fair-dealing claims presented viable causes of action, (ii) contractor failed to establish elements of Type I Differing Site Conditions claim because subsurface conditions of which it complained were reasonably foreseeable, and (iii) contractor's defective specification claim was essentially the same as its differing site conditions claim; reverses CoFC's prior holdings that: (i)  contractor's flood control event claim was barred by an accord and satisfaction (because CoFC did not consider all the evidence that might have precluded such a finding),  and (ii)  Government was entitled to withhold payments for unsatisfactory progress under FAR 52.232-5, barring contractor's claim for unpaid contract quantities (because (a) the cited clause only applied to progress payments, (b) there was no proof of unsatisfactory progress, and (c) there was no analysis of the parties' conflicting calculations of the appropriate amount of any set-off)

Securiforce International America, LLC, Nos. 2016-2589, 2016-2633 (Jan. 17, 2018) (affirms CoFC's prior decisions (i) upholding partial T for D and (ii) denying plaintiff's motions for sanctions, but vacates portion of CoFC's decision finding jurisdiction over claim for declaratory judgment that partial T for C had breached contract because proper remedy for breach claim would have been breach damages, not equitable relief)

 

2017

Lee's Ford Dock, Inc. v. Secretary of the Army, No. 2016-2308 (Aug. 2, 2017) (lease allowing contractor to operate marina on leased premises was a contract "for the disposal of personal property" under 41 U.S.C. § 7102(a)(4) and, therefore, was covered by CDA; no jurisdiction over contractor's reformation claim based upon misrepresentation because it was different from the claim presented to the Contracting Officer, which was based on mutual mistake; affirms Board's rejection of contractor's breach claim because contract clearly gave Government right to manipulate lake's water level "in any manner whatsoever")

Call Henry, Inc. v. United States, No. 2016-1732 (Apr. 28, 2017) (affirms CoFC decision dismissing breach-of-contract claim because Government has no contractual obligation to reimburse pension withdrawal liability costs incurred pursuant to Multi-Employer Pension Plan Amendment Act of 1980)

Northwest Title Agency, Inc. v. United States, No. 2016-2158 (Apr. 28, 2017) (affirms CoFC decision that contracts unambiguously precluded contractor providing closing services from charging closing fees to homebuyers and, therefore, extrinsic evidence of trade practice could not be used to vary the plain meaning)

Agility Public Warehousing Co. KSCP, FKA Public Warehousing Co. K.S.C. v. Mattis, No. 2016-1265 (Apr. 4, 2017) (affirms ASBCA's decision that Government did not breach the express terms of the contract but remands case to ASBCA to consider contractor's claims for constructive change and breach of the implied duty to cooperate)

Agility Defense & Government Services, Inc. v. United States, No. 2016-1068 (Feb. 6, 2017) (contrary to CoFC's findings, evidence supported contractor's contentions that: (i) Government had provided inadequate or negligent estimate, and (ii) contractor had relied on the faulty estimates)

2016

 

Rocky Mountain Helium LLC v. United States, No. 2016-1278 (Nov. 16, 2016) (affirms CoFC's holding that suit challenging 2004 termination of helium extraction contract is untimely under six year limitations period of 28 U.S.C. 2501; reverses CoFC's holding that Settlement Agreement was not "money-mandating" under Tucker Act and, therefore, that CoFC lacked jurisdiction over claim for breach of it)

Pacific Gas and Electric Co., et al., v. United States, No. 2015-5082 (Oct. 3, 2016) (affirms CoFC's dismissal of breach of contract suit because plaintiffs do not have privity of contract with Government and, therefore, lack standing)

Guardian Moving Storage v. United States, No. 2015-5132 (Aug. 22, 2016) (nonprecedential; affirms prior CoFC decision; protest against corrective action was based on flawed assumption that protester's proposal was acceptable and that no corrective action was necessary) 

Zafer Taahhut Insaat ve Ticaret A.S. v. United States, No. 2015-5083 (Aug. 17, 2016) (affirms CoFC decision; no evidence Government denied request for time extension, which is a required element of constructive acceleration claim, and contractor failed to establish Government's negotiations with Pakistan to re-open one contract route amounted to fault on the part of the Government establishing a constructive change)

Western States Federal Contracting, LLC v. VA , No.  2016-1042 (July 15, 2016) (nonprecedential; reverses CBCA's dismissal of appeal for lack of jurisdiction because, even though corporate appellant lacked standing at time it initially filed its appeal to CBCA (and still lacked good standing at time appeal originally dismissed), that original dismissal was vacated by the CAFC and the company is now in good standing)

Laguna Construction Co. v. Ashton Carter, No. 2015-1291 (July 15, 2016) (affirms ASBCA decision that contractor's Chief Operating Officer's guilty plea re acceptance of kickbacks from subcontractors demonstrated a prior material breach of the "Allowable Cost and Payment" clause of the contract at issue and was a defense to the contractor's claim for costs disapproved by DCAA audit) 

Sheridan Transportation Systems, Inc. v. GSA, No. 2015-1858 (June 9, 2016) (nonprecedential; court lacks jurisdiction over an appeal from a CBCA decision concerning dispute arising under Transportation Act (31 U.S.C. 3726) rather than CDA)

Northrop Grumman Computing Systems, Inc. v. United States, No. 2015-5074 (May 24, 2016) (affirms CoFC's decision that contractor failed to establish any damages as a result of Government's alleged breach of delivery order (by allegedly failing to use its best efforts to secure funding for the option years) because, without notice to the Government, the contractor had assigned all its rights under the delivery order to a third party in exchange for a payment that equaled its expected profit from the full term of the order, including options)

Kellogg Brown & Root Services, Inc. v. Murphy, No. 2015-1148 (May 18, 2016) (reverses ASBCA decision; for purposes of CDA's six year limitations period for submission of claim, contractor's claim sponsoring subcontractor's termination claim did not "accrue" until it had developed sufficiently to be presented in a sum certain) 

DG21, LLC v. Mabus, No. 2015-1930 (May 6, 2016) (affirms ASBCA decision denying contractor's claim because contractor, in agreeing to pay prevailing rate for fuel, had assumed risk of rising fuel prices, and those rising prices were not a change to the contract)

Yasmin Saighi v. GSA, No. 2015-8059 (Apr. 12, 2016) (nonprecedential; affirms CBCA holding that denied request for refund by purchaser because auction item was not misdescribed and purchaser failed to comply with procedural requirements for establishing claim)

System Fuels, Inc., et al., v. United States, Nos. 2015-5094, -5095 (Apr. 4, 2016) (reverses CoFC and holds contractors are entitled to recover costs of loading spent nuclear fuel in storage casks as element of damages for Government's partial breach of spent nuclear fuel contracts)

SUFI Network Services, Inc. v. United States, No. 2015-5151 (Mar. 29, 2016) (Government has no right to appeal ASBCA decision in Wunderlich Act case)

Guardian Angels Medical Service Dogs, Inc. v. United States, No. 2015-5058 (Jan. 8, 2016) (Contracting Officer's request for additional information from contractor after it had requested reconsideration of her prior decision terminating contract for default meant original decision was not final and did not become so until she subsequently informed contractor she would not reconsider her decision)

2015

Fidelity and Guaranty Insurance Underwriters, Inc. v. United States, No. 2015-5036 (Nov. 6, 2015) (affirms CoFC's prior decision that it lacked Tucker Act jurisdiction over suit by general liability insurer claiming to be an equitable subrogee of a prime contractor, but without any responsibility for contract performance or obligation to the Government)

Bruce E. Zoeller v. McHugh, No. 2015-1516 (Sep. 17, 2015) (nonprecedential; affirms ASBCA's denial of appellant's requests for discovery sanctions and a default judgment against the Government for alleged violations of a discovery order)

McHugh v. Kellogg Brown & Root Services, Inc., No. 2015-1053 (Sep. 15, 2015) (nonprecedential; affirms portion of ASBCA decision finding that government claim against contractor barred by six-year limitations period where a contractor submission contained sufficient information to start running of limitations period; reverses Board conclusion that contract prohibition against armed employees did not apply to situation where contractor hired private security firms with armed employees)

JRS Management v. Lynch, No. 2014-1834 (June 16, 2015) (in denying contractor's claims, CBCA erred in treating Government's motion to dismiss as motion for summary judgment without prior notice, resolving disputed factual issues against the contractor)

Yurok Tribe v. Dept. of Int., No. 2014-1529 (May 8, 2015) (affirms CBCA's dismissal of case because no contract had yet been formed between plaintiff and Government)

Allen Engineering Contractor, Inc. v. United States, Nos. 2014-5094, et al. (May 7, 2015) (nonprecedential; upholds CoFC's dismissal of complaint seeking to overturn default termination because plaintiff did not allege any plausible excuses for its material breach of contract by failing to provide valid performance and payment bonds)

SUFI Network Services, Inc. v. United States, Nos. 2014-5032, -5033 (Apr. 24, 2015) (vacates CoFC's denial of claims for overhead and profit on claim preparation expenses as elements of breach of contract claims)

Montano Electrical Contractor v. United States, No. 2014-5133 (Apr. 13, 2015) (affirms prior CoFC decision dismissing direct claim by subcontractor for lack of subject matter jurisdiction and refusing to transfer claim sounding in tort to district court)

CCI, Inc. v. McHugh, No. 2014-1470 (Apr. 10, 2014) (affirms ASBCA's prior decision that contractor did not establish elements of Type I differing site condition claim)

G4S Technology LLC v. United States, No. 2014-5078 (Mar. 6, 2015) (affirms CoFC's prior decision that subcontractor was not intended third party beneficiary of prime contract)

EM Logging v. Dept. of Agr., No- 2014-1227 (Feb. 20, 2015) (reverses CBCA decision because evidence did not establish "a pattern of activity that demonstrates flagrant disregard for the terms of this contract" as required by the contract's "Termination for Breach" clause)

K-Con Building Systems, Inc. v. United States, No. 2014-5062 (Feb. 12, 2015) (affirms prior CoFC decisions that (i) liquidated damages provision was enforceable; (ii) contractor had failed to provide timely notice of alleged changes in accordance with the "Changes" clause; and (iii) court lacked jurisdiction over contractor's claim for time extension because it had not been first presented to the Contracting Officer for decision)

Jacqueline R. Sims, LLC, DBA JRS Management v. United States, No. 2014-5076 (Jan. 27, 2015) (affirms CoFC's prior decision that, although contracts both contained flaws in language, both parties performed as if they intended to be bound; although regulations did not require Government to prepare past performance evaluations (PPEs) for contracts under micro-purchase threshold, Government had discretion to do so; negative PPEs based on contractor's failure to provide significant portions of required services did not  breach Government's obligation of good faith and fair dealing) 

DayDanyon Corp. v. Department of Defense, No. 2014-1507 (Jan. 9, 2015) (nonprecedential; affirms ASBCA's prior decision that contract unambiguously gave the Government two years within which to order the guaranteed minimum quantity)

2014 

Sikorsky Aircraft Corp. v. United States, No. 2013-5096, 5099 (Dec. 10, 2014) (affirms CoFC's prior decision that contractor's allocation of costs to government versus commercial contracts using direct labor base did not violate CAS 418; CDA statute of limitations is not jurisdictional)

Veridyne Corp. v. United States, Nos. 2013-5011, 5012 (July 15, 2014) (reverses CoFC's quantum meruit award to contractor and affirms the award of penalties to the Government under the False Claims Act and Contract Disputes Act); see prior CoFC decisions: 1, 2, 3   

Sacramento Municipal Utility district v. United States, Nos. 2013-5086, 6087 (June 20, 2014) (nonprecedential spent nuclear fuel case; reverses prior CoFC decision in part; determination of damages)

SUFI Network Services, Inc. v. United States, No. 2013-5039, -5040 (May 29, 2014) (remands several issues of alleged lost revenues to the ASBCA for reconsideration and further findings)

Shell Oil Co., et al. v. United States, No. 2013-5051 (Apr. 28, 2014) (reverses CoFC decision; avgas contracts required Government to indemnify contractors for CERCLA clean-up costs)

Lakeshore Engineering Services, Inc. v. United States, No. 2013-5094 (Apr. 11, 2014) (affirms prior CoFC decision; fixed-price contract placed risk of future cost increases on contractor)

Raytheon Co. v. United States, Nos. 2013-5004, -5006 (Apr. 4, 2014) (affirms prior CoFC decision; segment closing adjustments are not pension costs subject to the timely funding requirement of FAR 31-205.6(j); Government bears burden of proof that contractor's accounting practices do not comply with CAS; no jurisdiction over Government's claim for downward equitable adjustment because there was no Contracting Officer's decision concerning that claim)

Century Exploration New Orleans, LLC and Champion Exploration, LLC v. United States, No. 2013-5073 (Mar. 14, 2014) (affirms Court of Federal Claims decision that imposition of requirements in revisions to governing regulations issued after lease was executed was not a breach of the lease)

Metcalf Construction Co. v. United States, No. 2013-5041 (Feb. 11, 2014) (vacates prior CoFC decision because proving breach of implied duty of good faith and fair dealing does not require the plaintiff to establish that the Government's action were specifically targeted to reappropriate a benefit guaranteed by the contracts)

Crewzers Fire Crew Transport, Inc. v. United States, No. 2013-5104, -5105(Feb. 6, 2014) (affirms CoFC decision that BPA is not a binding contract that gives rise to Tucker Act jurisdiction)

Kellogg Brown & Root Services, Inc. v. United States, No. 2013-5030 (Feb. 3, 2014) (affirms CoFC's determination that costs approved by contractor in subcontractor's change order proposal were not reasonable as a result of contractor's gross negligence in approving the proposed costs)

Bell/Heery, A Joint Venture v. United States, No. 2013-5002 (Jan. 7, 2014) (affirms CoFC's dismissal of suit because "Permits and Responsibilities" clause placed total responsibility on contractor to comply with requirements for obtaining state environmental permit)

Estes Express Lines v. United States, No. 2013-5056 (Jan. 3, 2014) (bill of lading sufficient to establish privity of contract between motor carrier and Government)

2013

White Buffalo Construction, Inc. v. United States, No. 2012-5045 (Nov. 1, 2013) (nonprecedential; Government's decision shortly before trial to convert default termination to T for C mooted plaintiff's claim for attorneys fees under EAJA)

Rockies Express Pipeline LLC v. Salazar, Nos. 2012-1055, -1174 (Sep. 13, 2013) (CBCA incorrectly limited contractor's damages after government breach of contract; contractor entitled to damages through end of contract term)

Kellogg Brown & Root Services, Inc. v. United States, No. 2012-5106, -5115 (Sep. 5, 2013) (CoFC erred in not imputing contractor's employees' actions to contractor for purposes of Government's counterclaim under Anti-Kickback Act; otherwise, affirms decision of CoFC, except its calculation of base fee)

General Dynamics Corp. v. Sec'y of Defense, No. 2012-1249 (May 9, 2013) (affirms ASBCA decision contractor's use of a partial-year asset valuation in computing its retirement plan forward pricing rates was noncompliant with CAS 412)

Entergy Nuclear Fitzpatrick, LLC v. United States, No. 2012-5059 (Apr. 2, 2013) (affirms Court of Federal Claims decision in Spent Nuclear Fuel case; unavoidable delays clause does not limit Government's damages)

Haddon Housing Associates, Limited Partnership, et al. v. United States, No. 2012-5046, -5060 (Mar. 22, 2013) (reverses Court of Federal Claims decision in part--prevention doctrine did not excuse plaintiff's failure to timely request rent adjustments under HUD HAP contracts)

Christine Baldridge v. GPO, No. 2012-6001 (Mar. 12, 2013) (nonprecedential; affirms GAO Contract Appeals Board decision denying contractor's claim because contract unambiguously called for item contrary to her interpretation and, even if it had been ambiguous, it would have been patently so, which would have required her to inquire about its meaning before bidding)

Sharp Electronics Corp. v. McHugh, No. 2012-1299 (Feb. 22, 2013) (affirms ASBCA decision that, under FAR 8.406-6, only GSA Contracting Officer has authority to decide dispute involving interpretation of FSS contract provisions and that ordering agency Contracting Officer lacks such authority, even where dispute also involves purchase order provisions)

Northrop Grumman Computing Systems v. United States, No. 2011-5124 (Feb. 19, 2013) (reverses Court of Federal Claims; contractor's letter, despite omitting  information concerning third-party financing arrangements related to Anti-Assignment Act issues, gave Contracting Officer adequate notice of amount and basis of claim and, therefore, was sufficient under CDA)

2012 

Chu v. The Boeing Co., No. 2011-1304, -1317 (Nov. 20, 2012) (nonprecedential; affirms prior CBCA decisions regarding allowability of defense costs; although Board incorrectly determined it did not have power to apportion costs of litigation with mixed results, no need to remand because apportionment would not have been appropriate in this case)

Peter C. Nwogu, dba Environmental Safety Consultants, Inc. v. United States, No. 2011-5015 (Oct. 31, 2012) (nonprecedential; CDA gives  Court of Federal Claims jurisdiction to enforce a monetary judgment rendered by the ASBCA)

KD1 Development, Inc. v. GSA, No. 2012-1160 (Oct. 23, 2012) (nonprecedential; reverses CBCA; ambiguity in lease agreement as to whether operating costs were included in base rental rate is latent and, therefore, must be construed against the Government)

Bowers Investment Co., LLC v. United States, No. 2011-5102 (Oct. 15, 2012) (affirms CoFC's dismissal of claims for unpaid rent as based on same transactional facts as, and therefore precluded by, prior decision by CBCA)

Tip Top Construction, Inc. v. Donahoe, No. 2011-1509 (Sep. 19, 2012) (reverses PSBCA; consultant and attorney costs were recoverable because they were reasonable contract administration costs incurred in connection with negotiating quantum of change and not for prosecution of CDA claim) 

Scott Timber Co. V. United States, No. 2011-5092 (Sep. 5, 2012) (reverses decision by Court of Federal Claims and holds (i) Government could not have breached the covenant of good faith and fair dealing by its pre-award conduct of failing to disclose information to contractor because the covenant does not exist until the contract is signed; and (ii) Government did not unreasonably lengthen contract suspension by unduly delaying actions that caused suspensions because suspensions were not "specifically targeted" at delaying Scott's contracts and did not reappropriate any benefit guaranteed by the contracts, since the contracts contained no guarantee that performance would not be interrupted)

Kansas City Gas and Electric Co., et al. v. United States, Nos. 2011-5044, -5045 (July 12, 2012) (breach of Standard Contract for spent nuclear fuel; calculation of damages; costs associated with researching alternative spent nuclear fuel and radioactive waste storage 
options; overhead costs; reduction of damages by mitigation activities)

Vermont Yankee Nuclear Power Corp. v. United States, Nos. 2011-5033 et al. (June 13, 2012) (spent nuclear fuel case; assignment of claims; legal and lobbying fees as foreseeable damages; costs of disposing of contaminated material discovered due to the breach and the characterization of spent fuel moved to dry storage; cost of capital to fund mitigation activities; capital suspense loader overhead costs; Resource Code 19 payroll loader overhead costs)

FloorPro, Inc. v. United States, No. 2011-5116 (May 31, 2012) (reverses Court of Federal Claims and holds contractor's claim barred by CDA's statute of limitations)

Englewood Terrace Limited Partnership v. United States, Nos. 2011-5072, -5073 (May 2, 2012) (nonprecedential; remands case to CoFC for recalculation of lost profit award following breach because lower court did not subtract costs saved by reason of breach)

Parsons Global Services, Inc. v. McHugh, No. 2011-1201 (Apr. 20, 2012) (affirms ASBCA decision that request for subcontractor overhead costs submitted by prime two years after termination for convenience was "routine" and, therefore, not a claim within the meaning of the CDA)

The Minesen Co. v. McHugh, No. 2010-1453 (Mar. 2, 2012) (enforces provision in "Disputes" clause of NAFI contract stating ASBCA's decision on any appeal would be final and unreviewable)

Pacific Gas & Electric Co. v. United States, No. 2010-5123 (Feb. 21, 2012) (spent nuclear fuel; affirms damages award by Court of Federal Claims in prior decision favor of plaintiff)

The DIRECTV Group, Inc. v. United States, No. 2010-5031 (Jan. 26, 2012) (affirms CoFC's decision re appropriate segment closing adjustments under CAS 413 when sale of segment involves transfer of defined benefit pension plan)

 

2011

South Fuels, Inc., et al. v. United States, Nos. 2010-5116, -5117 (Jan. 19, 2012) (spent nuclear fuel; affirms CoFC's (i) denial of claim for cost of borrowed funds and (ii) causation analysis and revised award of nominal damages; and reverses CoFC's denial of overhead costs) 

Engage Learning, Inc., v. Salazar, No. 2011-1007 (Oct. 5, 2011) (reverses CBCA's summary dismissal of an appeal for lack of subject matter jurisdiction because, after the contractor initially pled that its appeal involved a contract covered by the CDA, the CBCA made summary conclusions about the credibility of evidence as to the existence of a contract) 

Boston Edison Co., et al. v. United States, Nos. 2010-5136, -5137 (Sep. 28, 2011) (spent nuclear fuel case; interest on loans for mitigation efforts is not recoverable; overhead costs on such efforts are recoverable; costs avoided by reason of breach must be accounted for)

Systems Development Corp. v. McHugh, No. 2011-1092 (Sep. 26, 2011) (affirms ASBCA's dismissal for lack of jurisdiction because the contractor failed to appeal termination settlement cost claim to Board within 90 days of receiving Contracting Officer's decision and failed to submit equitable adjustment claims within CDA's six-year statute of limitations)

Cardiosom, L.L.C. v. United States, No. 2010-5109 (Aug. 31, 2011) (reverses CoFC and holds court has Tucker Act jurisdiction over contractor's breach of contract claim following termination in accordance with the 2008 amendment to the Medicare Improvements for  Patients and Providers Act)

Todd Construction, L.P. v. United States, No. 2010-5166 (Aug 29, 2011) (affirms CoFC decision that court had CDA jurisdiction to consider contractor's claim that Government gave it unfair performance evaluation but that complaint failed to state claim under Rule 12(b)(6) because, even assuming its allegations were true, there was still basis for concluding Government's evaluation was not arbitrary or capricious)

Southern California Edison Co. v. United States, No. 2010-5147 (Aug. 23,2011) (spent nuclear fuel; affirms CoFC conclusion that indirect costs can be recovered as part of damages for breach)

Lumbermens Mutual Casualty Co. v. United States, No. 2010-5086, -5087 (Aug. 3, 2011) (rights of Miller Act sureties against United States)

Dairyland Power Cooperative v. United States, Nos. 2010-5110, -5111 (June 24, 2011) (spent nuclear fuel case; calculation of damages; "exchange model," overhead and G&A, investment in PFS)

Dominion Resources, Inc., et al. v. United States, Nos. 2009-5031, -5032 (Apr. 25, 2011) (affirms Court of Federal Claims decision that that the Assignment of Claims Act does not prohibit the assignment of existing contract claims in spent nuclear fuel case because the Nuclear Waste Policy Act, 42 U.S.C. § 10222, allows such assignments)

Stockton East Water District, et al. v. United States, No. 2007-5142 (Mar. 18, 2011) (on petition for rehearing, affirms earlier decision remanding case to Court of Federal Claims for limited purpose of determining amount of Government's liability for contract breaches)

Southern Nuclear Operating Co., et al., v. United States, No. 2008-5020 (Mar. 11, 2011) (spent nuclear fuels case; remands damages calculation portion of case to Court of Federal Claims to consider additional discovery or evidence in light of Federal Circuit decision made after original Court of Federal Claims decision)

Mabus v. General Dynamics C4 Systems, Inc., No. (Feb. 4, 2011) (reverses ASBCA decision because Board applied wrong test of equitable estoppel; fact that contractor accepted some emailed delivery orders, when contract required them to be mailed, estops contractor from refusing to perform subsequent, similarly deficient delivery orders)

Frank P. Slattery, Jr., et al. v. United States, No. 2007-5063, -5064, -5089 (Jan. 28, 2011) (Tucker Act jurisdiction exists over claims for breach of contract by the FDIC)

 

2010

Arctic Slope Native Ass'n, LTD. v. HHS, No. 2010-1013 (Dec. 15, 2010) (affirms CBCA decision; contractor not entitled to reimbursement for costs that exceed statutory cap when contract contains explicit "subject to availability of appropriated funds" and "not to exceed" language; Government did not breach contract by failing to request additional appropriations because there was no contractual requirement that it do so)

Norma C. Sullivan and Donald E. Sullivan, v. United States, No. 2010-5091 (Nov. 29, 2010) (nonprecedential; reverses Court of Federal Claims; plaintiffs injured by car driven by Postal Service contractor cannot sue Postal Service for breach of contract as third party beneficiaries for Postal Service's failure to enforce contract provision requiring contractor to obtain additional insurance)

McHugh v. DLT Solutions, Inc., No. 2009-1536 (Sep. 23, 2010) (reverses prior ASBCA decision; following termination of contractor, Government did not replace contracted-for software in violation of Non-Substitution clause in delivery order)

M. Maropakis Carpentry, Inc. v. United States, No. 2009-5024 (June 17, 2010) (CDA; definition of a claim; necessity to comply with CDA requirements when asserting claim as a defense to government claim)

Donley v. Lockheed Martin Corp., No. 2009-1261(June 10, 2010) (affirms ASBCA decision; definition of an "affected CAS-covered contract" within the meaning of FAR 30.602(3)(1993))

Guy W. Parker dba Parker International v. United States, No. 2010-1153 (June 9, 2010--nonprecedential) (affirms dismissal for failure to submit claim to Contracting Officer for decision and for untimely appeal of another claim)

ATK Thiokol, Inc. v. United States, No. 2009-5036 (Mar. 19, 2010) (IR & D costs; "required in the performance of a contract")

Precision Pine & Timber, Inc. v. United States, Nos. 2008-5092, -5093 (Feb. 19, 2010) (reverses Court of Federal Claims and holds Government did not breach either express warranty (because none existed) or duty of good faith and fair dealing in suspending timber harvesting contracts during consultations required by court order in separate litigation)

Francisco Javier Rivera Agredano and Alfonso Calderon Leon v. United States, No. 2008-5114, -5115 (Feb. 17, 2010) (purchase of vehicle at federal "As Is Where Is" auction did not create an implied-in-fact agreement (warranty) by Government that the vehicle did not contain hidden contraband)

Nebraska Public Power District v. United States, No. 2007-5083 (Jan. 12, 2010) (Standard Contract; district court jurisdiction on issue of statutory interpretation)

2009

Oregon Woods, Inc. v. United States, No.  2009-1271 (Dec. 10, 2009) (nonprecedential; affirms CBCA decision upholding default termination on summary judgment because there was a rational basis for the termination and it was not made in bad faith or as a result of an abuse of discretion)

States Roofing Corp. v. Secretary of the Navy, No. 2009-1067 (Dec. 7, 2009) (contract interpretation; reverses ASBCA decision in part because contractor's interpretation was within zone of reasonableness)

Teknowledge Corp. v. United States, No. 2009-5053 (November 3, 2009) (nonprecedential: affirms rejection of contractor's claim because software amortization costs not allocable to contract)

Arctic Slope Native Association LTD v. Secretary of Health and Human Services, No. 2008-1532 (Sep. 29, 2009) (CDA's six year statute of limitations is subject to equitable tolling)

Secretary of Defense v. Raytheon Co., No. 2008-1543 (Sep. 14, 2009) (reverses ASBCA decision that contractor's potential violation of CAS 413 had not caused the Government to pay increased costs and, therefore, that the contractor was not required to pay interest)

Vantage Assocs. v. Sec'y of Defense, No. 2009-1214 (Aug. 7, 2009) (nonprecedential; affirms ASBCA holding denying breach claim based on alleged premature termination of purchase order for default)

LAI Services, Inc. v. Secretary of Defense, No. 2008-1317 (July 24, 2009) (contract interpretation; reverses ASBCA and holds contractor should have been reimbursed for shipment of items at issue under CLIN 002 instead of CLIN 001; determines appropriate method of charging under CLIN 002, an issue not reached by the Board)

Carolina Power & Light Co. v. United States, No. 2008-5108 (July 21, 2009) (partial breach by United States of of contract with utilities to store spent nuclear waste; improper calculation of damages)

Total Procurement Service, Inc. v. Secretary of Defense, No. 2008-1450 (July 17, 2009) (nonprecedential; factual issues only; affirmed because all factual findings supported by substantial evidence)

American Contractors Indemnity Co. v. United States, No. 2008-5188 (June 29, 2009) (surety bond; interpretation of 13 C.F.R. 115.19(e); effective date of amendment to security bond agreement)

Secretary of the Navy v. FloorPro, Inc., No. 2008-1407 (June 26, 2009) (subcontractor claiming to be third party beneficiary of bilateral modification between Government and prime did not have CDA jurisdiction to file claim directly against Government)

Bell BCI Co. v. United States, No. 2008-5087 (June 25, 2009) (reverses parts of Court of Federal  Claims decision because it finds language "attributable to this modification" unambiguous as a bar to certain claims)

Tyler Construction Group v. United States, No 2008-5177 (June 25, 2009) (affirms Court of Federal Claims decision that use of ID/IQ contract on project was appropriate)

McDonnell Douglas Corp. and General Dynamics Corp. v. United States, No. 2007-5111, 5131 (June 2, 2009) (upholds default termination)

Tecom, Inc. v. Secy. of the Army, No. 2008-1171 (May 19, 2009) (defense and settlement costs of private suit for sexual harassment are not recoverable by government contractor unless it can establish the original plaintiff had very little chance of success on the merits)

In Re United States, No. 08-M885 (Mar. 5, 2009) (discovery; deliberative process privilege; unauthorized ex parte contacts)

Daewoo Engineering and Constr. Co., LTD v. United States, No. 2007-5129 (Feb. 20, 2009) (affirms CoFC decision; baseless claim submitted only as a negotiating ploy is fraudulent)

North Hartland, L.L.C. v. United States, No. 2008-5009 (Feb. 2, 2009) (nonprecedential; affirms CoFC holding that plaintiff was not authorized to sue the Government for breach of contract)

Arko Executive Services, Inc., No. 2008-5011 (Jan. 21, 2009) (affirms lower court ruling on services contract; interpretation of the meaning and interaction of the "Option to Extend the Term of the Contract" clause (FAR 52.217-9); the "Option to Extend Services" clause (FAR 52.217-8); and the "Continuity of Services" clause (FAR 52.237-3) )

2008

Conner Brothers Construction Co. v. Geren, No. 2008-1188 (Dec. 31, 2008) (sovereign acts doctrine precludes recovery)

Rothe Development Corp. v. Dept. of Defense, No. 2008-1017 (Nov. 4, 2008)(affirmative action goals and preferences of 10 U.S.C. 2323 are unconstitutional)

Delmarva Power & Light Co. and Atlantic City Electric Co. v. United States, No. 2008-5010 (Sep. 18, 2008) (Government's power to waive prohibition on assignment of claims in Anti-Assignment Act)

Nova Express v. Postmaster General , No  2008-1153(Aug. 14, 2008) (default termination; required insurance policy)

Northrop Grumman Information Technology, Inc. v. United States, No. 2008-5003 (August 5, 2008) (failure to incorporate disputed document into lease agreement; integration clause)

Parker v. United States, No. 2007-5163 (June 4, 2008  nonprecendential) (jurisdiction)

General Injectables & Vaccines, Inc. v. Gates, No. 2007-1119r (June 3, 2008) (petition for rehearing denied; FAR 52.212-4(f) interpreted to mean that unexcused delay of subcontractor is not excusable delay by the prime)

Nova Express v. Postmaster General, No. 2008-1033 (May 8, 2008) (upholding board decision sustaining default termination; nonprecedential)

Phillips/May Corp. v. United States, No. 2007-5139 (Apr. 23, 2008) (res judicata; claim preclusion; splitting claims between board and Court of Federal Claims)

International Technology Corp. v. Secretary of the Navy, No. 2007-1276 (Apr. 18, 2008) (differing site conditions; absence of reliance)

Rick's Mushroom Service, Inc. v. United States, No. 2007-5137 (Apr. 2 2008) (lack of jurisdiction; no contract for procurement of goods or services; claims sounding in tort; implied contract)

General Injectables & Vaccines, Inc. v. Secretary of Defense, No. 2007-1119 (Mar. 2008) (default termination; FAR 52.212-4(f); contractor responsible for fault attributable to its subcontractors)

 

2007

Secretary of the Navy v. Bath Iron Works Corp., No. 2006-1578, -1579  (Oct. 4,2007) (Insurance clause, defect in vessel)

Tesoro Hawaii Corp and Tesoro Alaska Co. v. United States, No. 2007-5022 (Sept. 28, 2007) (Minority preferences programs) 

ConocoPhillips et al v. United States, No. 2007-5004 (Sept. 21, 2007) (Economic Price Adjustment clause)

Ace Constructors, Inc. v. United States, No. 2006-5093 (Sept. 19, 2007) (construction contract; defective specs; differing site conditions)

National American Insurance Co. v. United States, No. 2007-5016 (Aug. 23, 2007) (Miller Act surety bond, subrogation issues) 

Winter v. Cath-dr/Balti, Joint Venture, No. 2006-1359 (Aug. 17, 2007) (express and implied authority; ratification)

J.G.B. Enterprises, Inc. v. United States, No. 2005-5065 (August 2, 2007) (cross-contract setoff of debts)

Comtrol, Inc. v. United States, No. 01-5115 (June 26, 2002) (differing site conditions, defective specifications, breach of implied duties of good faith and fair dealing, cooperation, and noninterference)

International Data Products Corp. v. United States, No. 2006-5083 (June 27, 2007) (convenience termination issues)

Bill Hubbard v. United States, No. 03-5076  (Mar. 20, 2007) (lost profits; EAJA; attorneys fees)

Ryste & Ricas v. Harvey, No. 06-1196 (Feb. 16, 2007) (untimely termination settlement proposal)

North Star Steel Co. v. United States, No. 06-5054 (Feb. 13, 2007) (damages for government breach of contract) 

Bianchi v. United States, No. 06-5042 (Jan. 29, 2007) (CoFC Jurisdiction; timeliness of VECP claim)

Clintwood Elkhorn Mining Co., et al. v. United States, No. 04-5155 (Jan. 22, 2007) (interest recovery on unconstitutional export tax)

Curtis v. United States, No. 06-5107 (Jan. 10, 2007) (jurisdiction over tort and breach claims--nonprecedential)

Schleicher Com. Corrections Ctr. v. Dept. of Justice, No. 06-1215 (Jan. 8, 2007) (tardy DOL wage determination--nonprecedential)

2006

 

Richlin Security Service Co. v. Secretary of Homeland Security, No. 2006-1055 (Dec. 26, 2006) (Equal Access to Justice Act--recovery of paralegal expenses at local market rates)

Night Vision Corp. v. United States, No. 06-5048 (Nov. 22, 2006) (no obligation by Government to enter into a Phase III SBIR program contract with a small business after it successfully completed Phases I and II)

American Capital Corp. and Transcapital Financial Corp. v. FDIC v. United States, Nos. 05-5150, 5152, 5159 (Oct. 30, 2006) (Winstar)

TEG-Paradigm Environmental, Inc. v. United States, No. 06-5007 (Sep. 29, 2006) (offeror's "work plan" submitted in compliance with solicitation's requirements did not become part of contract, did not bind the Government, and did not override specification requirements)

Kimco Realty Corp. and Centereach Mall Assocs. v. United States, No. 05-5181 (June 30, 2006) (nonprecedential; lease interpretation; responsibility for common area maintenance costs)

Medlin Construction Group, LTD v. Harvey, No. 05-1514 (June 1, 2006) (contract interpretation; specification versus drawings; "Order of Precedence" clause; reverses ASBCA summary judgment for government; directs summary judgment for contractor)

Massachusetts Bay Transportation Authority v. United States, No. 05-5017 (Feb. 8, 2006) (nonprecedential; damages; interest)

Jireh Consulting Inc. (dba The Writing Co.) v. United States, No. 05-5040 (Feb. 7, 2006) (nonprecedential; affirms dismissal of Court of Federal Claims case in part because a corporation may not appear pro se)

Information Systems & Networks Corp. v. United States, Nos. 04-5151, -5154 (Feb. 6, 2006) (S corporation's reimbursement of sole shareholder's state income taxes based on dividends she received from corporation was not an allowable cost under government contract)

Jacobs Engineering Group, Inc. v. United States, No. 05-5052 (Jan. 19, 2006) (convenience termination costs; contract interpretation; ambiguity construed against the drafter of the contract)

2005

Long Lane Limited Partnership v. Bibb, No. 05-1036 (Dec. 7, 2005) (nonprecedential; affirms GSBCA's dismissal of appeal from lease termination because contractor did not offer evidence lease was terminated in bad faith)

AST Anlagen – und Sanierungstechnick GmbH v. Secretary of the Army, No. 05-1053 (Dec. 6, 2005) (nonprecedential; affirms ASBCA's denial of contractor's claim for delay damages)

Robert Curtis v. United States, No. 05-5121 (Nov. 14, 2005) (nonprecedential; affirms Claims Court dismissal for failure to prosecute and for failed attempt to substitute individual plaintiff for corporation holding contracts and for failure of corporation to be represented by counsel)

Flexfab, L.L.C. v. United States, No. 05-5018 (Sep. 27, 2005) (affirms CoFC decision because plaintiff did not present evidence that it was an intended third party beneficiary under a government contract or that it had a contract with the Government; therefore, it lacked standing)

Lockheed Martin Corp. v. Secretary of the Navy, No. 04-1461 (Sep. 21, 2005) (affirms ASBCA decision that contractor is not entitled to recover for subcontractor effort in termination settlement)

2004

Campbell Plastics Engineering & Manufacturing, Inc. v. Brownlee, No. 03-1512 (Nov. 10, 2004) (affirms ASBCA decision sustaining right of government to invention after contractor failed to comply with invention disclosure provisions of contract)

England v. The Sherman R. Smoot Corp., No. 03-1461 (Nov. 3, 2004) (vacates ASBCA decision that there was a rebuttable presumption that the Government caused a 51-day delay arising simply from the fact that the Contracting Officer had extended the contract completion date by that amount)

Bruce e. Zoeller v. Brownlee, No. 04-1332 (Oct. 25, 2004) (affirms ASBCA decision that Army's partial termination of lease was proper; authority issues)

England v. Contel Advanced Systems, Inc., No. 04-1006 (Oct. 6, 2004) (reverses ASBCA; holds claim is essentially a claim for interest as a direct cost to the contractor resulting from the Government's alleged breach of contract, which is barred by the "no interest" rule)

Gardiner Kamya & Assocs., P.C. v. Jackson, No. 03-1235 (May 27, 2004) (reverses HUDBCA decision that modification was not premised on agreement to retroactively re-price past work)

Turner Construction Co. v. United States, No. 03-5055 (May 12, 2004) (reverses Court of Federal claims; contract interpretation--contractor's reading of drawings and specifications together was reasonable)

England v. the Swanson Group, Inc., No. 03-1051 (Jan. 9, 2004) (reverses ASBCA decision because contractor failed to submit a CDA "claim" for a decision by the Contracting Officer)

2003

Thompson v. Cherokee Nation of Oklahoma, No. 02-1286 (July 3, 2003) (affirms Department of Interior Board of Contract Appeals decision that Government's failure to pay contract support indirect costs breached contract)

Rumsfeld v. Applied Companies, Inc., 01-1630 (Apr. 2, 2003) (corrects some misstatements in prior decision but otherwise affirms opinion affirming ASBCA decision that DLA breached requirements contract by including negligently-prepared estimates in solicitation)  

Kearfott Guidance & Navigation Corp. v. Rumsfeld, No. 02-1039 (Feb. 25, 2003) (affirms ASBCA decision that contractor could not base its claim for payment on the stepped up valuation of assets under FAR 31.205-52 (1990))

Allegheny Teledyne, Inc., et al. v. United States, Nos. 02-5008, -5009, -5010, -5011 (Jan. 23, 2003) (affirms Court of Federal Claims' decision on pension surpluses or deficits issues with regard to segment closings under CAS 413;  pre-CAS contracts not subject to adjustment)

Eastman Kodak Co. v. Rumsfeld, No. 02-1058 (Jan. 16, 2003) (affirms ASBCA decision that claimed pension costs were not allocable to government contracts under CAS 412 and 413)

Rumsfeld v. United Technologies Corp., Pratt & Whitney, No. 02-1071 (Jan. 15, 2003) (vacates ASBCA decision; under CAS 410, 418 and 420, in allocating G&A, B&P, and IR&D, contractor was required to include a "cost"  for "collaboration parts" in its allocation bases)

2002

Metric Constructors v. United States, No. 02-5086 (Dec. 18, 2002) (contract interpretation; reverses Court of Federal Claims; poorly drafted document did not release prime and Government from subcontractor claims involved in this case)

Fireman's Fund Insurance v. England, No. 00-1420 (Nov. 27, 2002) (affirms ASBCA dismissal of portion of takeover surety's claim for refund of the portion of delay damages covering the time period before it took over the work)

Seaboard Lumber Co. and Capital Development Co. v. United States, No. 01-5097 (Oct. 18, 2002) (affirms Court of Federal Claims allowing government claims against contractors on timber sales contracts)

Johnson Management Group CFC, Inc. v. Martinez, No. 01-1145 (Oct. 17, 2002) (affirms HUDBCA's decision upholding propriety of default termination and deciding claims for damages; Government not bound by clause inserted by Contracting Officer in contract that directly contradicted clear FAR requirements)

AT&T Co. and Lucent Technologies v. United States, No. 01-5044 (Oct. 8, 2002) (affirms Court of Federal Claims decision that Navy's violation of section 8118 of Pub. L. 100-102, which prohibits fixed price contracts for development of major weapons systems absent specific findings by Secretary of Defense, did not void contract or create actionable wrong against (or enforceable interest by) contractor)

Florida Power & Light Co. et al. v. United States, Nos. 02-5012, -5023 (Oct. 4, 2002) (appropriateness of various government charges under uranium enrichment service contracts)

Raytheon Co. v. White, No. 01-1350 (Sep. 24, 2002) (partially affirms and partially vacates ASBCA decision on claims for increased costs under terminated contract)

Robinson and Florida Businessmen's Association, Inc. v. United States, No. 02-5028 (Sep. 24, 2002) (reverses Court of Federal Claims decision on amount of damages for breach of sales agreement because Government did not take appropriate steps to mitigate damages on resale, and, if it had, there would have been none)

International Air Response v. United States, No. 01-5117 (Sep. 4, 2002) (reverses Court of Federal Claims determination that complaint was untimely filed under CDA; Government collaterally estopped from challenging (in CoFC) order by federal district court staying the running of the CDA appeal period?! because the Government chose not to appeal that stay order)

Energy Capital Corp. v. United States, No. 01-5018 (Aug. 14, 2002) (vacates Court of Federal Claims decision; award of lost profits for contract breach was appropriate, but damages should have been calculated using a risk-adjusted discount rate)

Boeing North American, Inc. v. Roche, No. 01-1011 (July 29, 2002) (vacates ASBCA decision disallowing of legal costs contractor incurred in defending shareholder derivative suit, because the ASBCA applied the wrong legal standard and did not consider the contractor's likelihood of prevailing on the merits of that suit; on remand, ASBCA may allow costs only if it finds plaintiff's had very little likelihood of prevailing on the merits of the suit)

White v. Edsall Construction Co., No. 01-1628 (July 2, 2002) (implied warranty of design specifications; affirms ASBCA decision that general disclaimer in design drawing did not shift risk of design defects to contractor)

United Pacific Insurance Co. v. Roche, No. 01-1242 (June 27, 2002) (dismisses appeal from ASBCA,  without prejudice, for lack of jurisdiction because the Board's decision was not yet "final")

Hercules Inc. v. United States, No. 01-5103 (June 5, 2002) (proper handling of tax refunds to contractor; CAS 406 and 410 are not inconsistent with the FAR "Allowable Cost and Payment," "Taxes," and "Credits" clauses--leave granted for stay pending appeal to Supreme Court)

Varilease Technology Group, Inc. v. United States, No. 01-5114 (May 7, 2002) (affirms Court of Federal Claims decision that Government did not breach ordering requirements in option period in ID/IQ contract because exercising option did not convert contract to to a requirements contract)

Ridge Runner Forestry v. Veneman, No. 01-1233 (Apr. 18, 2002) (affirms AGBCA decision dismissing appeal for lack of jurisdiction because no underlying contract had been formed; "Tender Agreement" were illusory promises that did not bind the Government to order services from appellant)

Aerojet Solid Propulsion Co. v. White, No. 01-1140 (May 29, 2002) (defective pricing; affirms ASBCA decision that TINA required contractor to reveal its receipt of additional sealed bids to the Government during price negotiations because it was knowledge one would reasonably expect to affect price negotiations significantly)

The Hunt Construction Group, Inc. v. United States, No. 01-5061 (Mar. 1, 2002) (affirms Court of Federal Claims decision that contract unambiguously required the contractor to pay state and local sales and use taxes; Government not required to notify other bidders of one bidder's mistaken interpretation of solicitation)

Am-Pro Protective Agency, Inc. v. United States, No. 01-5077 (Feb. 26, 2002) (affirms Court of Federal Claims summary judgment in favor of Government that release barred contract claim)

The Xerxe Group, Inc. v. United States, No. 01-5055 (Feb. 4, 2002) (affirms Court of Federal Claims decision that failure to mark each page of unsolicited proposal with restricted rights legend required by FAR is fatal to claim for Government's misuse of proprietary information)

Franklin Pavkov Construction Co. v. United States, No. 01-1010 (Jan 28, 2002) (affirms ASBCA decision on defective specification and defective government-furnished material claims under construction contract)

P.R. Burke Corp. v. United States, No. 01-5001 (Jan. 24, 2002) (affirms Court of Federal Claims holding denying contractor entitlement to delay damages on contract to repair and improve sewage treatment plant; delays caused by contractor's failure to submit a required, conforming plan)

Oman-Fishbach International (JV) v. Pirie, No. 01-1075 (Jan 18, 2002) (affirms ASBCA decision that contract did not shift to Government the responsibility for excess costs caused by actions of Portuguese Armed Forces that limited access to site)

2001

Hughes Communications Galaxy, Inc. v. United States, Nos. 00-5109, -5119 (Nov. 13, 2001) (affirms Court of Federal Claims' calculation and award of damages for Government's breach of contract)

Charles G. Williams Construction, Inc. v. White, No. 01-1074 (Nov. 8, 2001) (vacates ASBCA's rejection of Eichleay claim for delay damages in order for board to more fully explain the rationale for its ruling)

Qualmed Plans for Health of New Mexico, Inc. v. United States, No. 00-5108 (Sep. 24, 2001) (reverses decision of Court of Federal Claims: contractor owes simple interest on amounts of government overpayments under contract incorporating FAR and  Federal Employees Health Benefit Acquisitions Regulations (FEHBAR) re defective pricing)

Robins Maintenance, Inc. v. United States, No. 01-5010 (Sep. 20, 2001) (affirms Court of Federal Claims decision that contractor's knowledge of specification defects at the time it submitted bid for contract precluded recovery for defective specifications; failure to raise other claims in Complaint or in status report to Court of Federal Claims constitutes abandonment of those claims)

Marine Logistics v. England, No. 00-1528 (Sep. 12, 2001) (transfers appeal from ASBCA to District Court because it is wholly maritime case)

American Federation of Government Employees, et al. v. United States, No. 00-5090 (July 23, 2001) (lack of standing to challenge cost comparison under OMB Circular A-76 because challengers are not actual or potential bidders)

Furash & Co. v. United States, No. 00-5084 (June 13, 2001) (affirms Court of Federal Claims decision that it lacked jurisdiction over claim under contract by non-appropriated funds activity)

General Electric Co. v. Delaney, No. 00-1401 (June 1, 2001) (reverses ASBCA decision; correct method of calculating foreign-currency depreciation costs of an affiliate)

UMC Electronics Co. v. United States, No. 00-5046 (May 14, 2001) (affirms Court of Federal Claims finding of fraudulent claim where contractor referred in claim to "actual costs," but used only purchase orders to compute the claim, when most invoices for delivered items were available)

Program and Construction Management Group, Inc. v. Davis, No. 00-1312 (Apr. 19, 2001) (affirms GSBCA on contract interpretation issue; contractor not entitled to compensation for delays)

Insurance Co. of the West v. United States, No. 00-5039 (Mar. 23, 2001) (subrogee, after stepping into shoes of government contractor, is not barred by sovereign immunity from suing Government under Tucker Act)

 

2000

Marathon Oil co. et al. v. United States, No. 97-5146 (Dec. 28, 2000) (government breach of oil and gas exploration contracts)

Jowett, Inc. v. United States, No. 00-5021 (Dec. 13, 2000) (affirms Court of Federal Claims decision that construction contract requirement to insulate air supply ducts was unambiguous)

Giesler and Coniglio, dba Central Park Co. v. United States, Nos. 00-5031, -5032 (Nov. 13, 2000) (reverses Court of Federal Claims and holds that contractor's failure to read specification incorporated by reference in solicitation did not entitle it to relief for failing to provide specified items, and contractor's submission of document after pre-award survey indicating the items it intended to supply did not conform to that spec did not entitle it to relief from the spec)

Ace-Federal Reporters, Inc., et al., No. 99-1528 (Sep. 28, 2000) (reverses GSBCA and holds Government breached multiple award schedule contracts for transcription services whenever agencies ordered services from a non-schedule contractor without having obtained the appropriate waiver; damages for lost profits)

Danzig v. AEC Corp., No.  99-1343 (Sep. 25, 2000) (reverses ASBCA decision that default termination was improper; failure of contractor to respond adequately to Government's request for adequate assurances of timely performance)

Kinetic Builders, Inc. v. Peters, No. 00-1065 (Sep. 25, 2000) (affirms ASBCA's denial of claims for extended jobsite overhead costs)

Rex Systems, Inc. v. United States, No. 99-1527 (Sep. 14, 2000) (affirms ASBCA decision denying contractor claim for interest on termination-for-convenience settlement amount because parties had not reached impasse in settlement negotiations and, therefore, letter to TCO was not a CDA claim requesting a final decision)

Freightliner Corp. v. Caldera, No. 99-1217 (Sep. 6, 2000) (affirms ASBCA that option exercise by Government did not violate option clause and, therefore, did not entitle contractor to equitable adjustment)

Maine Yankee Atomic Power Co. et al. v. United States, Nos. 99-5138, -5139, -5140 (Aug. 31, 2000) (government breach of Standard Contract for disposal of nuclear waste)

Northern States Power Co. v. United States, No. 99-5096 (Aug. 31, 2000) (government breach of Standard Contract for disposal of nuclear waste)

Essex Electro Engineers, Inc. v. Danzig, No. 99-1480 (Aug. 18, 2000) (reverses portions of ASBCA decision concerning concurrent delay because it did not use proper analysis to apportion delay between Government and contractor)

Sauer, Inc. v. Danzig, No. 99-1206 (July 20, 2000) (appeal from ASBCA; construction contract; labor and equipment inefficiencies; claim for remission of liquidated damages)

Sea-Land Service, Inc. v. Danzig, No. 99-1124 (May 8, 2000) (appeal from ASBCA; proper charges for transportation services under McCumber Amendment)

Herman B. Taylor Construction Co. v. Barram, No. 99-1028 (Feb. 15, 2000) (reverses GSBCA decision sustaining default termination; DOL "consent order" was not a finding of labor noncompliance that would justify default)

 


This website links to resources on the web concerning government contracting. It is not intended to provide legal advice. Moreover, I do not vouch for the completeness, currency, or accuracy of the sites to which it links. If you have comments, suggestions, or corrections, please email me